Extracted from MTO on 09-Jul-2025 00:31,
last changed 26-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 14-Jan-2016 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 14-Jan-2016 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 14-Jan-2016 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 14-Jan-2016 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 14-Jan-2016 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 14-Jan-2016 | |
7 | 1 | No excavation, excepting shafts, approaching closer to the Great Northern Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Great Northern Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface. | 14-Jan-2016 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Historical Structures Reserve 34549, Hospital Site Reserve 2982 and Water Reserve 4150. | 14-Jan-2016 | |
9 | 1 | No interference with Geodetic Survey Station CUE 29, CUE 31, CUE 105 and CUE 104 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 14-Jan-2016 | |
10 | 1 | In respect of the area covered by this licence if the Yugunga-Nya People (being the applicants in Federal Court Application No/s. WAD6132/1998 send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Yugunga-Nya People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Yamatji Marlpa Aboriginal Corporation. | 14-Jan-2016 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 14-Jan-2016 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 14-Jan-2016 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 14-Jan-2016 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 14-Jan-2016 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 14-Jan-2016 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 14-Jan-2016 | |
7 | 1 | No excavation, excepting shafts, approaching closer to the Great Northern Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Great Northern Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface. | 14-Jan-2016 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Historical Structures Reserve 34549, Hospital Site Reserve 2982 and Water Reserve 4150. | 14-Jan-2016 | |
9 | 1 | No interference with Geodetic Survey Station CUE 29, CUE 31, CUE 105 and CUE 104 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 14-Jan-2016 | |
10 | 1 | In respect of the area covered by this licence if the Yugunga-Nya People (being the applicants in Federal Court Application No/s. WAD6132/1998 send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Yugunga-Nya People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Yamatji Marlpa Aboriginal Corporation. | 14-Jan-2016 | |
Type | Number | Details |
Extension of Time | 458902 | Lodged:09:35 09 December 2014Type:SecurityRECORDED:09:35 09 December 2014APPROVED:15:20 10 December 2014 |
Amalgamation | 495992 | Lodged:09:57 24 October 2016Amalgamating:Portion of former P 21/654Situated within:External boundaries of E 21/186Amalgamating:Portion of former P 21/657Situated within:External boundaries of E 21/186Granted 05/07/2017 in respect to P 21/654Granted 05/07/2017 in respect to P 21/657 |
Application to Amend | 511288 | Lodged:13:00 26 July 2017Amending:NameFrom:GOLDVIEW METALS LIMITEDTo:GOLDVIEW METALS PTY LTDRECORDED:13:00 26 July 2017 |
Amalgamation | 529967 | Lodged:10:30 11 May 2018Amalgamating:Portion of P 21/709Situated within:External boundaries of E 21/186Granted 12/07/2019 in respect to P 21/709 |
Extension / Renewal of Term | 584254 | Lodged:09:39 17 August 2020Applied For Period:5 YearsRECORDED:09:39 17 August 2020GRANTED:06 November 2020Granted Period:5 YearsTerm Extended To:13/01/2026 |
Application to Amend | 589680 | Lodged:16:20 05 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : GOLDVIEW METALS PTY LTD, ADDRESS NOT PROVIDED and DTC :GOLDVIEW METALS PTY LTD, PO BOX 461, CLOVERDALE, WA, 6105To:Principal Place of Business : GOLDVIEW METALS PTY LTD, C/- WESTERN TENEMENT SERVICES, PO BOX 3285, EAST PERTH, WA, 6892, xxxxx@wts.net.au, xxxxxxx111 and DTC :GOLDVIEW METALS PTY LTD, WESTERN TENEMENT SERVICES, C/- WESTERN TENEMENT SERVICES, PO BOX 3285, EAST PERTH, WA, 6892, xxxxx@wts.net.au, xxxxxxx111RECORDED:16:20 05 November 2020 |
Forfeiture | 713556 | Initiated:03/09/2024 for non-compliance with reporting requirementsRECORDED:14:18 03 September 2024FINALISED:Order by Minister on 13 November 2024 that E 21/186 be Penalty ImposedNotice Issued:Regulation 50 Notice sent 03/09/2024 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:08/10/2024 |
Fine | 719828 | Fine in respect to:Forfeiture Process 713556Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$500.00Notification date:19/11/2024Due date:06/01/2025Pursuant to:Section 96A(5)RECORDED:19 November 2024PAYMENT RECEIVED:20 November 2024FINALISED:20 November 2024Receipt Number:48756158528Amount:$500.00Remaining balance:$0.00 |
Caveat | 729228 | Lodged:13:15 25 March 2025Caveat Type:Consent CaveatCaveator:CARUSO, Victor MichaelShares Caveated:100/100 shares GOLDVIEW METALS PTY LTDRECORDED:13:15 25 March 2025 |
Referred to Native Title Date | Referral Type | Current Status | Procedure | Details | Objections | Water Comments | Determination Areas | Claims | Representative Area Bodies |
18-Jun-2018 | Tenement Amalgamation | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2018-07-112018-11-11CLEARED - Expedited Applies2019-03-05112.61 HA273641S1175412E23km S'ly of Cue | WO2018/05782018-08-07WC1999/010Objection Withdrawn2019-03-05 | | | Wutha(WC1999/010)WC1999/010WAD6064/1998trueDismissedYugunga-Nya People (Unregistered)(WC1999/046)WC1999/046WAD29/2019truePartially Determined | 14GeraldtonYamatji Marlpa Aboriginal Corporation |
25-Oct-2016 | Tenement Amalgamation | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2016-11-162017-03-16CLEARED - Expedited Applies2017-07-048.4 HA27369S117547E23km S'ly of Cue | WO2016/08822016-12-12WC1999/010Objection Withdrawn Agreement2017-04-20WO2017/01792017-03-09WC1999/046Objection Withdrawn Agreement2017-07-04 | | | Wutha(WC1999/010)WC1999/010WAD6064/1998trueDismissedYugunga-Nya People (Unregistered)(WC1999/046)WC1999/046WAD29/2019truePartially Determined | 14GeraldtonYamatji Marlpa Aboriginal Corporation |
05-Feb-2015 | Tenement Application | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2015-02-252015-06-25CLEARED - Expedited Applies2016-01-086 BL27380S1175329E23 km S'ly of Cue | WO2015/02742015-03-25WC1996/098Objection Dismissed Sec 148(a)2015-06-17WO2015/02752015-03-25WC1999/046Objection Withdrawn Agreement2015-12-16WO2015/05402015-06-17WC1999/046Objection Rejected2015-07-09 | | | Badimia People(WC1996/098)WC1996/098WAD6123/1998falseDeterminedWutha(WC1999/010)WC1999/010WAD6064/1998falseDismissedYugunga-Nya People (Unregistered)(WC1999/046)WC1999/046WAD29/2019falsePartially Determined | 14GeraldtonYamatji Marlpa Aboriginal Corporation |