1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 24-Mar-2006 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 24-Mar-2006 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 24-Mar-2006 | |
4 | 2 | Unless the written approval of the Environment Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Aug-2007 | |
4 | 1 | Unless the written approval of the Director, Environment Division, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 24-Mar-2006 | 22-Aug-2007 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 24-Mar-2006 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 24-Mar-2006 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 47/105 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 24-Mar-2006 | |
8 | 1 | No interference with Geodetic Survey Station C1, CL 12, 36, 39, 41, ANKETEL, SOUTH DIXON, ROEBOURNE 59, 60, 61 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 24-Mar-2006 | |
9 | 1 | No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 24-Mar-2006 | |
10 | 1 | Mining within a radius of 150 metres of any Australian Telecommunications Commission microwave repeater station being confined to below a depth of 60 metres from the natural surface. | 24-Mar-2006 | |
11 | 1 | No interference with the Australian Telecommunications Commission microwave repeater station ray-line. | 24-Mar-2006 | |
12 | 1 | No excavation, excepting shafts, approaching closer to the North West Coastal Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the North West Coastal Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface. | 24-Mar-2006 | |
13 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipelines (referred to in TENGRAPH as PL22, PL40 and PL8R1). | 24-Mar-2006 | |
14 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 11 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
15 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 11 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 24-Mar-2006 | |
16 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 11 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
17 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
18 | 1 | Mining on the Safety Zone established in Condition 11 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
19 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 11 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 24-Mar-2006 | |
20 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 24-Mar-2006 | |
21 | 1 | No mining on a strip of land 60 metres wide with the Robe River Railway Line as the centreline and no materials being deposited or machinery or buildings being erected on such strip of land. | 24-Mar-2006 | |
22 | 1 | Blasting operations being controlled so that no damage or injury can be caused by fly rock, concussion, vibration or other means. | 24-Mar-2006 | |
23 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing mining on Crown Reserve 31115 (Gravel Main Roads Department); Crown Reserve 18571 (Stock Route for Shipping Stock); Crown Reserve 33775 (Recreation and Camping); and any foreshore, seabed or navigable waters. | 24-Mar-2006 | |
| 1 | Consent to Mine on Temporary Reserve 5461H granted subject to: | 24-Mar-2006 | |
24 | 1 | Cancellation of the licence without compensation, upon notice in writing from the Minister responsible for the Mining Act 1978 that the ground within this tenement or any portion thereof is required for public purposes or industrial development. | 24-Mar-2006 | |
25 | 1 | No mining or exploration activities being conducted on Dixon Island without the prior written consent of the Minister responsible for the Mining Act 1978. | 24-Mar-2006 | |
