Tenement: M09-161

View on Landtracker Maps (logon required)

Extracted from MTO on 20-Jun-2026 00:39, last changed 17-Jun-2026.

Tenement Summary

Identifier:M 09/161Type:Mining Lease
Status:LiveDistrict:GASCOYNE M.F.
Lodged:ONLINEArea:313.35000 HA
Purposes:Term:21 Years
Markout:08-Sep-2015 10:35Received:14-Sep-2015 16:27
Commence:25-Feb-2016 Expiry:24-Feb-2037

Holders

Company NameSharesTotal Shares
YANGIBANA JUBILEE PTY LTD40100
WYLOO GASCOYNE PTY LTD60100

Applicants on Receival

Company NameSharesTotal Shares
GASCOYNE METALS PTY LTD70100
MOJITO RESOURCES LIMITED30100

Relationships

Relationship TypeDealingDealing StatusTenementTenement Status
Section 67Conversion 474328RecordedE 09/1049Dead

Shires

Shire NameShire NumberStartArea
UPPER GASCOYNE SHIRE847001-Jun-2016 313.35000 HA

Conditions

#VerTextStartEnd
11All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.25-Feb-2016
21Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.25-Feb-2016
31The Lessee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.25-Feb-2016
41The Lessee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Lease; or
  • registration of a transfer introducing a new Lessee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
25-Feb-2016
51The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform.02-Dec-2020
61Topsoil and vegetation to be removed ahead of mining operations and appropriately stockpiled for later respreading or immediately respread as rehabilitation progresses.02-Dec-2020
71All rubbish and waste will be appropriately managed and disposed.02-Dec-2020
81The Lessee taking all reasonable and practicable measures to prevent or minimise the generation of dust from mining operations.02-Dec-2020
91Where saline water is used for dust suppression, all reasonable measures being taken to avoid any detrimental effects to surrounding vegetation and topsoil stockpiles.02-Dec-2020
101Placement of waste material must be such that the final footprint after rehabilitation will not be impacted upon by pit wall subsidence or be within the zone of pit instability to the satisfaction of the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety.02-Dec-2020
111All mining related landforms and disturbances must be rehabilitated, in a progressive manner where practicable, to ensure they are safe, stable, non-polluting, integrated with the surrounding landscape and support self-sustaining, functional ecosystems or alternative agreed outcome to the satisfaction of the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety.02-Dec-2020
121All activities being carried out in such a manner so as to not have a detrimental effect on the natural water flow through the lease and surrounding areas to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety.02-Dec-2020
131An annual environmental report is to be submitted to the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety, outlining the project operations, minesite environmental management and rehabilitation work undertaken in the previous 12 months and the proposed operations, environmental management plans and rehabilitation programs for the next 12 months. This report is to be submitted each year in:
  • March
02-Dec-2020
143A Mine Closure Plan is to be submitted in the Annual Environmental Reporting month specified in tenement conditions in the year specified below, unless otherwise directed by the Executive Director Resource and Environmental Compliance Division, Department of Energy, Mines, Industry Regulation and Safety. The Mine Closure Plan is to be prepared in accordance with the Department's "Guidelines for Preparing Mine Closure Plans":
  • 2027
14-Apr-2025
142A Mine Closure Plan is to be submitted in the Annual Environmental Reporting month specified in tenement conditions in the year specified below, unless otherwise directed by the Executive Director Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety. The Mine Closure Plan is to be prepared in accordance with the Department's "Guidelines for Preparing Mine Closure Plans":
  • 2024
15-Jan-2024 13-Apr-2025
141A Mine Closure Plan is to be submitted in the Annual Environmental Reporting month specified in tenement conditions in the year specified below, unless otherwise directed by the Executive Director Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety. The Mine Closure Plan is to be prepared in accordance with the Department's "Guidelines for Preparing Mine Closure Plans":
  • 2023
02-Dec-2020 14-Jan-2024
152All mining operations approved by a Mining Proposal submitted on or after 3 March 2020 to meet the environmental outcomes and performance criteria stated in the latest, relevant approved Mining Proposal/s.30-Nov-2021
151All mining operations to meet the environmental outcomes as measured by the performance criteria stated in Table 35 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026.02-Dec-2020 29-Nov-2021
162All ground disturbance approved by a Mining Proposal submitted on or after 3 March 2020 to be undertaken within the disturbance envelope as presented within the latest, relevant approved Mining Proposal/s.30-Nov-2021
161All ground disturbance to be undertaken within the disturbance envelope as represented by the spatial data provided on 17 October 2019 and retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 6920069.02-Dec-2020 29-Nov-2021
172No alteration or expansion of mining operations beyond the activities described within the Activity, and Key Mine Activity tables of the latest, relevant approved Mining Proposal/s unless a subsequent Mining Proposal is submitted, in the form defined in section 70O of the Mining Act 1978, to cover the alteration or expansion, and until such Mining Proposal is approved by the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety.30-Nov-2021
171No alteration or expansion of mining operations beyond the activities detailed in Table 2 and Table 3 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026.02-Dec-2020 29-Nov-2021
182The Lessee to ensure adequate environmental monitoring and analysis is undertaken of activities approved by a Mining Proposal submitted on or after 3 March 2020 to demonstrate the level of achievement of the performance criteria stated in the latest, relevant approved Mining Proposal/s.30-Nov-2021
181The Lessee to ensure adequate environmental monitoring and analysis is undertaken to demonstrate the level of achievement of the performance criteria stated in Table 35 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026.02-Dec-2020 29-Nov-2021
192Management of mine closure to be undertaken in accordance with the latest, relevant approved Mine Closure Plan.30-Nov-2021
191Management of mine closure to be undertaken in accordance with the Mine Closure Plan (Reg ID 83200) "Yangibana Rare Earths Project Mine Closure Plan Revision 8a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807024.02-Dec-2020 29-Nov-2021
202Report any incident arising from mining activities that has caused, or has the potential to cause environmental harm or injury to land, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety, within 24 hours of becoming aware of the occurrence of the incident.30-Nov-2021
201Report any incident arising from mining activities that has caused, or has the potential to cause environmental harm or injury to the land, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety, within 24 hours of becoming aware of the occurrence of the incident.02-Dec-2020 29-Nov-2021
212Report any breach of environmental outcome or performance criteria contained within an approved Mining Proposal submitted on or after 3 March 2020, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety within 24 hours of becoming aware of the occurrence of the breach.30-Nov-2021
211Report any breach of environmental outcome or performance criteria stated in Table 35 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety within 24 hours of becoming aware of the occurrence of the breach.02-Dec-2020 29-Nov-2021

