Extracted from MTO on 02-Jul-2025 00:49,
last changed 26-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 18-Sep-2019 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Sep-2019 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Sep-2019 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 18-Sep-2019 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 18-Sep-2019 | |
6 | 1 | No activities being carried out within the proposed railway corridor (designated FNA 9031 ) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent. | 18-Sep-2019 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 18-Sep-2019 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Sep-2019 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Sep-2019 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 18-Sep-2019 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 18-Sep-2019 | |
6 | 1 | No activities being carried out within the proposed railway corridor (designated FNA 9031 ) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent. | 18-Sep-2019 | |
Type | Number | Details |
Application to Amend | 622885 | Lodged:16:10:03 19 May 2021Amending:Address (Including DTC Details)From:ZEEDAM ENTERPRISES PTY LTD, KARL WOLZAK, C/- RESOURCE MAPPING PTY LTD, PO BOX 541, MT HAWTHORN, WA, 6915, xxxxxx@wantree.com.au, xxxxxxx317To:ZEEDAM ENTERPRISES PTY LTD, ZEEDAM ENTERPRISES PTY LTD, C/- MKII CONSULTING PTY LTD, PO BOX 753, WEMBLEY, WA, 6913, xxxxxx@mk2consulting.com.au, xxxxxxxxx555RECORDED:16:10:03 19 May 2021 |
Forfeiture | 649306 | Initiated:16/05/2022 for non-compliance with reporting requirementsRECORDED:07:55 16 May 2022Notice Issued:Regulation 50 Notice sent 16/05/2022 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:20/06/2022FINALISED:Order by Minister on 01 August 2022 that E 20/946 be Penalty Imposed |
Fine | 654956 | Fine in respect to:Forfeiture Process 649306Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$450.00Notification date:03/08/2022Due date:08/09/2022Pursuant to:Section 96A(5)RECORDED:03 August 2022PAYMENT RECEIVED:16 August 2022FINALISED:16 August 2022Receipt Number:26133006366Amount:$450.00Remaining balance:$0.00 |
Extension / Renewal of Term | 714844 | Lodged:10:03:16 17 September 2024Applied For Period:5 YearsRECORDED:10:03:16 17 September 2024GRANTED:10 December 2024Granted Period:5 YearsTerm Extended To:17/09/2029 |