26 | 2 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- "Programme of Works for Mt Anketell Pty Ltd on E47/1462, P47/1043 (EXP:6391)" dated dated 27 March 2007 signed by Warren Gilhome and retained on Department of Industry and Resources File No. T3890/200402;
- "Programme of Work on E47/1462 for MCC Sanjin Mining Pty Ltd" (Reg. ID: 30146) dated 8 March 2011 with revised disturbance table dated 15 June 2011, signed by Henggao Zhang and retained on Department of Mines and Petroleum file No. EARS-POW-30146.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 11-Jul-2011 | |
26 | 1 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- "Programme of Works for Mt Anketell Pty Ltd on E47/1462, P47/1043 (EXP:6391)" dated dated 27 March 2007 signed by Warren Gilhome and retained on Department of Industry and Resources File No. T3890/200402.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 01-Jun-2007 | 10-Jul-2011 |
27 | 1 | The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform. | 01-Jun-2007 | |
28 | 1 | The Licensee arranging lodgement of an Unconditional Performance Bond executed by a Bank or other approved financial institution in favour of the Minister responsible for the Mining Act 1978 for due compliance with the environmental conditions of the lease in the sum of: | 01-Jun-2007 | 20-Oct-2008 |
29 | 1 | All topsoil and vegetation being removed ahead of all mining operations and being stockpiled appropriately for later respreading or immediately respread as rehabilitation progresses. | 11-Jul-2011 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 24-Mar-2006 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 24-Mar-2006 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 24-Mar-2006 | |
4 | 2 | Unless the written approval of the Environment Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Aug-2007 | |
4 | 1 | Unless the written approval of the Director, Environment Division, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 24-Mar-2006 | 22-Aug-2007 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 24-Mar-2006 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 24-Mar-2006 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 47/105 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 24-Mar-2006 | |
8 | 1 | No interference with Geodetic Survey Station C1, CL 12, 36, 39, 41, ANKETEL, SOUTH DIXON, ROEBOURNE 59, 60, 61 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 24-Mar-2006 | |
9 | 1 | No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 24-Mar-2006 | |
10 | 1 | Mining within a radius of 150 metres of any Australian Telecommunications Commission microwave repeater station being confined to below a depth of 60 metres from the natural surface. | 24-Mar-2006 | |
11 | 1 | No interference with the Australian Telecommunications Commission microwave repeater station ray-line. | 24-Mar-2006 | |
12 | 1 | No excavation, excepting shafts, approaching closer to the North West Coastal Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the North West Coastal Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface. | 24-Mar-2006 | |
13 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipelines (referred to in TENGRAPH as PL22, PL40 and PL8R1). | 24-Mar-2006 | |
14 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 11 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
15 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 11 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 24-Mar-2006 | |
16 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 11 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
17 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
18 | 1 | Mining on the Safety Zone established in Condition 11 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer, DoCEP. | 24-Mar-2006 | |
19 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 11 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 24-Mar-2006 | |
