1 | 1 | The rights of ingress to and egress from Miscellaneous Licence 25/31 and 25/33 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 26-Aug-2016 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 26-Aug-2016 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 26-Aug-2016 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 26-Aug-2016 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 26-Aug-2016 | |
6 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 26-Jun-2018 | |
Cond # | Ver | Text | Start | End |
1 | 1 | The rights of ingress to and egress from Miscellaneous Licence 25/31 and 25/33 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 26-Aug-2016 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 26-Aug-2016 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 26-Aug-2016 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 26-Aug-2016 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 26-Aug-2016 | |
6 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 26-Jun-2018 | |
Type | Number | Details |
Application to Amend | 506338 | Lodged:11:00 02 May 2017Amending:Address (Including DTC Details)From:SILVER LAKE RESOURCES LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:SILVER LAKE RESOURCES LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:11:00 02 May 2017 |
Application to Amend | 622381 | Lodged:13:33:47 13 May 2021Amending:Address (Including DTC Details)From:Principal Place of Business : SILVER LAKE RESOURCES LIMITED, SAME AS CORRESPONDENCE and DTC :SILVER LAKE RESOURCES LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400To:Principal Place of Business : SILVER LAKE RESOURCES LIMITED, PO BOX 10939, KALGOORLIE PO, WA, 6433, xxxx@getmining.com.au, xxxxxxx525 and DTC :SILVER LAKE RESOURCES LIMITED, C/- GETS, PO BOX 10939, KALGOORLIE PO, WA, 6433, xxxx@getmining.com.au, xxxxxxx525RECORDED:13:33:47 13 May 2021 |
Extension / Renewal of Term | 630988 | Lodged:08:35:41 23 August 2021Applied For Period:5 YearsRECORDED:08:35:41 23 August 2021GRANTED:23 November 2021Granted Period:5 YearsTerm Extended To:25/08/2026 |
Application to Amend | 666681 | Lodged:09:49:30 11 January 2023Amending:Address (Including DTC Details)From:MONGER EXPLORATION PTY LTD, GLOBAL EXPLORATION TENEMENT SERVICES, C/- GETS, PO BOX 10939, KALGOORLIE PO, WA, 6433, xxxx@getmining.com.au, xxxxxxx525To:MONGER EXPLORATION PTY LTD, GLOBAL EXPLORATION TENEMENT SERVICES, C/- GETS, PO BOX 7070, CLOISTERS SQUARE PO, WA, 6850, xxxx@getmining.com.au, xxxxxxxxx600REJECTED:09:49:30 11 January 2023 |
Application to Amend | 676384 | Lodged:08:30 19 May 2023Amending:Address (Including DTC Details)From:MONGER EXPLORATION PTY LTD, GLOBAL EXPLORATION TENEMENT SERVICES, C/- GETS, PO BOX 7070, CLOISTERS SQUARE PO, WA, 6850, xxxx@getmining.com.au, xxxxxxxxx600To:MONGER EXPLORATION PTY LTD, ACQUIRE TECHNOLOGY SOLUTIONS PTY LTD, C/- ACQUIRE, PO BOX 7070, CLOISTERS SQUARE PO, WA, 6850, xxxxxxxxx@acquire.com.au, xxxxxxx600RECORDED:08:30 19 May 2023 |
Application to Amend | 676394 | Lodged:08:30 19 May 2023Amending:Address (Including DTC Details)From:Principal Place of Business : MONGER EXPLORATION PTY LTD, C/- GETS, PO BOX 10939, KALGOORLIE PO, WA, 6433 and DTC :MONGER EXPLORATION PTY LTD, GLOBAL EXPLORATION TENEMENT SERVICES, C/- GETS, PO BOX 7070, CLOISTERS SQUARE PO, WA, 6850, xxxx@getmining.com.au, xxxxxxxxx600To:Principal Place of Business : MONGER EXPLORATION PTY LTD, 7 RHEOLA ST, WEST PERTH, WA, 6005 and DTC :MONGER EXPLORATION PTY LTD, ACQUIRE TECHNOLOGY SOLUTIONS PTY LTD, C/- ACQUIRE, PO BOX 7070, CLOISTERS SQUARE PO, WA, 6850, xxxxxxxxx@acquire.com.au, xxxxxxx600RECORDED:08:30 19 May 2023 |
Amalgamation | 707244 | Lodged:08:30 21 June 2024Amalgamating:Portion of former P 25/2568Situated within:External boundaries of E 25/524Withdrawn 07/01/2025 in respect to P 25/2568 |