Extracted from MTO on 11-Jul-2025 01:07,
last changed 06-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 09-Aug-2017 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 09-Aug-2017 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 09-Aug-2017 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 09-Aug-2017 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 09-Aug-2017 | |
6 | 1 | No interference with Geodetic Survey Station SSM-KURN 77 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 09-Aug-2017 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 09-Aug-2017 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 09-Aug-2017 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 09-Aug-2017 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 09-Aug-2017 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 09-Aug-2017 | |
6 | 1 | No interference with Geodetic Survey Station SSM-KURN 77 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 09-Aug-2017 | |
Type | Number | Details |
Application to Amend | 462460 | Lodged:11:30 17 February 2015Amending:Other/Non-title changesRECORDED:11:30 17 February 2015Application to Amend ABN to read ABN " 27691471653". |
Caveat | 592041 | Lodged:11:26:17 09 December 2020Caveat Type:Absolute CaveatCaveator:VOX ROYALTY AUSTRALIA PTY LTDShares Caveated:100/100 shares BLACK CAT (BULONG) PTY LTDRECORDED:11:26:17 09 December 2020 |
Application to Amend | 647332 | Lodged:12:39:48 14 April 2022Amending:NameFrom:BLACK CAT (BULONG) PTY LTDTo:BLACK CAT (KAL EAST) PTY LTDRECORDED:12:39:48 14 April 2022 |
Extension / Renewal of Term | 653629 | Lodged:10:47:56 18 July 2022Applied For Period:5 YearsRECORDED:10:47:56 18 July 2022GRANTED:08 September 2022Granted Period:5 YearsTerm Extended To:08/08/2027 |
Forfeiture | 674616 | Initiated:12/01/2023 for non-compliance with tenement conditionsRECORDED:08:30 12 January 2023FINALISED:Order by Minister on 23 May 2023 that E 25/520 be Penalty ImposedNotice Issued:Regulation 50 Notice sent 12/01/2023 for non-compliance with tenement conditions pursuant to Sec 82.Compliance Date:20/02/2023 |
Fine | 676921 | Fine in respect to:Forfeiture Process 674616Fine reason:Breach of conditionsPenalty amount:$10,000.00Notification date:26/05/2023Due date:26/06/2023Pursuant to:Section 96A(5)RECORDED:25 May 2023PAYMENT RECEIVED:01 June 2023FINALISED:01 June 2023Receipt Number:10366654Amount:$10,000.00Remaining balance:$0.00 |