Endorsements

Cond #VerTextStartEnd
11All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program.25-Feb-2016
21Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations.25-Feb-2016
31The Lessee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment.25-Feb-2016
41The Lessee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
  • the grant of the Lease; or
  • registration of a transfer introducing a new Lessee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer.
25-Feb-2016
51The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform.02-Dec-2020
61Topsoil and vegetation to be removed ahead of mining operations and appropriately stockpiled for later respreading or immediately respread as rehabilitation progresses.02-Dec-2020
71All rubbish and waste will be appropriately managed and disposed.02-Dec-2020
81The Lessee taking all reasonable and practicable measures to prevent or minimise the generation of dust from mining operations.02-Dec-2020
91Where saline water is used for dust suppression, all reasonable measures being taken to avoid any detrimental effects to surrounding vegetation and topsoil stockpiles.02-Dec-2020
101Placement of waste material must be such that the final footprint after rehabilitation will not be impacted upon by pit wall subsidence or be within the zone of pit instability to the satisfaction of the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety.02-Dec-2020
111All mining related landforms and disturbances must be rehabilitated, in a progressive manner where practicable, to ensure they are safe, stable, non-polluting, integrated with the surrounding landscape and support self-sustaining, functional ecosystems or alternative agreed outcome to the satisfaction of the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety.02-Dec-2020
121All activities being carried out in such a manner so as to not have a detrimental effect on the natural water flow through the lease and surrounding areas to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety.02-Dec-2020
131An annual environmental report is to be submitted to the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety, outlining the project operations, minesite environmental management and rehabilitation work undertaken in the previous 12 months and the proposed operations, environmental management plans and rehabilitation programs for the next 12 months. This report is to be submitted each year in:
  • March
02-Dec-2020
143A Mine Closure Plan is to be submitted in the Annual Environmental Reporting month specified in tenement conditions in the year specified below, unless otherwise directed by the Executive Director Resource and Environmental Compliance Division, Department of Energy, Mines, Industry Regulation and Safety. The Mine Closure Plan is to be prepared in accordance with the Department's "Guidelines for Preparing Mine Closure Plans":
  • 2027
14-Apr-2025
142A Mine Closure Plan is to be submitted in the Annual Environmental Reporting month specified in tenement conditions in the year specified below, unless otherwise directed by the Executive Director Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety. The Mine Closure Plan is to be prepared in accordance with the Department's "Guidelines for Preparing Mine Closure Plans":
  • 2024
15-Jan-2024 13-Apr-2025
141A Mine Closure Plan is to be submitted in the Annual Environmental Reporting month specified in tenement conditions in the year specified below, unless otherwise directed by the Executive Director Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety. The Mine Closure Plan is to be prepared in accordance with the Department's "Guidelines for Preparing Mine Closure Plans":
  • 2023
02-Dec-2020 14-Jan-2024
152All mining operations approved by a Mining Proposal submitted on or after 3 March 2020 to meet the environmental outcomes and performance criteria stated in the latest, relevant approved Mining Proposal/s.30-Nov-2021
151All mining operations to meet the environmental outcomes as measured by the performance criteria stated in Table 35 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026.02-Dec-2020 29-Nov-2021
162All ground disturbance approved by a Mining Proposal submitted on or after 3 March 2020 to be undertaken within the disturbance envelope as presented within the latest, relevant approved Mining Proposal/s.30-Nov-2021
161All ground disturbance to be undertaken within the disturbance envelope as represented by the spatial data provided on 17 October 2019 and retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 6920069.02-Dec-2020 29-Nov-2021
172No alteration or expansion of mining operations beyond the activities described within the Activity, and Key Mine Activity tables of the latest, relevant approved Mining Proposal/s unless a subsequent Mining Proposal is submitted, in the form defined in section 70O of the Mining Act 1978, to cover the alteration or expansion, and until such Mining Proposal is approved by the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety.30-Nov-2021