20 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 24-Mar-2006 | |
21 | 1 | No mining on a strip of land 60 metres wide with the Robe River Railway Line as the centreline and no materials being deposited or machinery or buildings being erected on such strip of land. | 24-Mar-2006 | |
22 | 1 | Blasting operations being controlled so that no damage or injury can be caused by fly rock, concussion, vibration or other means. | 24-Mar-2006 | |
23 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing mining on Crown Reserve 31115 (Gravel Main Roads Department); Crown Reserve 18571 (Stock Route for Shipping Stock); Crown Reserve 33775 (Recreation and Camping); and any foreshore, seabed or navigable waters. | 24-Mar-2006 | |
| 1 | Consent to Mine on Temporary Reserve 5461H granted subject to: | 24-Mar-2006 | |
24 | 1 | Cancellation of the licence without compensation, upon notice in writing from the Minister responsible for the Mining Act 1978 that the ground within this tenement or any portion thereof is required for public purposes or industrial development. | 24-Mar-2006 | |
25 | 1 | No mining or exploration activities being conducted on Dixon Island without the prior written consent of the Minister responsible for the Mining Act 1978. | 24-Mar-2006 | |
26 | 2 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- "Programme of Works for Mt Anketell Pty Ltd on E47/1462, P47/1043 (EXP:6391)" dated dated 27 March 2007 signed by Warren Gilhome and retained on Department of Industry and Resources File No. T3890/200402;
- "Programme of Work on E47/1462 for MCC Sanjin Mining Pty Ltd" (Reg. ID: 30146) dated 8 March 2011 with revised disturbance table dated 15 June 2011, signed by Henggao Zhang and retained on Department of Mines and Petroleum file No. EARS-POW-30146.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 11-Jul-2011 | |
26 | 1 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- "Programme of Works for Mt Anketell Pty Ltd on E47/1462, P47/1043 (EXP:6391)" dated dated 27 March 2007 signed by Warren Gilhome and retained on Department of Industry and Resources File No. T3890/200402.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 01-Jun-2007 | 10-Jul-2011 |
27 | 1 | The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform. | 01-Jun-2007 | |
28 | 1 | The Licensee arranging lodgement of an Unconditional Performance Bond executed by a Bank or other approved financial institution in favour of the Minister responsible for the Mining Act 1978 for due compliance with the environmental conditions of the lease in the sum of: | 01-Jun-2007 | 20-Oct-2008 |
29 | 1 | All topsoil and vegetation being removed ahead of all mining operations and being stockpiled appropriately for later respreading or immediately respread as rehabilitation progresses. | 11-Jul-2011 | |
Type | Number | Details |
Iron Ore Inclusion | 211364 | Lodged 10:04:00 AM on 28 Oct 2004RECORDED 10:04 AM 28 Oct 2004AUTHORISED 8:30 AM 29 Mar 2006 |
Licence Instrument | 420445 | Lodged:08:30 24 February 2006ISSUED:08:30 24 February 2006 |
Bond | 265878 | Lodged on 09 May 2007 For $22,000.00RECORDED 09 May 2007RETIRED 21 Oct 2008 |
Copy Document | 177H/067 | Lodged 2:15 PM on 15 Jun 2007 in lieu of lost licence document.RECORDED 2:15 PM 15 Jun 2007 |
Caveat | 296942 | Lodged 4:20:00 PM on 07 Aug 2008 pursuant to Section 122A(1)(a) by MCC MINING (WESTERN AUSTRALIA) PTY LTD in respect to 100/100ths shares in the name of MT ANKETELL PTY LTDRECORDED 4:20 PM 07 Aug 2008WITHDRAWN 3:45 PM 11 Sep 2008 |
Bond | 299096 | Lodged 4:20 PM on 07 Aug 2008 For $22,000.00 (Unconditional Performance Bond)RECORDED 3:00 PM 08 Oct 2008RETIRED:13 January 2010 |
