Extracted from MTO on 08-Mar-2021 03:42,
last changed 25-Feb-2021.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 13-Dec-2005 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 13-Dec-2005 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 13-Dec-2005 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 13-Dec-2005 | |
5 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 13-Dec-2005 | |
6 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 13-Dec-2005 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licences 27/69, 27/71 and 28/24 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licences. | 13-Dec-2005 | |
8 | 3 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- Programme of Work titled "Low Impact Mining Activities - .Scrape and Detecting on Exploration Licence 27/278" (EXP 5316), dated 11 September 2006 and signed by Peter Langworthy, and retained on Department of Industry and Resources file No. 8267/02;
- "Low Impact Mining Operations - Scrape and Detect/Bulk Sampling" on E27/278 and E28/1746 dated 17 September 2009 (Reg ID 24044) signed by W. Groeneveld and retained on Department of Mines and Petroleum File No. 8267/02Vol01;
- "Programme of Work for scraping and detecting activities on E27/278" (Reg ID 24700) dated 10 December 2009 signed by David Guise and retained on Department of Mines and Petroleum File No. 8267/02Vol01
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 07-Jan-2010 | |
8 | 2 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- Programme of Work titled "Low Impact Mining Activities - .Scrape and Detecting on Exploration Licence 27/278" (EXP 5316), dated 11 September 2006 and signed by Peter Langworthy, and retained on Department of Industry and Resources file No. 8267/02;
- "Low Impact Mining Operations - Scrape and Detect/Bulk Sampling" on E27/278 and E28/1746 dated 17 September 2009 (Reg ID 24044) signed by W. Groeneveld and retained on Department of Mines and Petroleum File No. 8267/02Vol01
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 16-Oct-2009 | 06-Jan-2010 |
8 | 1 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- Programme of Work titled "Low Impact Mining Activities - .Scrape and Detecting on Exploration Licence 27/278" (EXP 5316), dated 11 September 2006 and signed by Peter Langworthy, and retained on Department of Industry and Resources file No. 8267/02.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 29-Nov-2006 | 15-Oct-2009 |
9 | 1 | The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform. | 29-Nov-2006 | |
10 | 1 | All topsoil and vegetation being removed ahead of all mining operations and being stockpiled for later respreading or immediately respread as rehabilitation progresses. | 29-Nov-2006 | |
11 | 1 | The licensee arranging lodgement of a Bond in favour of the Minister responsible for the Mining Act 1978 for due compliance with the environmental conditions of the licence in the sum of: | 29-Nov-2006 | 06-Jan-2010 |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 13-Dec-2005 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 13-Dec-2005 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 13-Dec-2005 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 13-Dec-2005 | |
5 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 13-Dec-2005 | |
6 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 13-Dec-2005 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licences 27/69, 27/71 and 28/24 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licences. | 13-Dec-2005 | |
8 | 3 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- Programme of Work titled "Low Impact Mining Activities - .Scrape and Detecting on Exploration Licence 27/278" (EXP 5316), dated 11 September 2006 and signed by Peter Langworthy, and retained on Department of Industry and Resources file No. 8267/02;
- "Low Impact Mining Operations - Scrape and Detect/Bulk Sampling" on E27/278 and E28/1746 dated 17 September 2009 (Reg ID 24044) signed by W. Groeneveld and retained on Department of Mines and Petroleum File No. 8267/02Vol01;
- "Programme of Work for scraping and detecting activities on E27/278" (Reg ID 24700) dated 10 December 2009 signed by David Guise and retained on Department of Mines and Petroleum File No. 8267/02Vol01
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 07-Jan-2010 | |
8 | 2 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- Programme of Work titled "Low Impact Mining Activities - .Scrape and Detecting on Exploration Licence 27/278" (EXP 5316), dated 11 September 2006 and signed by Peter Langworthy, and retained on Department of Industry and Resources file No. 8267/02;
- "Low Impact Mining Operations - Scrape and Detect/Bulk Sampling" on E27/278 and E28/1746 dated 17 September 2009 (Reg ID 24044) signed by W. Groeneveld and retained on Department of Mines and Petroleum File No. 8267/02Vol01
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 16-Oct-2009 | 06-Jan-2010 |
8 | 1 | The construction and operation of the project and measures to protect the environment being carried out generally in accordance with the document titled:- Programme of Work titled "Low Impact Mining Activities - .Scrape and Detecting on Exploration Licence 27/278" (EXP 5316), dated 11 September 2006 and signed by Peter Langworthy, and retained on Department of Industry and Resources file No. 8267/02.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 29-Nov-2006 | 15-Oct-2009 |
9 | 1 | The development and operation of the project being carried out in such a manner so as to create the minimum practicable disturbance to the existing vegetation and natural landform. | 29-Nov-2006 | |
10 | 1 | All topsoil and vegetation being removed ahead of all mining operations and being stockpiled for later respreading or immediately respread as rehabilitation progresses. | 29-Nov-2006 | |
11 | 1 | The licensee arranging lodgement of a Bond in favour of the Minister responsible for the Mining Act 1978 for due compliance with the environmental conditions of the licence in the sum of: | 29-Nov-2006 | 06-Jan-2010 |
Type | Number | Details |
Caveat | 1550H/056 | Lodged 11:55 AM on 13 Apr 2006 pursuant to Section 122A(1)(a) by INCO RESOURCES (AUSTRALIA) PTY LTD in respect to 100/100ths shares in the name of HERON RESOURCES LTDRECORDED 11:55 AM 13 Apr 2006Re Transfer KA30/067 14 day notice sent 23 Jan 2007.
