1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 30-Jan-2008 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 30-Jan-2008 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 30-Jan-2008 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 30-Jan-2008 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 30-Jan-2008 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 30-Jan-2008 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Water Act Reserve 7747, Rubbish Depot Reserve 5223, Historical Structures Reserve 34549, Hospital Site Reserve 2982, Water Reserve 4150 & Mainland and Austin Townsite boundaries.. | 30-Jan-2008 | |
8 | 1 | No interference with Geodetic Survey Station CUE 29, 30, 32, 33, 104, 105, 106, 107, 108, 109, 110, 111 & 112 & G21-2 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 30-Jan-2008 | |
9 | 1 | No mining on Cemetery Reserve 4983 & 5222 and mining within a distance of 140 metres laterally from the Reserve being confined to below a depth of 50 metres from the lowest part of the surface of the land with rights of ingress to and egress from the said Reserve being at all times preserved to the public. | 30-Jan-2008 | |
| 1 | Consent to Mine on Mainland and Austin Townsites given subject to: | 30-Jan-2008 | |
10 | 1 | Access to the surface of land within Mainland and Austin Townsite for mining purposes being subject to the approval of the local Authority or relevant reserve vestees, and mining activities within the first 100 metres below the surface of the land being limited to such exploration activities as may be approved by the Director, Environment DoIR. | 30-Jan-2008 | |
| 1 | Consent to mine on Water Reserve 4150 granted subject to the following: | 28-Feb-2008 | |
11 | 1 | Written notification, where practicable, of the time frame, type and extent of proposed ground disturbing activities being forwarded to the Department of Water Geraldton seven days prior to commencement of those activities. | 28-Feb-2008 | |
12 | 1 | Any significant waterway (flowing or not), wetland or its fringing vegetation that may exist on site not being disturbed or removed without prior written approval from the Department of Water. | 28-Feb-2008 | |
13 | 1 | The rights of ingress to and egress from the Licence being at all reasonable times preserved to officers of the Department of Water for inspection and investigation purposes. | 28-Feb-2008 | |
14 | 1 | The storage and disposal of hydrocarbons, chemicals and potentially hazardous substances being in accordance with the Department of Water's Guidelines and Water Quality Protection Notes . | 28-Feb-2008 | |
15 | 1 | All proposed exploration activities within Public Drinking Water Source Areas complying with the Department of Water's Water Quality Protection Note Land Use Compatibility in Public Drinking Water Source Areas. | 28-Feb-2008 | |
16 | 1 | All Mining Act tenement activities within Public Drinking Water Source Areas being prohibited unless the prior written approval has been obtained from the Department of Water. | 28-Feb-2008 | |
17 | 1 | All Mining Act tenement activities are prohibited within 2 kilometres of the maximum storage level of a reservoir including the reservoir itself, unless the prior written approval of the Department of Water is first obtained. | 28-Feb-2008 | |
18 | 1 | Storage and use of hydrocarbons and potentially hazardous substances requiring the prior written approval or appropriate permits from the Department of Water. | 28-Feb-2008 | |
19 | 1 | All hydrocarbon or other pollutant spillage being reported to the Department of Water. Remediation being carried out to the satisfaction of the Department of Water. | 28-Feb-2008 | |
20 | 1 | All Mining Act tenement activities are prohibited within a 300-metre radius of any observation well in a Public Drinking Water Source Priority P1, P2 & P3 Areas unless the written approval of the Department of Water is first obtained. | 28-Feb-2008 | |
21 | 1 | All Mining Act tenement activities are prohibited within a 500-metre radius in a P1 area or a 300-metre radius in a P2 or P3 area of any Public Drinking Water Source production well or dam, unless the written approval of the Department of Water is first obtained. | 28-Feb-2008 | |
22 | 1 | No excavation, excepting shafts, approaching closer to the Great Northern Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Great Northern Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface. | 17-Apr-2012 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 30-Jan-2008 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 30-Jan-2008 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 30-Jan-2008 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 30-Jan-2008 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 30-Jan-2008 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 30-Jan-2008 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Water Act Reserve 7747, Rubbish Depot Reserve 5223, Historical Structures Reserve 34549, Hospital Site Reserve 2982, Water Reserve 4150 & Mainland and Austin Townsite boundaries.. | 30-Jan-2008 | |