Caveat | 299156 | Lodged 2:35:00 PM on 05 Sep 2008 pursuant to Section 122A(2) by PHARLAP HOLDINGS PTE. LIMITED in respect to 100/100ths shares in the name of MT ANKETELL PTY LTDRECORDED 2:35 PM 05 Sep 2008WITHDRAWN 3:45 PM 11 Sep 2008 |
Withdrawal of Dealing | 299924 | Lodged 3:45:00 PM on 11 Sep 2008 withdrawing Caveat 296942RECORDED 3:45 PM 11 Sep 2008 |
Withdrawal of Dealing | 299925 | Lodged 3:45:00 PM on 11 Sep 2008 withdrawing Caveat 299156RECORDED 3:45 PM 11 Sep 2008 |
Caveat | 299935 | Lodged 4:10 PM on 17 Sep 2008 pursuant to Section 122A(2) by PHARLAP HOLDINGS PTE. LIMITED in respect to 100/100ths shares in the name of MCC MINING (WESTERN AUSTRALIA) PTY LTDLeave to Lodge Successive caveat granted by the Warden on 16 Oct 2008
RECORDED 10:00 AM 16 Oct 2008WITHDRAWN:11:15 31 December 2009 |
Application to Amend | 301680 | Lodged 3:39 PM on 10 Oct 2008 amending address of notices to : c/- Austwide Mining TiltIe Management Pty Ltd Post Office Box 1434 WANGARA WA 6947RECORDED 3:39 PM 10 Oct 2008 |
Bond Requirement | 308268 | Requirement Date:21/10/2008Amount:$22,000.00RECORDED:08:59:14 21 October 2008FINALISED:15:18:35 11 July 2011 |
Exemption from Drop-off | 313513 | Lodged:14:50 20 February 2009For relief from the provisions of Section 65/(1)(a)RECORDED:14:50 20 February 2009GRANTED:26 February 2009 |
Withdrawal of Dealing | 337911 | Lodged:11:15 31 December 2009In respect to:Caveat 299935RECORDED:11:15 31 December 2009 |
Caveat | 337919 | Lodged:11:15 31 December 2009Caveat Type:Consent CaveatCaveator:PHARLAP HOLDINGS PTE. LIMITEDShares Caveated:100/100 shares MCC AUSTRALIA SANJIN MINING PTY LTDRECORDED:11:15 31 December 2009 |
Bond | 337921 | Lodged:13:00 31 December 2009Bond Type:Unconditional Performance BondBond Amount:$22,000.00RECORDED:31 December 2009RETIRED - MRF:16 October 2014 |
Conversion | 339249 | Section:S67Application Date:15:45 12 Nov 2009New Tenement:M 47/1436Discontinued due to M 47/1436 Withdrawn 14:14:44 18 September 2014 |
Exemption from Drop-off | 343175 | Lodged:14:30 19 March 2010For relief from the Provisions of Section 65(1)(b)RECORDED:14:30 19 March 2010GRANTED:08 April 2010 |
Application to Amend | 343169 | Lodged:15:35 22 March 2010Amending:AddressFrom:Residential : MCC AUSTRALIA SANJIN MINING PTY LTD, SAME AS CORRESPONDENCE and Correspondance :MCC AUSTRALIA SANJIN MINING PTY LTDLEVEL 4, 50 ST GEORGES TCE, PERTH, WA, 6000, AUSTRALIATo:Residential : MCC AUSTRALIA SANJIN MINING PTY LTD, LEVEL 4, 50 ST GEORGES TCE, PERTH, WA, 6000 and Correspondance :MCC AUSTRALIA SANJIN MINING PTY LTDC/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947RECORDED:15:35 22 March 2010 |
Extension / Renewal of Term | 367778 | Lodged:14:50 17 March 2011Applied For Period:2 YearsRECORDED:14:50 17 March 2011GRANTED:23 March 2011Granted Period:2 YearsTerm Extended To:23/03/2013Licence falls within the "Iron Ore Policy" |
Bond | 375690 | Lodged:16:15 05 July 2011Bond Type:Unconditional Performance BondBond Amount:$50,000.00RECORDED:11 July 2011RETIRED - MRF:16 October 2014 |
Bond Requirement | 376041 | Requirement Date:11/07/2011Amount:$72,000.00RECORDED:08:48:10 11 July 2011FINALISED:08:12 16 October 2014 |
Extension / Renewal of Term | 418486 | Lodged:15:15 07 March 2013Applied For Period:2 YearsRECORDED:15:15 07 March 2013GRANTED:26 March 2013Granted Period:2 YearsTerm Extended To:23/03/2015 |
Caveat | 429347 | Lodged:09:00 20 August 2013Caveat Type:Subject to Claim CaveatCaveator:MT ANKETELL PTY LTD
CAPE LAMBERT IRON ORE LTDShares Caveated:100/100 shares MCC AUSTRALIA SANJIN MINING PTY LTDRECORDED:09:00 20 August 2013WITHDRAWN:15:05 17 July 2014 |
Application to Amend | 437098 | Lodged:10:19:35 12 December 2013Amending:AddressFrom:MCC AUSTRALIA SANJIN MINING PTY LTD, LEVEL 4, 50 ST GEORGES TCE, PERTH, WA, 6000To:MCC AUSTRALIA SANJIN MINING PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, UNIT 6 42 DELLAMARTA ROAD, WANGARA, WA, 6065REJECTED:10:19:35 12 December 2013 |
