1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 15-Mar-2010 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 15-Mar-2010 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-Mar-2010 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-Mar-2010 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-Mar-2010 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-Mar-2010 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 15-Mar-2010 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 15-Mar-2010 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-Mar-2010 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-Mar-2010 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-Mar-2010 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-Mar-2010 | |
Type | Number | Details |
Application to Amend | 312807 | Lodged:08:45 12 February 2009Amend area of blocks from 9 to 12 although first received attachment 1 with 12 blocks.RECORDED:08:45 12 February 2009 |
Extension of Time | 324060 | Lodged:00:00 24 June 2009Type:SecurityRECORDED:00:00 24 June 2009APPROVED:17:20 24 June 2009 |
Application to Amend | 397029 | Lodged:14:15 08 May 2012Amending:AddressFrom:KUNDANA GOLD PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249 PERTH BUSINESS CENTRE, WA, 6849To:KUNDANA GOLD PTY LTD, C/- BARRICK (PD) AUSTRALIA LIMITED, ATT: LAND MANAGER, LOCKED BAG 12, CLOISTERS SQUARE, PERTH, WA, 6850RECORDED:14:15 08 May 2012 |
Application to Amend | 443540 | Lodged:15:40:10 03 April 2014Amending:AddressFrom:KUNDANA GOLD PTY LTD, C/- BARRICK (PD) AUSTRALIA LIMITED, ATT: LAND MANAGER, LOCKED BAG 12, CLOISTERS SQUARE, PERTH, WA, 6850To:KUNDANA GOLD PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947RECORDED:15:40:10 03 April 2014 |
Extension of Time | 444141 | Lodged:15:19 10 April 2014Type:Form 5RECORDED:15:19 10 April 2014Extension of time until 27 May 2014 to lodge Form 5 for the year ending 14 March 2014APPROVED:09:59:24 02 September 2014 |
Extension / Renewal of Term | 463833 | Lodged:08:30 13 March 2015Applied For Period:5 YearsRECORDED:08:30 13 March 2015GRANTED:18 May 2015Granted Period:5 YearsTerm Extended To:14/03/2020 |
Application to Amend | 476099 | Lodged:15:18:21 19 October 2015Amending:AddressFrom:KUNDANA GOLD PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:KUNDANA GOLD PTY LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904RECORDED:15:18:21 19 October 2015 |
Partial Surrender - Compulsory | 481307 | Lodged:11:30:52 05 February 2016Section:Section 65 (3)Surrendered Blocks:KALGOORLIE 2320 b, h, o, u
KALGOORLIE 2392 eSurrendered Total:5 BL.REGISTERED:Midnight 14 March 2016Surrendered area to be released 08:30:00 11/04/2016 under Section 65 (3)Surrendered area released 08:30:00 11/04/2016 under Section 65 (3) |
Extension / Renewal of Term | 574057 | Lodged:13:53 13 March 2020Applied For Period:2 YearsRECORDED:13:53 13 March 2020GRANTED:13 May 2020Granted Period:2 YearsTerm Extended To:14/03/2022 |
Application to Amend | 617439 | Lodged:14:03:51 10 March 2021Amending:NameFrom:KUNDANA GOLD PTY LTDTo:KUNDANA GOLD PTY LIMITEDRECORDED:14:03:51 10 March 2021 |
Application to Amend | 617956 | Lodged:15:12:55 16 March 2021Amending:Address (Including DTC Details)From:Principal Place of Business : KUNDANA GOLD PTY LIMITED, SAME AS CORRESPONDENCE and DTC :KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904To:Principal Place of Business : KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904 and DTC :KUNDANA GOLD PTY LIMITED, NORTHERN STAR RESOURCES LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxxxxxx@nsrltd.com, xxxxx100RECORDED:15:12:55 16 March 2021 |
Application to Amend | 617957 | Lodged:15:12:55 16 March 2021Amending:Address (Including DTC Details)From:KUNDANA GOLD PTY LIMITED, SAME AS CORRESPONDENCETo:KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxxxxxx@nsrltd.com, xxxxx100REJECTED:15:12:55 16 March 2021 |
Application to Amend | 617974 | Lodged:15:25:28 16 March 2021Amending:Address (Including DTC Details)From:KUNDANA GOLD PTY LIMITED, SAME AS CORRESPONDENCETo:KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904RECORDED:15:25:28 16 March 2021 |
Application to Amend | 630638 | Lodged:11:56:19 18 August 2021Amending:Address (Including DTC Details)From:Principal Place of Business : KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904 and DTC :KUNDANA GOLD PTY LIMITED, NORTHERN STAR RESOURCES LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxxxxxx@nsrltd.com, xxxxx100To:Principal Place of Business : KUNDANA GOLD PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :KUNDANA GOLD PTY LIMITED, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:11:56:19 18 August 2021 |
Extension / Renewal of Term | 643684 | Lodged:13:34:50 11 March 2022Applied For Period:2 YearsRECORDED:13:34:50 11 March 2022GRANTED:28 October 2022Granted Period:2 YearsTerm Extended To:14/03/2024 |
Extension / Renewal of Term | 698506 | Lodged:12:06:33 12 March 2024Applied For Period:2 YearsRECORDED:12:06:33 12 March 2024GRANTED:14 May 2024Granted Period:2 YearsTerm Extended To:14/03/2026 |