Order under Section122E(1) that Caveat remain in full force and effect upon expiry of 14 day notice, Warden Auty 01 Feb 2007.Re Transfer 279929 - 14 day notice sent 04 Jan 2008.LAPSED:23:59:59 18 January 2008 |
Bond | 248087 | Lodged on 19 Sep 2006 For $10,000.00 (Security)REJECTED 19 Sep 2006 |
Bond | 249280 | Lodged on 09 Oct 2006 For $10,000.00 (Security)RECORDED 09 Oct 2006RETIRED 12 Feb 2008 |
Bond Requirement | 307700 | Requirement Date:29/11/2006Amount:$10,000.00RECORDED:10:13:05 29 November 2006FINALISED:13:49:33 20 May 2013 |
Bond | 282989 | Lodged on 11 Dec 2007 For $10,000.00 (Security)RECORDED 11 Dec 2007Lodged:00:00 11 December 2007Bond Type:SecurityBond Amount:$10,000.00RECORDED:11 December 2007RETIRED:20 May 2013 |
Caveat | 283376 | Lodged 10:20 AM on 25 Jan 2008 pursuant to Section 122A(2) by INCO RESOURCES (AUSTRALIA) PTY LTDLeave to Lodge Successive caveat granted by the Warden on 20 Feb 2008
RECORDED 10:00 AM 20 Feb 2008WITHDRAWN:09:30 25 June 2009 |
Partial Surrender - Compulsory | 306493 | Lodged:16:20 10 December 2008Section:Section 65 (1)(a)Surrendered Blocks:KALGOORLIE 1967 n, s, x, z
KALGOORLIE 2039 b, c, d, e, h, j, k
KALGOORLIE 2040 a, f, l, y
KALGOORLIE 2112 d, j, k, pSurrendered Total:19 BL.REGISTERED:23:59:59 12 December 2008Surrendered area to be released 08:30:00 15/04/2009 under Section 65(5)Surrendered area released 08:30:00 15/04/2009 under Section 65(5) |
Withdrawal of Dealing | 324416 | Lodged:09:30 25 June 2009In respect to:Caveat 283376RECORDED:09:30 25 June 2009 |
Application to Amend | 330098 | Lodged:13:30 14 September 2009Amending:NameFrom:PIONEER NICKEL LTDTo:PIONEER RESOURCES LIMITEDRECORDED:13:30 14 September 2009 |
Partial Surrender - Voluntary | 336228 | Lodged:14:50 08 December 2009Surrendered Blocks:KALGOORLIE 2040 b, c, g, h, m, n, r, s, w, xSurrendered Total:10 BL.REGISTERED:14:50 08 December 2009 |
Extension / Renewal of Term | 361268 | Lodged:16:00 10 December 2010Applied For Period:2 YearsRECORDED:16:00 10 December 2010GRANTED:11 February 2011Granted Period:2 YearsTerm Extended To:12/12/2012 |
Application to Amend | 367348 | Lodged:09:00 09 March 2011Amending:AddressFrom:Residential : XSTRATA NICKEL AUSTRALASIA OPERATIONS PTY LTD, SAME AS CORRESPONDENCE and Correspondence :XSTRATA NICKEL AUSTRALASIA OPERATIONS PTY LTD, LEVEL 3, 24 OUTRAM STREET, WEST PERTH, WA, 6005To:Residential : XSTRATA NICKEL AUSTRALASIA OPERATIONS PTY LTD, ADDRESS NOT PROVIDED and Correspondence :XSTRATA NICKEL AUSTRALASIA OPERATIONS PTY LTD, PO BOX 504, WEST PERTH, WA, 6872RECORDED:09:00 09 March 2011 |
Excess Tonnage | 399746 | Lodged:10:57 11 June 2012RECORDED:10:57 11 June 2012GRANTED:00:00 18 June 2012for 800 tonnes for the purpose of scraping and detecting activities. |
Extension / Renewal of Term | 412884 | Lodged:16:20 07 December 2012Applied For Period:2 YearsRECORDED:16:20 07 December 2012GRANTED:08 February 2013Granted Period:2 YearsTerm Extended To:12/12/2014 |