171No alteration or expansion of mining operations beyond the activities detailed in Table 2 and Table 3 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026.02-Dec-2020 29-Nov-2021
182The Lessee to ensure adequate environmental monitoring and analysis is undertaken of activities approved by a Mining Proposal submitted on or after 3 March 2020 to demonstrate the level of achievement of the performance criteria stated in the latest, relevant approved Mining Proposal/s.30-Nov-2021
181The Lessee to ensure adequate environmental monitoring and analysis is undertaken to demonstrate the level of achievement of the performance criteria stated in Table 35 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026.02-Dec-2020 29-Nov-2021
192Management of mine closure to be undertaken in accordance with the latest, relevant approved Mine Closure Plan.30-Nov-2021
191Management of mine closure to be undertaken in accordance with the Mine Closure Plan (Reg ID 83200) "Yangibana Rare Earths Project Mine Closure Plan Revision 8a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807024.02-Dec-2020 29-Nov-2021
202Report any incident arising from mining activities that has caused, or has the potential to cause environmental harm or injury to land, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety, within 24 hours of becoming aware of the occurrence of the incident.30-Nov-2021
201Report any incident arising from mining activities that has caused, or has the potential to cause environmental harm or injury to the land, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety, within 24 hours of becoming aware of the occurrence of the incident.02-Dec-2020 29-Nov-2021
212Report any breach of environmental outcome or performance criteria contained within an approved Mining Proposal submitted on or after 3 March 2020, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety within 24 hours of becoming aware of the occurrence of the breach.30-Nov-2021
211Report any breach of environmental outcome or performance criteria stated in Table 35 of the Mining Proposal (Reg ID 83200) "Yangibana Rare Earths Project Mining Proposal Minor and Preliminary works (stage 1 and 2) and Site- Wide Mining Proposal Revision 7a" retained on Department of Mines, Industry Regulation and Safety File No. EARS-MPMCP-83200 as Doc ID 7807026, to the Executive Director, Resource and Environmental Compliance Division, Department of Mines, Industry Regulation and Safety within 24 hours of becoming aware of the occurrence of the breach.02-Dec-2020 29-Nov-2021

Dealings

TypeNumberDetails
Caveat380962Primary Tenements:Lodged against E 09/1049 is now effective against this tenement.Pursuant To:S122CCaveat Type:Consent CaveatCaveat Number:380962,Caveator:ARTEMIS RESOURCES LTDShares Caveated:60/100 shares GASCOYNE METALS PTY LTDRECORDED:00:00 25 February 2016WITHDRAWN:16:15:15 17 September 2019
Extension of Time475775Lodged:15:33:07 12 October 2015Type:SecurityRECORDED:15:33:07 12 October 2015APPROVED:09:25 13 October 2015
Application to Amend493247Lodged:15:15 01 September 2016Amending:Address (Including DTC Details)From:MOJITO RESOURCES LIMITED, C/- RARE EARTH MINERALS PLC, SUITE 3B, PRINCES HOUSE, 38 JERMYN STREET, LONDON, UK, SW1Y 6DN, UNITED KINGDOMTo:MOJITO RESOURCES LIMITED, C/- RARE EARTH MINERALS PLC, SUITE 3B, PRINCES HOUSE, 38 JERMYN STREET, LONDON, SW1Y 6DN, ENGLANDRECORDED:15:15 01 September 2016
Application to Amend526837Lodged:14:50:57 29 March 2018Amending:Address (Including DTC Details)From:Principal Place of Business : GASCOYNE METALS PTY LTD, SAME AS CORRESPONDENCE and DTC :GASCOYNE METALS PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:Principal Place of Business : GASCOYNE METALS PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :GASCOYNE METALS PTY LTD, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:14:50:57 29 March 2018
Withdrawal of Dealing563181Lodged:16:15:15 17 September 2019In respect to:Caveat 380962RECORDED:16:15:15 17 September 2019
Application to Amend673176Lodged:15:24:05 12 April 2023Amending:Address (Including DTC Details)From:Principal Place of Business : YANGIBANA PTY LTD, LEVEL 3, 5 MILL STREET, PERTH, WA, 6000 and DTC :YANGIBANA PTY LTD, YANGIBANA PTY LTD, LEVEL 3, 5 MILL STREET, PERTH, WA, 6000To:Principal Place of Business : YANGIBANA PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxx400 and DTC :YANGIBANA PTY LTD, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxx400RECORDED:15:24:05 12 April 2023
Application to Amend734926Lodged:15:17:42 03 June 2025Amending:NameFrom:YANGIBANA PTY LTDTo:YANGIBANA JUBILEE PTY LTDRECORDED:15:17:42 03 June 2025

