Extracted from MTO on 01-Jul-2025 00:55,
last changed 01-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 26-Jul-2021 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 26-Jul-2021 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 26-Jul-2021 | |
4 | 1 | The Licensee making verbal or written contact with the holder of any underlying pastoral or grazing lease within a reasonable time prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 26-Jul-2021 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 26-Jul-2021 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licences 24/30, 24/76, 24/140, 24/141, 24/142 and 24/194 being at all times preserved to the licensees and no interference with the purpose or installations connected to the licences. | 26-Jul-2021 | |
7 | 1 | No mining within 25 metres of either side of the petroleum pipeline licence area of PL 37 and to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area. | 26-Jul-2021 | |
8 | 1 | No surface excavation approaching closer to the boundary of the Consultation Area than a distance equal to three times the depth of the excavation without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 26-Jul-2021 | |
9 | 1 | No explosives being used or stored within 150 metres of the petroleum licence area without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 26-Jul-2021 | |
10 | 1 | The rights of ingress to and egress from the petroleum pipeline licence area being at all times preserved for the employees, contractors and agents of the owners and operators of the pipeline. | 26-Jul-2021 | |
11 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purposes of protecting the pipeline and any existing condition imposed for this purpose may be cancelled or varied. | 26-Jul-2021 | |
| 1 | Consent to explore on Water Reserve 5058 granted . | 26-Jul-2021 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 26-Jul-2021 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 26-Jul-2021 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 26-Jul-2021 | |
4 | 1 | The Licensee making verbal or written contact with the holder of any underlying pastoral or grazing lease within a reasonable time prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 26-Jul-2021 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 26-Jul-2021 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licences 24/30, 24/76, 24/140, 24/141, 24/142 and 24/194 being at all times preserved to the licensees and no interference with the purpose or installations connected to the licences. | 26-Jul-2021 | |
7 | 1 | No mining within 25 metres of either side of the petroleum pipeline licence area of PL 37 and to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area. | 26-Jul-2021 | |
8 | 1 | No surface excavation approaching closer to the boundary of the Consultation Area than a distance equal to three times the depth of the excavation without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 26-Jul-2021 | |
9 | 1 | No explosives being used or stored within 150 metres of the petroleum licence area without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 26-Jul-2021 | |
10 | 1 | The rights of ingress to and egress from the petroleum pipeline licence area being at all times preserved for the employees, contractors and agents of the owners and operators of the pipeline. | 26-Jul-2021 | |
11 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purposes of protecting the pipeline and any existing condition imposed for this purpose may be cancelled or varied. | 26-Jul-2021 | |
| 1 | Consent to explore on Water Reserve 5058 granted . | 26-Jul-2021 | |
Type | Number | Details |
Objection | 521461 | Lodged:11:00:05 11 January 2018Objectors:WINGSTAR INVESTMENTS PTY LTDObjection Type:Tenement ApplicationRECORDED:11:00:05 11 January 2018WITHDRAWN:00:00 07 September 2018Wardens Decision Made on:00:00 07 September 2018Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn. |