Application to Amend | 434122 | Lodged:12:55:08 30 October 2013Amending:AddressFrom:XSTRATA NICKEL AUSTRALASIA OPERATIONS PTY LTD, PO BOX 504, WEST PERTH, WA, 6872To:XSTRATA NICKEL AUSTRALASIA OPERATIONS PTY LTD, PO BOX Z5523, ST GEORGES TCE, PERTH, WA, 6831RECORDED:12:55:08 30 October 2013 |
Extension / Renewal of Term | 458916 | Lodged:16:00 09 December 2014Applied For Period:1 YearsRECORDED:16:00 09 December 2014GRANTED:13 February 2015Granted Period:1 YearsTerm Extended To:12/12/2015 |
Excess Tonnage | 471883 | Lodged:00:00 27 July 2015RECORDED:00:00 27 July 2015GRANTED:16:11:45 27 July 2015For an additional four thousand seven hundred and seventy (4,770) tonnes of material for the purpose of scraping and detecting activities. |
Excess Tonnage | 480783 | Lodged:08:30 06 November 2015RECORDED:08:30 06 November 2015GRANTED:08:42:27 25 February 2016For an additional ten thousand (10,000) tonnes of material for the purpose of bulk sampling activities. |
Extension / Renewal of Term | 478764 | Lodged:11:06:02 10 December 2015Applied For Period:1 YearsRECORDED:11:06:02 10 December 2015GRANTED:22 March 2016Granted Period:1 YearsTerm Extended To:12/12/2016 |
Extension / Renewal of Term | 498280 | Lodged:16:21:07 08 December 2016Applied For Period:1 YearsRECORDED:16:21:07 08 December 2016GRANTED:08 February 2017Granted Period:1 YearsTerm Extended To:12/12/2017 |
Application to Amend | 498337 | Lodged:15:25:35 09 December 2016Amending:Address (Including DTC Details)From:Principal Place of Business : PIONEER RESOURCES LIMITED, SAME AS CORRESPONDENCE and DTC :PIONEER RESOURCES LIMITED, PO BOX 1787, WEST PERTH, WA, 6872To:Principal Place of Business : PIONEER RESOURCES LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxx@nsrltd.com, xxxxx610 and DTC :PIONEER RESOURCES LIMITED, NORTHERN STAR RESOURCES LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxx@nsrltd.com, xxxxx610RECORDED:15:25:35 09 December 2016 |
Extension / Renewal of Term | 519344 | Lodged:08:30 01 December 2017Applied For Period:1 YearsRECORDED:08:30 01 December 2017GRANTED:06 March 2018Granted Period:1 YearsTerm Extended To:12/12/2018 |
Extension / Renewal of Term | 543863 | Lodged:12:37:17 04 December 2018Applied For Period:1 YearsRECORDED:12:37:17 04 December 2018GRANTED:01 February 2019Granted Period:1 YearsTerm Extended To:12/12/2019 |
Extension / Renewal of Term | 568558 | Lodged:13:32:51 11 December 2019Applied For Period:1 YearsRECORDED:13:32:51 11 December 2019GRANTED:13 February 2020Granted Period:1 YearsTerm Extended To:12/12/2020 |
Excess Tonnage | 570378 | Lodged:15:00 16 January 2020RECORDED:15:00 16 January 2020GRANTED:16:30 20 February 2020An additional 10,000 tonnes |
Application to Amend | 584564 | Lodged:12:35 20 August 2020Amending:NameFrom:PIONEER RESOURCES LIMITEDTo:ESSENTIAL METALS LIMITEDRECORDED:12:35 20 August 2020 |
Extension / Renewal of Term | 591694 | Lodged:15:09:09 02 December 2020Applied For Period:1 YearsRECORDED:15:09:09 02 December 2020 |