Extracted from MTO on 13-Jul-2025 01:18,
last changed 18-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 07-Mar-2014 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 20-May-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 07-Mar-2014 | 19-May-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 07-Mar-2014 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 07-Mar-2014 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 07-Mar-2014 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 07-Mar-2014 | |
7 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 20-May-2024 | |
8 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 20-May-2024 | |
9 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 20-May-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 07-Mar-2014 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 20-May-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 07-Mar-2014 | 19-May-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 07-Mar-2014 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 07-Mar-2014 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 07-Mar-2014 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 07-Mar-2014 | |
7 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 20-May-2024 | |
8 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 20-May-2024 | |
9 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 20-May-2024 | |
Type | Number | Details |
Forfeiture | 467734 | Initiated:20/05/2015 for non-compliance with rent requirementsRECORDED:11:17:42 19 May 2015Notice Issued:Regulation 50 Notice sent 20/05/2015 for non-compliance with rent requirements pursuant to Reg 109/Sec 63A- non payment of rent.Compliance Date:19/06/2015FINALISED:Order by Minister on 01 July 2015 that E 26/166 be Penalty Imposed |
Forfeiture | 469373 | Initiated:17/06/2015 for non-compliance with reporting requirements( Form 5 )RECORDED:13:10:39 16 June 2015Notice Issued:Regulation 50 Notice sent 17/06/2015 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- non lodgement of Form 5.Compliance Date:22/07/2015FINALISED:Order by Minister on 29 July 2015 that E 26/166 be Penalty Imposed |
Fine | 470558 | Fine in respect to:Forfeiture Process 467734Fine reason:Non-compliance with rent obligationsPenalty amount:$134.00Notification date:03/07/2015Due date:07/08/2015Pursuant to:Section 96A(5)RECORDED:03 July 2015PAYMENT RECEIVED:22 July 2015FINALISED:22 July 2015Receipt Number:06-147250Amount:$134.00Remaining balance:$0.00 |
Fine | 471983 | Fine in respect to:Forfeiture Process 469373Fine reason:Non-compliance with expenditure obligationsPenalty amount:$660.00Notification date:29/07/2015Due date:01/09/2015Pursuant to:Section 96A(5)RECORDED:29 July 2015PAYMENT RECEIVED:14 August 2015Receipt Number:06-147882Amount:$660.00Remaining balance:$0.00FINALISED:14 August 2015 |
Caveat | 484003 | Lodged:11:36:24 30 March 2016Caveat Type:Absolute CaveatCaveator:CITY OF KALGOORLIE- BOULDERShares Caveated:96/96 shares STRINDBERG, Brooke LouiseRECORDED:11:36:24 30 March 2016 |
Forfeiture | 489064 | Initiated:23/06/2016 for non-compliance with reporting requirements( Form 5 )RECORDED:13:30:41 22 June 2016Notice Issued:Regulation 50 Notice sent 23/06/2016 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- late lodgement of Form 5.Compliance Date:28/07/2016FINALISED:Order by Minister on 09 August 2016 that E 26/166 be Penalty Imposed |
Fine | 492152 | Fine in respect to:Forfeiture Process 489064Fine reason:Non-compliance with expenditure obligationsPenalty amount:$120.00Notification date:09/08/2016Due date:13/09/2016Pursuant to:Section 96A(5)RECORDED:12 August 2016PAYMENT RECEIVED:09 September 2016Receipt Number:06-156366Amount:$120.00Remaining balance:$0.00FINALISED:09 September 2016 |
