Extracted from MTO on 10-Jul-2025 00:32,
last changed 10-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 23-Apr-2008 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 23-Apr-2008 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 23-Apr-2008 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Apr-2008 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 23-Apr-2008 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 23-Apr-2008 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 24/105, 24/151, 26/19, 26/63, 26/64, 26/96, 26/185, 26/191 & 26/192 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 23-Apr-2008 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Unnumbered Land Act Reserve 3. | 23-Apr-2008 | |
9 | 1 | No interference with Geodetic Survey Station SSM - Kalgoorlie 188, 188T, 189, 189T, 190, 191, 191T & 254 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 23-Apr-2008 | |
10 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 23-Apr-2008 | |
11 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land (RCL 11) as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 23-Apr-2008 | |
12 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition (11) hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
13 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition (11) hereof being approved by the State Mining Engineer, DoCEP in consultation with the operator of the railway on corridor land. | 23-Apr-2008 | |
14 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition (10) hereof without the prior approval of the operator of the railway on corridor land. | 23-Apr-2008 | |
15 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition (11) hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
16 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods Safety Branch, DoCEP. | 23-Apr-2008 | |
17 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 23-Apr-2008 | |
18 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 23-Apr-2008 | |
19 | 1 | No mining within 25 metres of either side of the Goldfields Pipeline Licence 24. | 23-Apr-2008 | |
20 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 19 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
21 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 19 hereof without the prior approval of the operators of the Pipeline Licence 24. | 23-Apr-2008 | |
22 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 19 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
23 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Pipeline Licence 24 without the prior written consent of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
24 | 1 | Mining on the Safety Zone established in Condition 19 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
25 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 19 hereof being at all times preserved for employees, contractors and agents of the operators of the Pipeline Licence 24. | 23-Apr-2008 | |
26 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Pipeline Licence 24. | 23-Apr-2008 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 23-Apr-2008 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 23-Apr-2008 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 23-Apr-2008 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Apr-2008 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 23-Apr-2008 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 23-Apr-2008 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 24/105, 24/151, 26/19, 26/63, 26/64, 26/96, 26/185, 26/191 & 26/192 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 23-Apr-2008 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Unnumbered Land Act Reserve 3. | 23-Apr-2008 | |
9 | 1 | No interference with Geodetic Survey Station SSM - Kalgoorlie 188, 188T, 189, 189T, 190, 191, 191T & 254 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 23-Apr-2008 | |
10 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 23-Apr-2008 | |
11 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land (RCL 11) as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 23-Apr-2008 | |
12 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition (11) hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
13 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition (11) hereof being approved by the State Mining Engineer, DoCEP in consultation with the operator of the railway on corridor land. | 23-Apr-2008 | |
14 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition (10) hereof without the prior approval of the operator of the railway on corridor land. | 23-Apr-2008 | |
15 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition (11) hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
16 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods Safety Branch, DoCEP. | 23-Apr-2008 | |
17 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 23-Apr-2008 | |
18 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 23-Apr-2008 | |
19 | 1 | No mining within 25 metres of either side of the Goldfields Pipeline Licence 24. | 23-Apr-2008 | |
20 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 19 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
21 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 19 hereof without the prior approval of the operators of the Pipeline Licence 24. | 23-Apr-2008 | |
22 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 19 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