8 | 1 | No interference with Geodetic Survey Station CUE 29, 30, 32, 33, 104, 105, 106, 107, 108, 109, 110, 111 & 112 & G21-2 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 30-Jan-2008 | |
9 | 1 | No mining on Cemetery Reserve 4983 & 5222 and mining within a distance of 140 metres laterally from the Reserve being confined to below a depth of 50 metres from the lowest part of the surface of the land with rights of ingress to and egress from the said Reserve being at all times preserved to the public. | 30-Jan-2008 | |
| 1 | Consent to Mine on Mainland and Austin Townsites given subject to: | 30-Jan-2008 | |
10 | 1 | Access to the surface of land within Mainland and Austin Townsite for mining purposes being subject to the approval of the local Authority or relevant reserve vestees, and mining activities within the first 100 metres below the surface of the land being limited to such exploration activities as may be approved by the Director, Environment DoIR. | 30-Jan-2008 | |
| 1 | Consent to mine on Water Reserve 4150 granted subject to the following: | 28-Feb-2008 | |
11 | 1 | Written notification, where practicable, of the time frame, type and extent of proposed ground disturbing activities being forwarded to the Department of Water Geraldton seven days prior to commencement of those activities. | 28-Feb-2008 | |
12 | 1 | Any significant waterway (flowing or not), wetland or its fringing vegetation that may exist on site not being disturbed or removed without prior written approval from the Department of Water. | 28-Feb-2008 | |
13 | 1 | The rights of ingress to and egress from the Licence being at all reasonable times preserved to officers of the Department of Water for inspection and investigation purposes. | 28-Feb-2008 | |
14 | 1 | The storage and disposal of hydrocarbons, chemicals and potentially hazardous substances being in accordance with the Department of Water's Guidelines and Water Quality Protection Notes . | 28-Feb-2008 | |
15 | 1 | All proposed exploration activities within Public Drinking Water Source Areas complying with the Department of Water's Water Quality Protection Note Land Use Compatibility in Public Drinking Water Source Areas. | 28-Feb-2008 | |
16 | 1 | All Mining Act tenement activities within Public Drinking Water Source Areas being prohibited unless the prior written approval has been obtained from the Department of Water. | 28-Feb-2008 | |
17 | 1 | All Mining Act tenement activities are prohibited within 2 kilometres of the maximum storage level of a reservoir including the reservoir itself, unless the prior written approval of the Department of Water is first obtained. | 28-Feb-2008 | |
18 | 1 | Storage and use of hydrocarbons and potentially hazardous substances requiring the prior written approval or appropriate permits from the Department of Water. | 28-Feb-2008 | |
19 | 1 | All hydrocarbon or other pollutant spillage being reported to the Department of Water. Remediation being carried out to the satisfaction of the Department of Water. | 28-Feb-2008 | |
20 | 1 | All Mining Act tenement activities are prohibited within a 300-metre radius of any observation well in a Public Drinking Water Source Priority P1, P2 & P3 Areas unless the written approval of the Department of Water is first obtained. | 28-Feb-2008 | |
21 | 1 | All Mining Act tenement activities are prohibited within a 500-metre radius in a P1 area or a 300-metre radius in a P2 or P3 area of any Public Drinking Water Source production well or dam, unless the written approval of the Department of Water is first obtained. | 28-Feb-2008 | |
22 | 1 | No excavation, excepting shafts, approaching closer to the Great Northern Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Great Northern Highway or Highway verge being confined to below a depth of 30 metres from the natural surface, and on any other road or road verge, to below a depth of 15 metres from the natural surface. | 17-Apr-2012 | |
Type | Number | Details |
Partial Surrender - Voluntary | 309073 | Lodged:09:14 09 January 2009REGISTERED:09:14 09 January 2009 |
Amalgamation | 313468 | Lodged:08:30 19 February 2009Amalgamating:Whole of P 21/658Situated within:External boundaries of E 21/129Amalgamating:Portion of P 21/657Situated within:External boundaries of E 21/129Granted 17/04/2012 in respect to P 21/657Granted 17/04/2012 in respect to P 21/658 |