Extension / Renewal of Term | 548861 | Lodged:16:16 06 March 2019Applied For Period:5 YearsRECORDED:16:16 06 March 2019GRANTED:07 May 2019Granted Period:5 YearsTerm Extended To:06/03/2024 |
Amalgamation | 639121 | Lodged:14:55 12 January 2022Amalgamating:Portion of P 26/3891Situated within:External boundaries of E 26/166Granted 13/12/2022 in respect to P 26/3891 |
Amalgamation | 639122 | Lodged:14:55 12 January 2022Amalgamating:Portion of P 26/3889Situated within:External boundaries of E 26/166Granted 11/10/2022 in respect to P 26/3889 |
Extension / Renewal of Term | 698026 | Lodged:10:48:22 06 March 2024Applied For Period:2 YearsRECORDED:10:48:22 06 March 2024GRANTED:06 May 2024Granted Period:2 YearsTerm Extended To:06/03/2026 |
Application to Amend | 698051 | Lodged:12:47:08 06 March 2024Amending:Address (Including DTC Details)From:Principal Residence : STRINDBERG, Brooke Louise, ADDRESS NOT PROVIDED and DTC :STRINDBERG, Brooke Louise, 20 WANN COURT, UPPER SWAN, WA, 6069To:Principal Residence : STRINDBERG, Brooke Louise, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :STRINDBERG, Brooke Louise, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:12:47:08 06 March 2024 |
Application to Amend | 714602 | Lodged:16:21:54 12 September 2024Amending:Address (Including DTC Details)From:STRINDBERG, Brooke Louise, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997To:STRINDBERG, Brooke Louise, AURORA TENEMENT CONSULTING PTY LTD, C/- AURORA TENEMENT CONSULTING PTY LTD, PO BOX 1907, WEST PERTH, WEST PERTH, WA, 6872, xxxxxx@auroratenements.com, xxxxxxx800REJECTED:16:21:54 12 September 2024 |
Application to Amend | 715403 | Lodged:16:18:40 24 September 2024Amending:Address (Including DTC Details)From:Principal Residence : STRINDBERG, Brooke Louise, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :STRINDBERG, Brooke Louise, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997To:Principal Residence : STRINDBERG, Brooke Louise, C/- AURORA TENEMENT CONSULTING PTY LTD, PO BOX 1907, WEST PERTH, WA, 6872, xxxxxx@auroratenements.com, xxxxxxx800 and DTC :STRINDBERG, Brooke Louise, AURORA TENEMENT CONSULTING PTY LTD, C/- AURORA TENEMENT CONSULTING PTY LTD, PO BOX 1907, WEST PERTH, WA, 6872, xxxxxx@auroratenements.com, xxxxxxx800RECORDED:16:18:40 24 September 2024 |
Referred to Native Title Date | Referral Type | Current Status | Procedure | Details | Objections | Water Comments | Determination Areas | Claims | Representative Area Bodies |
14-Apr-2022 | Tenement Amalgamation | Expedited Procedure : In Process | Expedited Procedure | 2022-04-292022-08-2916.51179 HA311043S121485E13km E'ly of Kambalda | WO2022/06072022-05-05WC1999/002Objection Withdrawn No Agreement2022-10-04 | | Ngadju Part B(WCD2017/002)WC1999/002WAD6020/1998trueWCD2017/002EXISTNo | | 13GoldfieldsNative Title Services Goldfields |
14-Apr-2022 | Tenement Amalgamation | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2022-05-042022-09-04CLEARED - Expedited Applies2022-12-1343.95539 HA311028S121489E13.2km E'ly of Kambalda | WO2022/06912022-05-16WC2017/007Objection Withdrawn2022-12-13WO2022/08232022-06-29WC1999/002Objection Withdrawn No Agreement2022-10-04 | | Ngadju Part B(WCD2017/002)WC1999/002WAD6020/1998falseWCD2017/002EXISTNo | Marlinyu Ghoorlie(WC2017/007)WC2017/007WAD647/2017falseRegistered | 13GoldfieldsNative Title Services Goldfields |
01-May-2013 | Tenement Application | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2013-05-222013-09-22CLEARED - Expedited Applies2014-03-053 BL31110S121490E14km E'ly of Kambalda | WO2013/09842013-09-20WC1999/002Objection Withdrawn Agreement2014-02-27 | | | Ngadju(WC1999/002)WC1999/002WAD6020/1998falsePartially Determined | 13GoldfieldsNative Title Services Goldfields |