Extension of Time | 449284 | Lodged:13:04 18 June 2014Type:Stat DecRECORDED:13:04 18 June 2014Extension of time until 4 July 2014 to lodge statutory declaration in support of Appln 446931 for exemption from the prescribed expenditure condition for the year ending 23 March 2014APPROVED:10:37:44 20 June 2014 |
Withdrawal of Dealing | 450936 | Lodged:15:05 17 July 2014In respect to:Caveat 429347RECORDED:15:05 17 July 2014 |
Extension / Renewal of Term | 464154 | Lodged:15:50 17 March 2015Applied For Period:1 YearsRECORDED:15:50 17 March 2015GRANTED:23 April 2015Granted Period:1 YearsTerm Extended To:23/03/2016 |
Licence Instrument | 473137 | Lodged:13:56 20 August 2015ISSUED:13:57:03 20 August 2015 |
Application to Amend | 476022 | Lodged:14:04:22 16 October 2015Amending:AddressFrom:MCC AUSTRALIA SANJIN MINING PTY LTD, LEVEL 4, 50 ST GEORGES TCE, PERTH, WA, 6000To:MCC AUSTRALIA SANJIN MINING PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947RECORDED:14:04:22 16 October 2015 |
Extension / Renewal of Term | 483040 | Lodged:15:20 11 March 2016Applied For Period:1 YearsRECORDED:15:20 11 March 2016GRANTED:29 June 2016Granted Period:1 YearsTerm Extended To:23/03/2017 |
Application for Forfeiture | 499570 | Lodged:09:45:57 12 January 2017Respondent:MCC AUSTRALIA SANJIN MINING PTY LTDApplicant:J R CONTRACTING (WA) PTY LTDRECORDED:09:45:57 12 January 2017Order by Warden O'Sullivan on 08 January 2018 that Application for Forfeiture 499570 be withdrawn with no order as to costs.Warden's Determination:Withdrawn 08/01/2018 10:00:00WITHDRAWN:10:00:01 08 January 2018 |
Extension / Renewal of Term | 502338 | Lodged:14:55 09 March 2017Applied For Period:1 YearsRECORDED:14:55 09 March 2017GRANTED:16 June 2017Granted Period:1 YearsTerm Extended To:23/03/2018 |
Amalgamation | 510928 | Lodged:09:05 20 July 2017Amalgamating:Whole of former P 47/1135Situated within:External boundaries of E 47/1462-IGranted 13/02/2018 in respect to P 47/1135 |
Amalgamation | 510929 | Lodged:09:05 20 July 2017Amalgamating:Whole of former P 47/1136Situated within:External boundaries of E 47/1462-IGranted 13/02/2018 in respect to P 47/1136 |
Partial Surrender - Voluntary | 512335 | Lodged:11:43:12 10 August 2017REJECTED:11:43:12 10 August 2017 |
Partial Surrender - Voluntary | 512336 | Lodged:11:43:12 10 August 2017REJECTED:11:43:12 10 August 2017 |
Application for Forfeiture | 515982 | Lodged:14:08:22 09 October 2017Applicant:WINDFIELD METALS PTY LTDRespondent:MCC AUSTRALIA SANJIN MINING PTY LTDRECORDED:14:08:22 09 October 2017By consent of the parties Application for Forfeiture is dismissed by order of Warden O'Sullivan with no order as to costs.Warden's Determination:Dismissed 27/07/2018 10:00:00 |
Extension / Renewal of Term | 526238 | Lodged:15:03:23 22 March 2018Applied For Period:1 YearsRECORDED:15:03:23 22 March 2018GRANTED:23 May 2018Granted Period:1 YearsTerm Extended To:23/03/2019 |
Extension of Time | 530919 | Lodged:14:22:38 22 May 2018Type:Form 5RECORDED:14:22:38 22 May 2018APPROVED:15:54:07 22 May 2018Time to lodge extended to 31/05/2018 |
Extension of Time | 531317 | Lodged:08:30 29 May 2018Type:Form 5RECORDED:08:30 29 May 2018APPROVED:15:37:10 30 May 2018Time to lodge extended to 12/06/2018 |
Extension of Time | 532616 | Lodged:12:05:31 12 June 2018Type:Form 5RECORDED:12:05:31 12 June 2018APPROVED:15:01:03 12 June 2018Time to lodge extended to 13/06/2018 |
Application for Forfeiture | 550063 | Lodged:16:25:09 22 March 2019Applicant:WOODIWISS, DavidRespondent:MCC AUSTRALIA SANJIN MINING PTY LTDRECORDED:16:25:09 22 March 2019Withdrawn 2 April, 2019 |
Expiry - Full | 550477 | EFFECTIVE:Midnight 23 March 2019 |