23 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Pipeline Licence 24 without the prior written consent of the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
24 | 1 | Mining on the Safety Zone established in Condition 19 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer, DoCEP. | 23-Apr-2008 | |
25 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 19 hereof being at all times preserved for employees, contractors and agents of the operators of the Pipeline Licence 24. | 23-Apr-2008 | |
26 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Pipeline Licence 24. | 23-Apr-2008 | |
Type | Number | Details |
Extension of Time | 261596 | Lodged on 06 Mar 2007 to lodge SecurityApproved by the Warden on 06 Mar 2007 |
Extension of Time | 262524 | Lodged on 12 Mar 2007 to lodge late advertisementApproved by the Warden on 19 Mar 2007 |
Application to Amend | 274077 | Lodged 9:05 AM on 05 Sep 2007 amending Mineral Field to read: "East Coolgardie"RECORDED 9:05 AM 05 Sep 2007 |
Forfeiture | 328287 | Initiated:18/08/2009 for non-compliance with reporting requirementsRECORDED:09:09:33 21 August 2009Notice Issued:Regulation 50 Notice sent 18/08/2009 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:18/09/2009FINALISED:Order by Minister on 30 September 2009 that Penalty Imposed |
Fine | 331386 | Fine in respect to:Forfeiture Process 328287Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$450.00Notification date:01/10/2009Due date:02/11/2009Pursuant to:Section 96A(5)RECORDED:01 October 2009PAYMENT RECEIVED:08 October 2009Receipt Number:70814Amount:$450.00Remaining balance:$0.00FINALISED:08 October 2009 |
Application to Amend | 344188 | Lodged:12:25 06 April 2010Amending:AddressFrom:Residential : HERON RESOURCES LTD, SAME AS CORRESPONDENCE and Correspondance :HERON RESOURCES LTDC/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 8638 PERTH BUSINESS CENTRE, PERTH, WA, 6849To:Residential : HERON RESOURCES LTD, ADDRESS NOT PROVIDED and Correspondance :HERON RESOURCES LTDPO BOX 1280, KALGOORLIE, WA, 6433RECORDED:12:25 06 April 2010 |
Application to Amend | 347056 | Lodged:09:00 14 May 2010Amending:AddressFrom:Residential : HERON RESOURCES LTD, ADDRESS NOT PROVIDED and Correspondance :HERON RESOURCES LTDPO BOX 1280, KALGOORLIE, WA, 6433To:Residential : HERON RESOURCES LTD, SAME AS CORRESPONDENCE and Correspondance :HERON RESOURCES LTDC/-, PO BOX 1380, WEST PERTH, WA, 6872RECORDED:09:00 14 May 2010 |
Caveat | 365309 | Lodged:15:45 09 February 2011Caveat Type:Absolute CaveatCaveator:KALGOORLIE CONSOLIDATED GOLD MINES PTY LTDShares Caveated:100/100 shares HERON RESOURCES LIMITEDRECORDED:15:45 09 February 2011WITHDRAWN:12:45 20 December 2011 |
Application to Amend | 369563 | Lodged:16:00 12 April 2011Amending:AddressFrom:HERON RESOURCES LTD, C/-, PO BOX 1380, WEST PERTH, WA, 6872To:HERON RESOURCES LTD, ATT'N:LAND ADMINISTRATORS, C/- KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD, PMB 27, BLACK ST, KALGOORLIE, WA, 6430RECORDED:16:00 12 April 2011 |
Withdrawal of Dealing | 387806 | Lodged:12:45 20 December 2011In respect to:Caveat 365309RECORDED:12:45 20 December 2011 |
Extension / Renewal of Term | 420965 | Lodged:15:43 15 April 2013Applied For Period:5 YearsRECORDED:15:43 15 April 2013GRANTED:10 June 2013Granted Period:5 YearsTerm Extended To:22/04/2018 |
Partial Surrender - Voluntary | 420988 | Lodged:11:15 16 April 2013Surrendered Blocks:KALGOORLIE 2178 v, w
KALGOORLIE 2250 a, j, k, o, p, wSurrendered Total:8 BL.REGISTERED:11:15 16 April 2013 |
Application to Amend | 442217 | Lodged:09:30 17 March 2014Amending:AddressFrom:BARRICK (AUSTRALIA PACIFIC) LIMITED, C/- KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD, PMB 27, BLACK ST, KALGOORLIE, WA, 6430To:BARRICK (AUSTRALIA PACIFIC) LIMITED, ATTN: TENEMENT OFFICER C/- KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD, PMB 27, BLACK ST, KALGOORLIE, WA, 6430From:KALGOORLIE LAKE VIEW PTY LTD, C/- KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD, PMB 27, BLACK ST, KALGOORLIE, WA, 6430To:KALGOORLIE LAKE VIEW PTY LTD, ATTN: TENEMENT OFFICER C/- KALGOORLIE CONSOLIDATED GOLD MINES PTY LTD, PMB 27, BLACK ST, KALGOORLIE, WA, 6430RECORDED:09:30 17 March 2014 |
Application to Amend | 482153 | Lodged:12:02:49 24 February 2016Amending:NameFrom:BARRICK (AUSTRALIA PACIFIC) LIMITEDTo:BARRICK (AUSTRALIA PACIFIC) PTY LIMITEDRECORDED:12:02:49 24 February 2016 |
Caveat | 494269 | Provisionally Lodged:12:32:06 22 September 2016Caveat Type:Absolute CaveatCaveator:HERON RESOURCES LIMITEDShares Caveated:50/100 shares KALGOORLIE LAKE VIEW PTY LTD
50/100 shares BARRICK (AUSTRALIA PACIFIC) PTY LIMITEDREJECTED:12:32:06 22 September 2016 |
Caveat | 495060 | Lodged:12:20:39 07 October 2016Caveat Type:Absolute CaveatCaveator:HERON RESOURCES LIMITEDShares Caveated:50/100 shares KALGOORLIE LAKE VIEW PTY LTD
50/100 shares BARRICK (AUSTRALIA PACIFIC) PTY LIMITEDRECORDED:12:20:39 07 October 2016 |
Extension / Renewal of Term | 528495 | Lodged:10:38:25 20 April 2018Applied For Period:2 YearsRECORDED:10:38:25 20 April 2018REFUSED:13 March 2019This licence continues in force on and after 12 midnight on 13/03/2019 only in respect of that portion of land comprised within application for General Purpose Lease 24/40. |
Conversion | 540901 | New Tenement:G 24/40Application Date:13:49:56 18 Oct 2018Section:S67Converted 00:00 16 April 2019 being commencement of term of G 24/40 |
Expiry - Full | 551763 | EFFECTIVE:00:00 16 April 2019 |