Extracted from MTO on 06-Jul-2025 01:41,
last changed 03-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 24-Apr-2006 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 24-Apr-2006 | 30-Oct-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 24-Apr-2006 | |
4 | 2 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 31-Oct-2024 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 24-Apr-2006 | 30-Oct-2024 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 24-Apr-2006 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 24-Apr-2006 | |
7 | 2 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (Pow Reg ID 79321) "Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)" dated 11 April 2019 signed by P Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-79321 as Doc ID 6475965;
- (PoW Reg ID 116879) “Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)” dated 29 September 2021 submitted by Sinosteel Midwest Corporation Limited, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-116879 as Doc ID 995405;
- (PoW Reg ID 116879) “Programme of Work on E 20/459-I, E 20/546-I and E 20/753-I for Sinosteel Midwest Corporation Limited” dated 28 February 2023 submitted by Roger Kemp, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-116879 as Doc ID 9954067
| 26-Apr-2023 | |
7 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (Pow Reg ID 79321) "Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)" dated 11 April 2019 signed by P Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-79321 as Doc ID 6475965
| 02-May-2019 | 25-Apr-2023 |
8 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
9 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 31-Oct-2024 | |
10 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 31-Oct-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 24-Apr-2006 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 24-Apr-2006 | 30-Oct-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 24-Apr-2006 | |
4 | 2 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 31-Oct-2024 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 24-Apr-2006 | 30-Oct-2024 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 24-Apr-2006 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 24-Apr-2006 | |
7 | 2 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (Pow Reg ID 79321) "Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)" dated 11 April 2019 signed by P Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-79321 as Doc ID 6475965;
- (PoW Reg ID 116879) “Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)” dated 29 September 2021 submitted by Sinosteel Midwest Corporation Limited, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-116879 as Doc ID 995405;
- (PoW Reg ID 116879) “Programme of Work on E 20/459-I, E 20/546-I and E 20/753-I for Sinosteel Midwest Corporation Limited” dated 28 February 2023 submitted by Roger Kemp, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-116879 as Doc ID 9954067
| 26-Apr-2023 | |
7 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (Pow Reg ID 79321) "Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)" dated 11 April 2019 signed by P Hogan, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-79321 as Doc ID 6475965
| 02-May-2019 | 25-Apr-2023 |
8 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
9 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 31-Oct-2024 | |
10 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 31-Oct-2024 | |
Type | Number | Details |
Extension of Time | 183354 | Lodged 8:30 AM on 08 Aug 2003 to lodge Security.Approved by the Warden on 11 Aug 2003 |
Application to Amend | 369H/067 | Lodged 9:30 AM on 14 Aug 2006 amending the address for Sipa Exploration NL to read: "PO Box 1183, WEST PERTH WA 6872"RECORDED 9:30 AM 14 Aug 2006 |
Fine | 294123 | Penalty of $1,740 imposed pursuant to section 96A(5) for non-compliance with the expenditure commitment.
Date Due: 30 Jul 2008 Date Paid: 16 Jul 2008RECORDED 30 Jun 2008Penalty amount:$1,740.00Notification date:30/06/2008Due date:30/07/2008Pursuant to:Section 96A(5)RECORDED:30 June 2008PAYMENT RECEIVED:16 July 2008FINALISED:16 July 2008Receipt Number:53811Amount:$1,740.00 |
Partial Surrender - Compulsory | 318446 | Lodged:13:20 22 April 2009Section:Section 65 (1)(a)Surrendered Blocks:MEEKATHARRA 2633 y, z
