# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 17-Nov-2021 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 17-Nov-2021 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 17-Nov-2021 | |
4 | 1 | The rights of ingress to and egress from Miscellaneous Licence 16/35 and 16/93 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 17-Nov-2021 | |
| 1 | In respect to the area designated as CPL 50 (Credo) in TENGRAPH the following conditions apply: | 17-Nov-2021 | |
5 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 17-Nov-2021 | |
6 | 1 | The licensee, at their expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 17-Nov-2021 | |
7 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 17-Nov-2021 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 17-Nov-2021 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 17-Nov-2021 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 17-Nov-2021 | |
4 | 1 | The rights of ingress to and egress from Miscellaneous Licence 16/35 and 16/93 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 17-Nov-2021 | |
| 1 | In respect to the area designated as CPL 50 (Credo) in TENGRAPH the following conditions apply: | 17-Nov-2021 | |
5 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 17-Nov-2021 | |
6 | 1 | The licensee, at their expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 17-Nov-2021 | |
7 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 17-Nov-2021 | |
Type | Number | Details |
Objection | 531422 | Lodged:14:50:28 29 May 2018Objectors:HAYES MINING PTY LTDObjection Type:Tenement ApplicationRECORDED:14:50:28 29 May 2018FINALISED:14:39:11 17 February 2021Wardens Decision Made on:16:30 10 February 2021Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent. |
Objection | 531423 | Lodged:14:50:28 29 May 2018Objectors:EVOLUTION MINING (PHOENIX) PTY LIMITEDObjection Type:Tenement ApplicationRECORDED:14:50:28 29 May 2018FINALISED:14:40:14 17 February 2021Wardens Decision Made on:16:30 10 February 2021Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent. |
Amalgamation | 636143 | Lodged:08:30 19 November 2021Amalgamating:Portion of former P 16/2796Situated within:External boundaries of E 16/509Granted 28/07/2022 in respect to P 16/2796 |
Forfeiture | 733215 | Initiated:30/04/2025 for non-compliance with expenditure conditionsRECORDED:15:50 07 January 2025FINALISED:Order by Minister on 02 July 2025 that E 16/509 be No Penalty ImposedNotice Issued:Regulation 50 Notice sent 30/04/2025 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:03/06/2025 |
Extension of Time | 724983 | Lodged:15:44:14 04 February 2025Type:Stat DecRECORDED:15:44:14 04 February 2025APPROVED:10:36:29 06 February 2025Time extended to lodge statutory declaration in support of the application by COB 18 February 2025 |
Referred to Native Title Date | Referral Type | Current Status | Procedure | Details | Objections | Water Comments | Determination Areas | Claims | Representative Area Bodies |
21-Jan-2022 | Tenement Amalgamation | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2022-02-092022-06-09CLEARED - Expedited Applies2022-07-2521.88159 HA30202S1204552E28.7km W'ly of Ora Banda | WO2022/03652022-03-17WC2017/007Objection Withdrawn2022-07-21 | | | Marlinyu Ghoorlie(WC2017/007)WC2017/007WAD647/2017trueRegisteredMaduwongga(WC2017/001)WC2017/001WAD186/2017trueDismissed | 13GoldfieldsNative Title Services Goldfields |
12-Apr-2021 | Tenement Application | Expedited Procedure : Native Title Cleared - Expedited Applies | Expedited Procedure | 2021-05-052021-09-05CLEARED - Expedited Applies2021-11-1715 BL301910S120436E33.3km W'ly of Ora Banda | WO2021/09522021-05-06WC2017/007Objection Withdrawn2021-11-15 | | | Maduwongga(WC2017/001)WC2017/001WAD186/2017trueDismissedMarlinyu Ghoorlie(WC2017/007)WC2017/007WAD647/2017trueRegistered | 13GoldfieldsNative Title Services Goldfields |