Extracted from MTO on 15-Jul-2025 01:13,
last changed 18-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 25-Sep-2006 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 25-Sep-2006 | 30-Oct-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 25-Sep-2006 | |
4 | 2 | Unless the written approval of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 31-Oct-2024 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 25-Sep-2006 | 30-Oct-2024 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 25-Sep-2006 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 25-Sep-2006 | |
7 | 1 | No interference with Geodetic Survey Station NMF 616 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 25-Sep-2006 | |
8 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
9 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 31-Oct-2024 | |
10 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 31-Oct-2024 | |
11 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (PoW RegID 122742) “Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)” dated 29 September 2021 submitted by Sinosteel Midwest Corporation Limited, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-122742 as Object ID A72223769.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 31-Oct-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 25-Sep-2006 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 25-Sep-2006 | 30-Oct-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 25-Sep-2006 | |
4 | 2 | Unless the written approval of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 31-Oct-2024 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 25-Sep-2006 | 30-Oct-2024 |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 25-Sep-2006 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 25-Sep-2006 | |
7 | 1 | No interference with Geodetic Survey Station NMF 616 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 25-Sep-2006 | |
8 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 31-Oct-2024 | |
9 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 31-Oct-2024 | |
10 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 31-Oct-2024 | |
11 | 1 | The construction and operation of the project and measures to protect the environment to be carried out in accordance with the document titled:
- (PoW RegID 122742) “Sinosteel Midwest Corporation Limited - Environmental Management Plan (Exploration)” dated 29 September 2021 submitted by Sinosteel Midwest Corporation Limited, and retained on Department of Mines, Industry Regulation and Safety File No. EARS-POW-122742 as Object ID A72223769.
Where a difference exists between the above document(s) and the following conditions, then the following conditions shall prevail. | 31-Oct-2024 | |
Type | Number | Details |
Application to Amend | MM12/990 | Lodged 10:00:00 AM on 15 Oct 1999 amending the locality on form 21 attachment 1 to read: Weld Range amending million plan name on form 21 attachment 1 to read - MeekatharraREGISTERED 10:00 AM 15 Oct 1999 |
Application to Amend | 650H/012 | Lodged 11:20 AM on 14 Feb 2002 amending address to read " Ground floor , 17 Ord St West Perth WA 6005"REGISTERED 11:20 AM 14 Feb 2002 |
Application to Amend | 316907 | Lodged:15:00 30 March 2009Amending:NameFrom:MIDWEST CORPORATION LTDTo:SINOSTEEL MIDWEST CORPORATION LIMITEDRECORDED:15:00 30 March 2009 |
Copy Document | 317754 | Lodged:16:05 08 April 2009ISSUED:16:05 08 April 2009 |
Exemption from Drop-off | 330099 | Lodged:15:25 14 September 2009For relief from the provisions of Section 65(1)(a)RECORDED:15:25 14 September 2009GRANTED:23 October 2009 |
Caveat | 355626 | Lodged:15:59 15 September 2010Caveat Type:Consent CaveatCaveator:HAMPTON HILL MINING NLShares Caveated:100/100 shares SINOSTEEL MIDWEST CORPORATION LIMITEDRECORDED:15:59 15 September 2010WITHDRAWN:15:38:09 07 April 2017 |
Exemption from Drop-off | 355930 | Lodged:15:26 21 September 2010RECORDED:15:26 21 September 2010GRANTED:24 September 2010 |
Extension / Renewal of Term | 380516 | Lodged:16:20 01 September 2011Applied For Period:2 YearsRECORDED:16:20 01 September 2011GRANTED:06 September 2011Granted Period:2 YearsTerm Extended To:24/09/2013 |