MEEKATHARRA 2634 o, p, q, r, s, t, u, v, w, x
MEEKATHARRA 2635 lSurrendered Total:13 BL.REGISTERED:23:59:59 23 April 2009Surrendered area to be released 08:30:00 05/06/2009 under Section 65(5)Surrendered area released 08:30:00 05/06/2009 under Section 65(5) |
Exemption from Drop-off | 345220 | Lodged:15:40 21 April 2010for relief from the provisions of Section 65(1)(b)RECORDED:15:40 21 April 2010GRANTED:23 August 2010 |
Application to Amend | 348611 | Lodged:15:20 02 June 2010Amending:AddressFrom:SINOSTEEL MIDWEST CORPORATION LIMITED, 7 RHEOLA STREET, WEST PERTH, WA, 6005To:SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION AND MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, WA, 6849RECORDED:15:20 02 June 2010 |
Extension / Renewal of Term | 369585 | Lodged:16:01 13 April 2011Applied For Period:2 YearsRECORDED:16:01 13 April 2011GRANTED:15 July 2011Granted Period:2 YearsTerm Extended To:23/04/2013 |
Extension / Renewal of Term | 421337 | Lodged:15:08:37 19 April 2013Applied For Period:2 YearsRECORDED:15:08:37 19 April 2013GRANTED:24 May 2013Granted Period:2 YearsTerm Extended To:23/04/2015 |
Extension / Renewal of Term | 466071 | Lodged:15:09:24 21 April 2015Applied For Period:1 YearsRECORDED:15:09:24 21 April 2015GRANTED:07 August 2015Granted Period:1 YearsTerm Extended To:23/04/2016 |
Amalgamation | 470441 | Lodged:15:45 01 July 2015Amalgamating:Whole of former P 20/1961Situated within:External boundaries of E 20/546-IGranted 17/02/2016 in respect to P 20/1961 |
Extension / Renewal of Term | 485391 | Lodged:11:27:56 20 April 2016Applied For Period:1 YearsRECORDED:11:27:56 20 April 2016GRANTED:27 May 2016Granted Period:1 YearsTerm Extended To:23/04/2017 |
Application to Amend | 490195 | Lodged:13:03:58 07 July 2016Amending:Address (Including DTC Details)From:SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, WA, 6849To:SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:13:03:58 07 July 2016 |
Extension / Renewal of Term | 504529 | Lodged:08:30 13 April 2017Applied For Period:1 YearsRECORDED:08:30 13 April 2017GRANTED:18 May 2017Granted Period:1 YearsTerm Extended To:23/04/2018 |
Extension / Renewal of Term | 528245 | Lodged:09:06:25 18 April 2018Applied For Period:1 YearsRECORDED:09:06:25 18 April 2018GRANTED:21 June 2018Granted Period:1 YearsTerm Extended To:23/04/2019 |
Extension / Renewal of Term | 551675 | Lodged:11:11:55 15 April 2019Applied For Period:1 YearsRECORDED:11:11:55 15 April 2019GRANTED:05 July 2019Granted Period:1 YearsTerm Extended To:23/04/2020 |
Extension / Renewal of Term | 576306 | Lodged:14:21:52 17 April 2020Applied For Period:1 YearsRECORDED:14:21:52 17 April 2020GRANTED:23 June 2020Granted Period:1 YearsTerm Extended To:23/04/2021 |
Application to Amend | 590049 | Lodged:14:30 11 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxx977REJECTED:14:30 11 November 2020 |
Application to Amend | 590404 | Lodged:16:09:27 13 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:16:09:27 13 November 2020 |
Caveat | 590748 | Lodged:08:30 19 November 2020Caveat Type:Absolute CaveatCaveator:VOX ROYALTY AUSTRALIA PTY LTDShares Caveated:100/100 shares SINOSTEEL MIDWEST CORPORATION LIMITEDRECORDED:08:30 19 November 2020 |
Extension / Renewal of Term | 620959 | Lodged:12:04:01 22 April 2021Applied For Period:1 YearsRECORDED:12:04:01 22 April 2021GRANTED:17 August 2021Granted Period:1 YearsTerm Extended To:23/04/2022 |
Extension / Renewal of Term | 647586 | Lodged:11:23:12 21 April 2022Applied For Period:1 YearsRECORDED:11:23:12 21 April 2022GRANTED:07 September 2022Granted Period:1 YearsTerm Extended To:23/04/2023 |
Extension / Renewal of Term | 673893 | Lodged:16:26:13 19 April 2023Applied For Period:1 YearsRECORDED:16:26:13 19 April 2023GRANTED:31 July 2023Granted Period:1 YearsTerm Extended To:23/04/2024 |
Extension / Renewal of Term | 701955 | Lodged:11:40:03 22 April 2024Applied For Period:1 YearsRECORDED:11:40:03 22 April 2024GRANTED:31 July 2024Granted Period:1 YearsTerm Extended To:23/04/2025 |
Extension / Renewal of Term | 731601 | Lodged:12:39:53 22 April 2025Applied For Period:1 YearsRECORDED:12:39:53 22 April 2025GRANTED:02 July 2025Granted Period:1 YearsTerm Extended To:23/04/2026 |