Extracted from MTO on 05-Jul-2025 01:25,
last changed 05-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | The rights of ingress to and egress from Miscellaneous Licence 24/198 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 11-Aug-2016 | |
2 | 2 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. (Same applies to FNA 87777) Transmission Line Easement. | 27-Feb-2017 | |
2 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 11-Aug-2016 | 26-Feb-2017 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 11-Aug-2016 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 11-Aug-2016 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 11-Aug-2016 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 11-Aug-2016 | |
7 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 12-Aug-2019 | |
Cond # | Ver | Text | Start | End |
1 | 1 | The rights of ingress to and egress from Miscellaneous Licence 24/198 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 11-Aug-2016 | |
2 | 2 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. (Same applies to FNA 87777) Transmission Line Easement. | 27-Feb-2017 | |
2 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 11-Aug-2016 | 26-Feb-2017 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 11-Aug-2016 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 11-Aug-2016 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 11-Aug-2016 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 11-Aug-2016 | |
7 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 12-Aug-2019 | |
Type | Number | Details |
Extension of Time | 465156 | Lodged:10:09 07 April 2015Type:ObjectionRECORDED:10:09 07 April 2015APPROVED:16:00 07 April 2015 |
Objection | 465155 | Lodged:16:00 07 April 2015Objectors:PADDINGTON GOLD PTY LIMITEDObjection Type:Tenement ApplicationRECORDED:16:00 07 April 2015Extension of Time for late lodgement of Objection Granted by the Warden.WITHDRAWN:12:20:29 26 February 2016Wardens Decision Made on:00:00 26 February 2016Wardens Decision Status:Finalised |
Extension of Time | 466100 | Lodged:10:00 21 April 2015Type:SecurityRECORDED:10:00 21 April 2015APPROVED:16:06 30 April 2015 |
Application to Amend | 485639 | Lodged:14:26:30 26 April 2016Amending:AddressFrom:YANDAN GOLD MINES PTY LTD, 27 GENERAL MACARTHUR PL, REDBANK, QLD, 4301To:YANDAN GOLD MINES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849RECORDED:14:26:30 26 April 2016 |
Application to Amend | 490226 | Lodged:14:20:17 07 July 2016Amending:Address (Including DTC Details)From:YANDAN GOLD MINES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849To:YANDAN GOLD MINES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:14:20:17 07 July 2016 |
Amalgamation | 492453 | Lodged:15:35 17 August 2016Amalgamating:Portion of former P 24/4252Situated within:External boundaries of E 24/197Granted 16/02/2017 in respect to P 24/4252 |
Amalgamation | 492890 | Lodged:15:55 25 August 2016Amalgamating:Portion of former P 24/4236Situated within:External boundaries of E 24/197Granted 27/02/2017 in respect to P 24/4236 |
Extension of Time | 540328 | Lodged:13:58:57 10 October 2018Type:Form 5RECORDED:13:58:57 10 October 2018Time to lodge late Form 5 for YE 2018 extended to COB 07/11/2018APPROVED:15:28:43 11 October 2018 |
Application to Amend | 554324 | Lodged:15:35 21 May 2019Amending:Address (Including DTC Details)From:Principal Place of Business : YANDAN GOLD MINES PTY LTD, SAME AS CORRESPONDENCE and DTC :YANDAN GOLD MINES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : YANDAN GOLD MINES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849 and DTC :YANDAN GOLD MINES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxxx977RECORDED:15:35 21 May 2019 |
Forfeiture | 566977 | Initiated:22/11/2019 for non-compliance with expenditure requirementsRECORDED:09:28 22 November 2019Notice Issued:Regulation 50 Notice sent 22/11/2019 for non-compliance with expenditure requirements pursuant to Reg 21/Sec 63A- under expended.Compliance Date:26/02/2020FINALISED:Order by Minister on 21 January 2020 that E 24/197 be Penalty Imposed |
Fine | 570680 | Fine in respect to:Forfeiture Process 566977Fine reason:Non-compliance with expenditure obligationsPenalty amount:$90.00Notification date:22/01/2020Due date:27/02/2020Pursuant to:Section 96A(5)RECORDED:22 January 2020PAYMENT RECEIVED:24 January 2020FINALISED:24 January 2020Receipt Number:50624831327Amount:$90.00Remaining balance:$0.00 |
Extension of Time | 587962 | Lodged:10:02:44 09 October 2020Type:Form 5RECORDED:10:02:44 09 October 2020Time to lodge late form 5 YE 2020 extended up until COB 23 October 2020APPROVED:12:01:01 27 October 2020 |
Application to Amend | 590155 | Lodged:14:30 11 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : YANDAN GOLD MINES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849 and DTC :YANDAN GOLD MINES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxxx977To:Principal Place of Business : YANDAN GOLD MINES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :YANDAN GOLD MINES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxxx977RECORDED:14:30 11 November 2020 |
Extension / Renewal of Term | 629884 | Lodged:12:42:54 09 August 2021Applied For Period:5 YearsRECORDED:12:42:54 09 August 2021GRANTED:13 October 2021Granted Period:5 YearsTerm Extended To:10/08/2026 |
Surrender - Outright | 668837 | Lodged:09:13:23 14 February 2023REGISTERED:09:13:23 14 February 2023 |