Extracted from MTO on 05-Jul-2025 00:14,
last changed 05-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 18-Aug-2008 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 18-Aug-2008 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Aug-2008 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Aug-2008 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 18-Aug-2008 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 18-Aug-2008 | |
7 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 18-Aug-2008 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 18-Aug-2008 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 18-Aug-2008 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Aug-2008 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Aug-2008 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 18-Aug-2008 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 18-Aug-2008 | |
7 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 18-Aug-2008 | |
Type | Number | Details |
Extension of Time | 272404 | Lodged 9:42 AM on 14 Aug 2007 to lodge security (Form 32) 160 days late.Approved by the Warden on 15 Aug 2007 |
Transfer | 275124 | Transfer 275124 was registered on 21 Sep 2007 against E 24/68. Pursuant to Section 120AA the applicant details have been amended. |
Transfer | 288598 | Transfer 288598 was registered on 11 Apr 2008 against E 24/68. Pursuant to Section 120AA the applicant details have been amended. |
Application to Amend | 397029 | Lodged:14:15 08 May 2012Amending:AddressFrom:KUNDANA GOLD PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249 PERTH BUSINESS CENTRE, WA, 6849To:KUNDANA GOLD PTY LTD, C/- BARRICK (PD) AUSTRALIA LIMITED, ATT: LAND MANAGER, LOCKED BAG 12, CLOISTERS SQUARE, PERTH, WA, 6850RECORDED:14:15 08 May 2012 |
Extension / Renewal of Term | 428946 | Lodged:11:20 13 August 2013Applied For Period:5 YearsRECORDED:11:20 13 August 2013GRANTED:11 October 2013Granted Period:5 YearsTerm Extended To:17/08/2018 |
Application to Amend | 443540 | Lodged:15:40:10 03 April 2014Amending:AddressFrom:KUNDANA GOLD PTY LTD, C/- BARRICK (PD) AUSTRALIA LIMITED, ATT: LAND MANAGER, LOCKED BAG 12, CLOISTERS SQUARE, PERTH, WA, 6850To:KUNDANA GOLD PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947RECORDED:15:40:10 03 April 2014 |
Application to Amend | 476099 | Lodged:15:18:21 19 October 2015Amending:AddressFrom:KUNDANA GOLD PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:KUNDANA GOLD PTY LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904RECORDED:15:18:21 19 October 2015 |
Amalgamation | 484929 | Lodged:10:53 12 April 2016Amalgamating:Whole of P 24/4236Situated within:External boundaries of E 24/152Refused 28/04/2016 in respect to P 24/4236 |
Extension / Renewal of Term | 537333 | Lodged:11:46:39 17 August 2018Applied For Period:2 YearsRECORDED:11:46:39 17 August 2018GRANTED:18 February 2019Granted Period:2 YearsTerm Extended To:17/08/2020 |
Extension / Renewal of Term | 583686 | Lodged:11:34:53 06 August 2020Applied For Period:2 YearsRECORDED:11:34:53 06 August 2020GRANTED:26 October 2020Granted Period:2 YearsTerm Extended To:17/08/2022 |
Application to Amend | 617439 | Lodged:14:03:51 10 March 2021From:KUNDANA GOLD PTY LTDAmending:NameTo:KUNDANA GOLD PTY LIMITEDRECORDED:14:03:51 10 March 2021 |
Application to Amend | 617956 | Lodged:15:12:55 16 March 2021Amending:Address (Including DTC Details)From:Principal Place of Business : KUNDANA GOLD PTY LIMITED, SAME AS CORRESPONDENCE and DTC :KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904To:Principal Place of Business : KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904 and DTC :KUNDANA GOLD PTY LIMITED, NORTHERN STAR RESOURCES LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxxxxxx@nsrltd.com, xxxxx100RECORDED:15:12:55 16 March 2021 |
Application to Amend | 617957 | Lodged:15:12:55 16 March 2021Amending:Address (Including DTC Details)From:KUNDANA GOLD PTY LIMITED, SAME AS CORRESPONDENCETo:KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxxxxxx@nsrltd.com, xxxxx100REJECTED:15:12:55 16 March 2021 |
Application to Amend | 617974 | Lodged:15:25:28 16 March 2021Amending:Address (Including DTC Details)From:KUNDANA GOLD PTY LIMITED, SAME AS CORRESPONDENCETo:KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904RECORDED:15:25:28 16 March 2021 |
Application to Amend | 630638 | Lodged:11:56:19 18 August 2021Amending:Address (Including DTC Details)From:Principal Place of Business : KUNDANA GOLD PTY LIMITED, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904 and DTC :KUNDANA GOLD PTY LIMITED, NORTHERN STAR RESOURCES LTD, C/- LAND DEPARTMENT, PO BOX 2008, SUBIACO, WA, 6904, xxxxxxxxx@nsrltd.com, xxxxx100To:Principal Place of Business : KUNDANA GOLD PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :KUNDANA GOLD PTY LIMITED, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:11:56:19 18 August 2021 |
Expiry - Full | 659211 | EFFECTIVE:Midnight 17 August 2022 |