Payments

TypeYearReceipt DateReceipt No.MR LodgedAmountRental AreaEffective DateAmt DueDiscrepancy
Rental202724-Feb-2026 11030972$9,200.20313.35000 HA01-Jun-2016 $9,200.20$0.00
Rental202619-Feb-2025 10763031$8,980.40313.35000 HA01-Jun-2016 $8,980.40$0.00
Rental202523-Feb-2024 10512900$8,164.00313.35000 HA01-Jun-2016 $8,164.00$0.00
Rental202415-Feb-2023 10328330$7,536.00313.35000 HA01-Jun-2016 $7,536.00$0.00
Rental202315-Feb-2022 10242929$6,908.00313.35000 HA01-Jun-2016 $6,908.00$0.00
Rental202216-Feb-2021 10183649$6,280.00313.35000 HA01-Jun-2016 $6,280.00$0.00
Rental202124-Feb-2020 10134579$6,217.20313.35000 HA01-Jun-2016 $6,217.20$0.00
Rental202018-Feb-2019 10086248$5,871.80313.35000 HA01-Jun-2016 $5,871.80$0.00
Rental201915-Feb-2018 7158923214$5,526.40313.35000 HA01-Jun-2016 $5,526.40$0.00
Rental201810-Feb-2017 MT-210010932771-DD$5,353.70313.35000 HA01-Jun-2016 $5,353.70$0.00
Rental201714-Sep-2015 525718343442$5,181.00313.35000 HA01-Jun-2016 $5,181.00$0.00

Expenditure

YearForm 5 TypeMin ExpdExp Lodged DateTotal ExpdExemp NoExemp LodgedExemp AmtExemp StatusOutcome DateExploration ActivitiesMining ActivitiesAboriginal SurveyRentAdministrationProspectingStrike Through
2027$31,400.00false
2026$31,400.0022-Apr-2026 $58,739.00$27,665.00$0.00$0.00$24,794.00$6,280.00$0.00false
2025$31,400.0024-Apr-2025 $61,172.00$39,839.00$0.00$0.00$15,053.00$6,280.00$0.00false
2024$31,400.0012-Apr-2024 $48,693.00$31,087.00$0.00$0.00$11,326.00$6,280.00$0.00false
2023$31,400.0024-Apr-2023 $60,912.00$31,366.00$3,679.00$0.00$17,922.00$7,945.00$0.00false
2022$31,400.0021-Apr-2022 $44,529.00$28,707.00$0.00$0.00$12,682.00$3,140.00$0.00false
2021$31,400.0023-Apr-2021 $36,816.00$19,872.00$0.00$0.00$10,695.00$6,249.00$0.00false
2020$31,400.0024-Apr-2020 $23,910.0057684924-Apr-2020 $31,400.00Granted03-Jun-2020 $9,565.00$0.00$0.00$10,462.00$3,883.00$0.00false
2019$31,400.0024-Apr-2019 $42,007.00$31,905.00$0.00$0.00$9,803.00$299.00$0.00false
2018$31,400.0026-Apr-2018 $337,867.39$260,188.19$0.00$12,037.79$9,330.18$56,311.23$0.00false
2017$31,400.0021-Apr-2017 $390,589.84$304,636.46$0.00$5,520.25$15,334.83$65,098.30$0.00false

Native Title Referrals

Referred to Native Title DateReferral TypeCurrent StatusProcedureDetailsObjectionsWater CommentsDetermination AreasClaimsRepresentative Area Bodies
01-Oct-2015 Tenement ApplicationRTN Procedure : Right to Negotiate Cleared - GrantRTN Procedure2015-10-212016-02-21313.1 HA235325S1161734E161km SW'ly of Paraburdoo14GeraldtonYamatji Marlpa Aboriginal Corporation