Extracted from MTO on 06-Jul-2025 00:37,
last changed 18-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 28-Oct-2010 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 28-Oct-2010 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 28-Oct-2010 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 28-Oct-2010 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 28-Oct-2010 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 28-Oct-2010 | |
7 | 1 | In respect of the area covered by this licence if the Yugunga-Nya People (being the applicants in Federal Court Application No/s. WAD 6132 of 1998 (WC99/46) send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Yugunga- Nya People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Yamatji Land and Sea Council. | 28-Oct-2010 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 28-Oct-2010 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 28-Oct-2010 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 28-Oct-2010 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 28-Oct-2010 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 28-Oct-2010 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 28-Oct-2010 | |
7 | 1 | In respect of the area covered by this licence if the Yugunga-Nya People (being the applicants in Federal Court Application No/s. WAD 6132 of 1998 (WC99/46) send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Yugunga- Nya People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Yamatji Land and Sea Council. | 28-Oct-2010 | |
Type | Number | Details |
Application to Amend | 245716 | Lodged:11:31 20 September 2011Amending:AddressFrom:CULLEN EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 8638 PERTH BUSINESS CENTRE, PERTH, WA, 6849To:CULLEN EXPLORATION PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931RECORDED:11:31 20 September 2011 |
Partial Surrender - Voluntary | 413013 | Lodged:15:05 11 December 2012Surrendered Blocks:MEEKATHARRA 2860 n, r, s, w, x
MEEKATHARRA 2932 b, c, g, l, m, q, v
MEEKATHARRA 3003 d, e, j, k, n, o, p, r, s, t, u, w, x, y
MEEKATHARRA 3004 a, f, l, q
MEEKATHARRA 3075 b, cSurrendered Total:32 BL.REGISTERED:15:05 11 December 2012 |
Extension / Renewal of Term | 476421 | Lodged:15:45 26 October 2015Applied For Period:5 YearsRECORDED:15:45 26 October 2015GRANTED:29 December 2015Granted Period:5 YearsTerm Extended To:27/10/2020 |
Extension of Time | 480481 | Lodged:15:47 19 January 2016Type:Stat DecRECORDED:15:47 19 January 2016APPROVED:15:48 19 January 2016Time extended to 3 February 2016 |
Partial Surrender - Voluntary | 516747 | Lodged:16:15:52 19 October 2017Surrendered Blocks:MEEKATHARRA 2858 p, r, s, w, x
MEEKATHARRA 2859 l, m, n, o
MEEKATHARRA 2860 v
MEEKATHARRA 2931 e, k, o, p, t, u, y, z
MEEKATHARRA 2932 a, fSurrendered Total:20 BL.REGISTERED:16:15:52 19 October 2017 |
Application to Amend | 533221 | Lodged:09:39:14 20 June 2018Amending:Address (Including DTC Details)From:Principal Place of Business : CULLEN EXPLORATION PTY LIMITED, SAME AS CORRESPONDENCE and DTC :CULLEN EXPLORATION PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931To:Principal Place of Business : CULLEN EXPLORATION PTY LIMITED, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxx997 and DTC :CULLEN EXPLORATION PTY LIMITED, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxx997RECORDED:09:39:14 20 June 2018 |
Forfeiture | 554881 | Initiated:10/05/2019 for non-compliance with expenditure conditionsRECORDED:09:10 29 May 2019Notice Issued:Regulation 50 Notice sent 10/05/2019 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:24/06/2019FINALISED:Order by Minister on 26 June 2019 that E 20/714 be Penalty Imposed |
Fine | 557132 | Fine in respect to:Forfeiture Process 554881Fine reason:Non-compliance with expenditure obligationsPenalty amount:$3,897.00Notification date:26/06/2019Due date:31/07/2019Pursuant to:Section 96A(5)RECORDED:26 June 2019PAYMENT RECEIVED:10 July 2019FINALISED:10 July 2019Receipt Number:95138231006Amount:$3,897.00Remaining balance:$0.00 |
Extension / Renewal of Term | 587530 | Lodged:11:07:19 02 October 2020Applied For Period:2 YearsRECORDED:11:07:19 02 October 2020GRANTED:23 December 2020Granted Period:2 YearsTerm Extended To:27/10/2022 |
Extension / Renewal of Term | 659081 | Lodged:15:07:41 19 September 2022Applied For Period:2 YearsRECORDED:15:07:41 19 September 2022GRANTED:10 February 2023Granted Period:2 YearsTerm Extended To:27/10/2024 |
Extension / Renewal of Term | 716807 | Lodged:09:08:31 14 October 2024Applied For Period:2 YearsRECORDED:09:08:31 14 October 2024GRANTED:20 December 2024Granted Period:2 YearsTerm Extended To:27/10/2026 |