Extension of Time | 395479 | Lodged:16:40 13 April 2012Type:Stat DecRECORDED:16:40 13 April 2012Extension of time until 4 May 2012 to lodge statutory declaration in support of Appln 393866 for exemption from expenditure condition for the year ending 29 January 2012APPROVED:07:21:23 16 April 2012 |
Deferral of Drop Off | 414396 | Lodged:11:00 04 January 2013RECORDED:11:00 04 January 2013GRANTED:01 March 2013 |
Extension / Renewal of Term | 415013 | Lodged:15:39:39 15 January 2013Applied For Period:5 YearsRECORDED:15:39:39 15 January 2013GRANTED:01 March 2013Granted Period:5 YearsTerm Extended To:29/01/2018 |
Partial Surrender - Voluntary | 434702 | Lodged:15:28:25 07 November 2013Surrendered Blocks:MEEKATHARRA 3071 z
MEEKATHARRA 3072 s, v, w, xSurrendered Total:5 BL.REGISTERED:15:28:25 07 November 2013 |
Caveat | 480404 | Lodged:14:40 18 January 2016Caveat Type:Consent CaveatCaveator:MUSGRAVE MINERALS LIMITEDShares Caveated:100/100 shares SILVER LAKE RESOURCES LIMITEDRECORDED:14:40 18 January 2016Affected Dealing:Transfer 50255714 day notice sent:15 March 2017WITHDRAWN:08:33:50 03 April 2017 |
Withdrawal of Dealing | 503768 | Lodged:08:33:50 03 April 2017In respect to:Caveat 480404RECORDED:08:33:50 03 April 2017 |
Extension / Renewal of Term | 521801 | Lodged:10:01:12 17 January 2018Applied For Period:2 YearsRECORDED:10:01:12 17 January 2018GRANTED:09 April 2018Granted Period:2 YearsTerm Extended To:29/01/2020 |
Amalgamation | 532796 | Lodged:15:15 07 June 2018Amalgamating:Portion of former P 21/659Situated within:External boundaries of E 21/129Granted 20/06/2018 in respect to P 21/659 |
Amalgamation | 539372 | Lodged:10:19 13 September 2018Amalgamating:Portion of former P 21/653Situated within:External boundaries of E 21/129Granted 20/08/2019 in respect to P 21/653 |
Extension / Renewal of Term | 569320 | Lodged:10:03:14 20 December 2019Applied For Period:2 YearsRECORDED:10:03:14 20 December 2019GRANTED:30 March 2020Granted Period:2 YearsTerm Extended To:29/01/2022 |
Extension / Renewal of Term | 636847 | Lodged:13:04:06 02 December 2021Applied For Period:2 YearsRECORDED:13:04:06 02 December 2021GRANTED:06 April 2022Granted Period:2 YearsTerm Extended To:29/01/2024 |
Application to Amend | 638168 | Lodged:12:52:43 22 December 2021Amending:Address (Including DTC Details)From:Principal Place of Business : MUSGRAVE MINERALS LIMITED, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008 and DTC :MUSGRAVE MINERALS LIMITED, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008To:Principal Place of Business : MUSGRAVE MINERALS LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :MUSGRAVE MINERALS LIMITED, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxxxx997RECORDED:12:52:43 22 December 2021 |
Caveat | 683328 | Lodged:16:10:12 09 August 2023Caveat Type:Consent CaveatCaveator:EVOLUTION MINING (CUE) PTY LIMITEDShares Caveated:100/100 shares MUSGRAVE MINERALS LIMITEDRECORDED:16:10:12 09 August 2023WITHDRAWN:09:50:41 24 April 2024 |
Extension / Renewal of Term | 694092 | Lodged:09:32 16 January 2024Applied For Period:2 YearsRECORDED:09:32 16 January 2024GRANTED:07 May 2024Granted Period:2 YearsTerm Extended To:29/01/2026 |
Application to Amend | 702109 | Lodged:14:23:15 23 April 2024Amending:Address (Including DTC Details)From:Principal Place of Business : MUSGRAVE MINERALS LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997 and DTC :MUSGRAVE MINERALS LIMITED, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxxxxxx997To:Principal Place of Business : MUSGRAVE MINERALS LIMITED, C/- RAMELIUS RESOURCES LTD, PO BOX 6070, EAST PERTH, WA, 6892, xxxxxxxxx@rameliusresources.com.au, xxxxxxx063 and DTC :MUSGRAVE MINERALS LIMITED, TENEMENT MANAGER, C/- RAMELIUS RESOURCES LTD, PO BOX 6070, EAST PERTH, WA, 6892, xxxxxxxxx@rameliusresources.com.au, xxxxxxx063RECORDED:14:23:15 23 April 2024 |
Withdrawal of Dealing | 702167 | Lodged:09:50:41 24 April 2024In respect to:Caveat 683328RECORDED:09:50:41 24 April 2024 |
Application to Amend | 736733 | Lodged:12:26:34 26 June 2025Amending:Address (Including DTC Details)From:Principal Place of Business : MUSGRAVE MINERALS LIMITED, C/- RAMELIUS RESOURCES LTD, PO BOX 6070, EAST PERTH, WA, 6892, xxxxxxxxx@rameliusresources.com.au, xxxxxxx063 and DTC :MUSGRAVE MINERALS LIMITED, TENEMENT MANAGER, C/- RAMELIUS RESOURCES LTD, PO BOX 6070, EAST PERTH, WA, 6892, xxxxxxxxx@rameliusresources.com.au, xxxxxxx063To:Principal Place of Business : MUSGRAVE MINERALS LIMITED, C/- RAMELIUS RESOURCES LTD, PO BOX 2714, CLOISTERS SQUARE PO, WA, 6850, xxxxxxxxx@rameliusresources.com.au, xxxxxxx063 and DTC :MUSGRAVE MINERALS LIMITED, TENEMENT MANAGER, C/- RAMELIUS RESOURCES LTD, PO BOX 2714, CLOISTERS SQUARE PO, WA, 6850, xxxxxxxxx@rameliusresources.com.au, xxxxxxx063RECORDED:12:26:34 26 June 2025 |