Extension / Renewal of Term | 431732 | Lodged:10:04:36 23 September 2013Applied For Period:2 YearsRECORDED:10:04:36 23 September 2013GRANTED:21 March 2014Granted Period:2 YearsTerm Extended To:24/09/2015 |
Excess Tonnage | 446386 | Lodged:13:34 14 May 2014RECORDED:13:34 14 May 2014An additional 307 tonnesGRANTED:15:17:22 14 May 2014 |
Amalgamation | 472430 | Lodged:15:40 05 August 2015Amalgamating:Whole of former P 20/1962Situated within:External boundaries of E 20/457-IAmalgamating:Whole of former P 20/1990Situated within:External boundaries of E 20/457-IAmalgamating:Whole of former P 20/2003Situated within:External boundaries of E 20/457-IAmalgamating:Whole of P 20/2077-ISituated within:External boundaries of E 20/457-IAmalgamating:Whole of P 20/2078-ISituated within:External boundaries of E 20/457-IGranted 17/02/2016 in respect to P 20/1962Granted 17/02/2016 in respect to P 20/1990Granted 17/02/2016 in respect to P 20/2003Granted 17/02/2016 in respect to P 20/2077-IGranted 17/02/2016 in respect to P 20/2078-I |
Extension / Renewal of Term | 474541 | Lodged:14:24:04 17 September 2015Applied For Period:1 YearsRECORDED:14:24:04 17 September 2015GRANTED:18 December 2015Granted Period:1 YearsTerm Extended To:24/09/2016 |
Excess Tonnage | 481029 | Lodged:15:33 28 January 2016RECORDED:15:33 28 January 2016GRANTED:11:45:43 01 April 2016Approved for additional 299 tonnes |
Application to Amend | 490195 | Lodged:13:03:58 07 July 2016Amending:Address (Including DTC Details)From:SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, WA, 6849To:SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:13:03:58 07 July 2016 |
Extension / Renewal of Term | 493887 | Lodged:14:16:20 14 September 2016Applied For Period:1 YearsRECORDED:14:16:20 14 September 2016GRANTED:13 January 2017Granted Period:1 YearsTerm Extended To:24/09/2017 |
Withdrawal of Dealing | 504187 | Lodged:15:38:09 07 April 2017In respect to:Caveat 355626RECORDED:15:38:09 07 April 2017 |
Extension / Renewal of Term | 514464 | Lodged:13:49:54 13 September 2017Applied For Period:1 YearsRECORDED:13:49:54 13 September 2017GRANTED:04 April 2018Granted Period:1 YearsTerm Extended To:24/09/2018 |
Extension / Renewal of Term | 539420 | Lodged:09:59:48 20 September 2018Applied For Period:1 YearsRECORDED:09:59:48 20 September 2018GRANTED:17 December 2018Granted Period:1 YearsTerm Extended To:24/09/2019 |
Extension / Renewal of Term | 562777 | Lodged:09:29:39 11 September 2019Applied For Period:1 YearsRECORDED:09:29:39 11 September 2019GRANTED:17 December 2019Granted Period:1 YearsTerm Extended To:24/09/2020 |
Extension / Renewal of Term | 586422 | Lodged:11:45:39 17 September 2020Applied For Period:1 YearsRECORDED:11:45:39 17 September 2020GRANTED:20 November 2020Granted Period:1 YearsTerm Extended To:24/09/2021 |
Application to Amend | 590049 | Lodged:14:30 11 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxx977REJECTED:14:30 11 November 2020 |
Application to Amend | 590404 | Lodged:16:09:27 13 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, SAME AS CORRESPONDENCE and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:Principal Place of Business : SINOSTEEL MIDWEST CORPORATION LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400 and DTC :SINOSTEEL MIDWEST CORPORATION LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:16:09:27 13 November 2020 |
Extension / Renewal of Term | 632219 | Lodged:14:46:37 13 September 2021Applied For Period:1 YearsRECORDED:14:46:37 13 September 2021GRANTED:12 January 2022Granted Period:1 YearsTerm Extended To:24/09/2022 |
Extension / Renewal of Term | 659354 | Lodged:16:15:42 21 September 2022Applied For Period:1 YearsRECORDED:16:15:42 21 September 2022GRANTED:09 February 2023Granted Period:1 YearsTerm Extended To:24/09/2023 |
Extension / Renewal of Term | 686042 | Lodged:08:30 15 September 2023Applied For Period:1 YearsRECORDED:08:30 15 September 2023GRANTED:22 December 2023Granted Period:1 YearsTerm Extended To:24/09/2024 |
Extension / Renewal of Term | 715153 | Lodged:15:06:39 19 September 2024Applied For Period:1 YearsRECORDED:15:06:39 19 September 2024GRANTED:09 December 2024Granted Period:1 YearsTerm Extended To:24/09/2025 |