Extracted from MTO on 07-Jul-2025 00:59,
last changed 18-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 29-Sep-2010 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 19-Dec-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 29-Sep-2010 | 18-Dec-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 29-Sep-2010 | |
4 | 2 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 19-Dec-2024 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 29-Sep-2010 | 18-Dec-2024 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 29-Sep-2010 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 29-Sep-2010 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 20/53 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 29-Sep-2010 | |
8 | 1 | No activities being carried out within the proposed railway corridor (designated FNA 9031) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent. | 29-Sep-2010 | |
9 | 2 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- “Sinosteel Midwest Corporation Limited – Environmental Management Plan (Exploration)” dated 29 September 2021 signed by P. Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-122884 as Object ID A73805900
| 19-Dec-2024 | |
9 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (POW REG ID 78084) “Sinosteel Midwest Corporation Limited – Environmental Management Plan (Exploration)” dated 11 April 2019 signed by P. Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-78084 as Doc ID 6517596
| 15-May-2019 | 18-Dec-2024 |
10 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 19-Dec-2024 | |
11 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 19-Dec-2024 | |
12 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 19-Dec-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 29-Sep-2010 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 19-Dec-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 29-Sep-2010 | 18-Dec-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 29-Sep-2010 | |
4 | 2 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 19-Dec-2024 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 29-Sep-2010 | 18-Dec-2024 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 29-Sep-2010 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 29-Sep-2010 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 20/53 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 29-Sep-2010 | |
8 | 1 | No activities being carried out within the proposed railway corridor (designated FNA 9031) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent. | 29-Sep-2010 | |
9 | 2 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- “Sinosteel Midwest Corporation Limited – Environmental Management Plan (Exploration)” dated 29 September 2021 signed by P. Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-122884 as Object ID A73805900
| 19-Dec-2024 | |
9 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (POW REG ID 78084) “Sinosteel Midwest Corporation Limited – Environmental Management Plan (Exploration)” dated 11 April 2019 signed by P. Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-78084 as Doc ID 6517596
| 15-May-2019 | 18-Dec-2024 |
10 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 19-Dec-2024 | |
11 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 19-Dec-2024 | |
12 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 19-Dec-2024 | |
Type | Number | Details |
Objection | MM67/056 | Lodged 10:37:00 AM on 10 Mar 2006 by MURCHISON METALS LTDRECORDED 10:37 AM 10 Mar 2006WITHDRAWN 11:30 AM 31 Aug 2006 |
Objection | MM70/056 | Lodged 3:44:00 PM on 03 Apr 2006 by ST. BARBARA MINES LTDRECORDED 3:44 PM 03 Apr 2006WITHDRAWN 10:00 AM 21 Sep 2007 |
Application to Amend | 316907 | Lodged:15:00 30 March 2009Amending:NameFrom:MIDWEST CORPORATION LTDTo:SINOSTEEL MIDWEST CORPORATION LIMITEDRECORDED:15:00 30 March 2009 |
Extension of Time | 385939 | Lodged:15:41 25 November 2011Type:Form 5RECORDED:15:41 25 November 2011APPROVED:15:51:14 25 November 2011Time to lodge Form 5 extended to 16 December 2011 |
Extension / Renewal of Term | 474564 | Lodged:08:30 18 September 2015Applied For Period:5 YearsRECORDED:08:30 18 September 2015GRANTED:03 December 2015Granted Period:5 YearsTerm Extended To:28/09/2020 |
Application to Amend | 490195 | Lodged:13:03:58 07 July 2016Amending:Address (Including DTC Details)From:SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, WA, 6849To:SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:13:03:58 07 July 2016 |
Extension of Time | 519047 | Lodged:16:03:11 24 November 2017Type:Form 5RECORDED:16:03:11 24 November 2017APPROVED:17:02:59 01 December 2017Time to lodge extended to 15 Dec 2017 |
Excess Tonnage | 546555 | Lodged:14:30:35 24 January 2019RECORDED:14:30:35 24 January 2019GRANTED:11:25:48 15 February 2019For an additional 315 tonnes |
Excess Tonnage | 570610 | Lodged:10:00:44 21 January 2020RECORDED:10:00:44 21 January 2020GRANTED:12:14:22 28 April 2020For an additional 1,949 tonnes |
Extension / Renewal of Term | 586980 | Lodged:12:51:28 24 September 2020Applied For Period:2 YearsRECORDED:12:51:28 24 September 2020GRANTED:05 January 2021Granted Period:2 YearsTerm Extended To:28/09/2022 |
Application to Amend | 590049 | Lodged:14:30 11 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxx977REJECTED:14:30 11 November 2020 |
Application to Amend | 590404 | Lodged:16:09:27 13 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:16:09:27 13 November 2020 |
Extension / Renewal of Term | 659365 | Lodged:08:30 23 September 2022Applied For Period:2 YearsRECORDED:08:30 23 September 2022GRANTED:24 February 2023Granted Period:2 YearsTerm Extended To:28/09/2024 |
Extension / Renewal of Term | 715170 | Lodged:16:29:15 19 September 2024Applied For Period:2 YearsRECORDED:16:29:15 19 September 2024GRANTED:09 December 2024Granted Period:2 YearsTerm Extended To:28/09/2026 |