Extracted from MTO on 02-Jul-2025 01:19,
last changed 21-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 06-Feb-2007 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 06-Feb-2007 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 06-Feb-2007 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 06-Feb-2007 | |
5 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 06-Feb-2007 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 06-Feb-2007 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing mining on Use and Benefit of Aborigines Reserves 16670 & 21805. | 06-Feb-2007 | |
8 | 1 | The rights of ingress to and egress from Miscellaneous Licence 20/46 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 06-Feb-2007 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 06-Feb-2007 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 06-Feb-2007 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 06-Feb-2007 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 06-Feb-2007 | |
5 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 06-Feb-2007 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 06-Feb-2007 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing mining on Use and Benefit of Aborigines Reserves 16670 & 21805. | 06-Feb-2007 | |
8 | 1 | The rights of ingress to and egress from Miscellaneous Licence 20/46 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 06-Feb-2007 | |
Type | Number | Details |
Objection | MM80/056 | Lodged 3:01:00 PM on 24 Apr 2006 by APPLICANTS FOR THE WAJARRI YAMATJI NATIVE TITLE CLAIMRECORDED 3:01 PM 24 Apr 2006WITHDRAWN 4:30 PM 09 Jun 2006 |
Application to Amend | 316907 | Lodged:15:00 30 March 2009Amending:NameFrom:MIDWEST CORPORATION LTDTo:SINOSTEEL MIDWEST CORPORATION LIMITEDRECORDED:15:00 30 March 2009 |
Extension / Renewal of Term | 390505 | Lodged:08:30 02 February 2012Applied For Period:5 YearsRECORDED:08:30 02 February 2012GRANTED:14 February 2012Granted Period:5 YearsTerm Extended To:05/02/2017 |
Deferral of Drop Off | 390599 | Lodged:16:10 02 February 2012RECORDED:16:10 02 February 2012GRANTED:14 February 2012 |
Plaint | 397638 | Lodged:11:00 17 May 2012Plaintiffs:VIPER HOLDINGS PTY LTDSeeking:For orders:
For compensation pursuant to Section 123 of the Mining Act 1978; and
For costs.Respondents:SINOSTEEL MIDWEST CORPORATION LIMITEDRECORDED:11:00 17 May 2012Warden's Determination:Dismissed 10:00 01 November 2013There be no order as to the costs of the Plaints and all previous costs orders, including reserved costs be vacated. |
Amalgamation | 489606 | Lodged:15:55 29 June 2016Amalgamating:Whole of former P 20/1658Situated within:External boundaries of E 20/635-IAmalgamating:Portion of P 20/2080-ISituated within:External boundaries of E 20/635-IAmalgamating:Whole of former P 20/2097Situated within:External boundaries of E 20/635-IAmalgamating:Whole of former P 20/2099Situated within:External boundaries of E 20/635-IGranted 22/12/2016 in respect to P 20/1658Granted 22/12/2016 in respect to P 20/2080-IGranted 22/12/2016 in respect to P 20/2097Granted 22/12/2016 in respect to P 20/2099 |
Application to Amend | 490195 | Lodged:13:03:58 07 July 2016Amending:Address (Including DTC Details)From:SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, WA, 6849To:SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:13:03:58 07 July 2016 |
Extension / Renewal of Term | 500342 | Lodged:14:34:38 25 January 2017Applied For Period:2 YearsRECORDED:14:34:38 25 January 2017GRANTED:28 April 2017Granted Period:2 YearsTerm Extended To:05/02/2019 |
Excess Tonnage | 500668 | Lodged:08:37:58 02 February 2017RECORDED:08:37:58 02 February 2017GRANTED:09:51:40 08 February 2017Approved for an additional 181 tonnes. |
Extension / Renewal of Term | 546931 | Lodged:14:28:30 31 January 2019Applied For Period:2 YearsRECORDED:14:28:30 31 January 2019GRANTED:11 June 2019Granted Period:2 YearsTerm Extended To:05/02/2021 |
Application to Amend | 590049 | Lodged:14:30 11 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxx977REJECTED:14:30 11 November 2020 |
Application to Amend | 590404 | Lodged:16:09:27 13 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:16:09:27 13 November 2020 |
Extension / Renewal of Term | 595289 | Lodged:16:08:11 03 February 2021Applied For Period:2 YearsRECORDED:16:08:11 03 February 2021GRANTED:08 April 2021Granted Period:2 YearsTerm Extended To:05/02/2023 |
Extension / Renewal of Term | 668168 | Lodged:08:30 03 February 2023Applied For Period:2 YearsRECORDED:08:30 03 February 2023GRANTED:14 June 2023Granted Period:2 YearsTerm Extended To:05/02/2025 |
Extension / Renewal of Term | 724657 | Lodged:14:08:09 30 January 2025Applied For Period:2 YearsRECORDED:14:08:09 30 January 2025GRANTED:20 June 2025Granted Period:2 YearsTerm Extended To:05/02/2027 |
Extension of Time | 735623 | Lodged:12:23:53 12 June 2025Type:OtherRECORDED:12:23:53 12 June 2025APPROVED:17:13:23 19 June 2025Time to lodge extended to 22 May 2025 |