Objection | 521726 | Lodged:10:51:35 16 January 2018Objectors:APHRODITE GOLD LIMITEDObjection Type:Tenement ApplicationRECORDED:10:51:35 16 January 2018Subject to Minute of Programming Directions sought by Consent dated 16 February 2018.FINALISED:14:15 24 October 2019Wardens Decision Made on:14:15 24 October 2019Wardens Decision Status:Finalised |
Extension of Time | 531165 | Lodged:09:36:32 25 May 2018Type:SecurityRECORDED:09:36:32 25 May 2018APPROVED:09:44:59 19 September 2018 |
Application to Amend | 549883 | Lodged:13:58:39 21 March 2019Amending:Address (Including DTC Details)From:Principal Place of Business : BA EXPLORATION PTY LTD, C/O ECONOMOS, CITIGROUP CENTRE, SUITE 38B, LEVEL 38, 2 PARK STREET, SYDNEY, NSW, 2000, xxxxxxxxxx@gmail.com, xxxxxxx891 and DTC :BA EXPLORATION PTY LTD, CHELVIE LEE, C/O ECONOMOS, CITIGROUP CENTRE, SUITE 38B, LEVEL 38, 2 PARK STREET, SYDNEY, NSW, 2000, xxxxxxxxxx@gmail.com, xxxxxxx891To:Principal Place of Business : BA EXPLORATION PTY LTD, 35/119 SOUTH TERRACE, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390 and DTC :BA EXPLORATION PTY LTD, WILLIAM HIGGINS, 35/119 SOUTH TERRACE, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390RECORDED:13:58:39 21 March 2019 |
Application to Amend | 549892 | Lodged:14:18:46 21 March 2019Amending:Address (Including DTC Details)From:Principal Place of Business : BA EXPLORATION PTY LTD, C/O ECONOMOS, CITIGROUP CENTRE, SUITE 38B, LEVEL 38, 2 PARK STREET, SYDNEY, NSW, 2000, xxxxxxxxxx@gmail.com, xxxxxxx891 and DTC :BA EXPLORATION PTY LTD, CHELVIE LEE, C/O ECONOMOS, CITIGROUP CENTRE, SUITE 38B, LEVEL 38, 2 PARK STREET, SYDNEY, NSW, 2000, xxxxxxxxxx@gmail.com, xxxxxxx891To:Principal Place of Business : BA EXPLORATION PTY LTD, 35/119 SOUTH TERRACE, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390 and DTC :BA EXPLORATION PTY LTD, WILLIAM HIGGINS, 35/119 SOUTH TERRACE, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390Duplication with Application to Amend 549883REJECTED:14:18:46 21 March 2019 |
Extension of Time | 561549 | Lodged:08:30 26 August 2019Type:SecurityRECORDED:08:30 26 August 2019APPROVED:14:48:48 02 October 2019 |
Extension of Time | 564187 | Lodged:08:30 07 October 2019Type:Stat DecRECORDED:08:30 07 October 2019REFUSED:11:28:35 22 October 2019Stat. Dec. incorrectly signed. |
Extension of Time | 564188 | Lodged:08:30 07 October 2019Type:Stat DecRECORDED:08:30 07 October 2019REFUSED:11:34:48 22 October 2019Stat. Dec. incorrectly signed |
Extension of Time | 564882 | Lodged:10:44:38 17 October 2019Type:SecurityRECORDED:10:44:38 17 October 2019APPROVED:15:27 24 October 2019 |
Application to Amend | 567159 | Lodged:08:30 22 November 2019Amending:Address (Including DTC Details)From:Principal Place of Business : BA EXPLORATION PTY LTD, 35/119 SOUTH TERRACE, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390 and DTC :BA EXPLORATION PTY LTD, WILLIAM HIGGINS, 35/119 SOUTH TERRACE, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390To:Principal Place of Business : BA EXPLORATION PTY LTD, 5 HOWARD STREET, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390 and DTC :BA EXPLORATION PTY LTD, WILLIAM HIGGINS, 5 HOWARD STREET, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390RECORDED:08:30 22 November 2019 |
Application to Amend | 586441 | Lodged:13:52:13 17 September 2020Amending:Address (Including DTC Details)From:BA EXPLORATION PTY LTD, WILLIAM HIGGINS, 5 HOWARD STREET, FREMANTLE, WA, 6160, xxxxxxxxxx@gmail.com, xxxxxxx390To:BA EXPLORATION PTY LTD, UTM GLOBAL PTY LTD, GPO BOX 1661, BRISBANE, QLD, 4001, xxxxx@utmglobal.com.au, xxxxx249RECORDED:13:52:13 17 September 2020 |
Application to Amend | 682585 | Lodged:09:31:56 01 August 2023Amending:Address (Including DTC Details)From:NATIVE MINERAL RESOURCES PTY LTD, QLD LAW GROUP, 100 WHARF STREET, BRISBANE, QLD, 4000, xxxxxxxxxxxxx@qldlawgroup.com.au, xxxxxxxxxxx000To:NATIVE MINERAL RESOURCES PTY LTD, UTM GLOBAL PTY LTD, GPO BOX 1661, 46 EDWARD STREET, BRISBANE, QLD, 4001, xxxxx@UTMGLOBAL.COM.AU, xxxxx249REJECTED:09:31:56 01 August 2023 |
Surrender - Outright | 714163 | Lodged:12:27:18 06 September 2024REGISTERED:12:27:18 06 September 2024 |