Extracted from MTO on 07-Jul-2025 01:34,
last changed 26-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 06-Feb-2020 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 06-Feb-2020 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 06-Feb-2020 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 06-Feb-2020 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 06-Feb-2020 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 06-Feb-2020 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 06-Feb-2020 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 06-Feb-2020 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 06-Feb-2020 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 06-Feb-2020 | |
Type | Number | Details |
Application to Amend | 559636 | Lodged:12:59:48 01 August 2019Amending:Address (Including DTC Details)From:Principal Place of Business : BLACK MOUNTAIN GOLD LIMITED, 163-167 STIRLING HIGHWAY, NEDLANDS, WA, 6009, xxxxxxxxxxxxxx@intermin.com.au, xxxxxxxxxxx699 and DTC :BLACK MOUNTAIN GOLD LIMITED, BIANCA TAVEIRA, PO BOX 1104, NEDLANDS, WA, 6909, xxxxxxxxxxxxxx@intermin.com.au, xxxxxxxxxxx699To:Principal Place of Business : BLACK MOUNTAIN GOLD LIMITED, 163-167 STIRLING HIGHWAY, NEDLANDS, WA, 6009, xxxxxxxxxxxxxx@horizonminerals.com.au, xxxxxxxxx699 and DTC :BLACK MOUNTAIN GOLD LIMITED, BIANCA TAVEIRA, PO BOX 1104, NEDLANDS, WA, 6909, xxxxxxxxxxxxxx@horizonminerals.com.au, xxxxxxxxx699RECORDED:12:59:48 01 August 2019 |
Application to Amend | 683876 | Lodged:15:26:17 17 August 2023Amending:Address (Including DTC Details)From:BLACK MOUNTAIN GOLD LIMITED, BIANCA TAVEIRA, PO BOX 1104, NEDLANDS, WA, 6909, xxxxxxxxxxxxxx@horizonminerals.com.au, xxxxxxxxx699To:BLACK MOUNTAIN GOLD LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:15:26:17 17 August 2023 |
Caveat | 685980 | Lodged:09:59:40 14 September 2023Caveat Type:Consent CaveatCaveator:METAL HAWK LIMITEDShares Caveated:100/100 shares BLACK MOUNTAIN GOLD LIMITEDRECORDED:09:59:40 14 September 2023 |
Extension / Renewal of Term | 724022 | Lodged:16:09:40 21 January 2025Applied For Period:5 YearsRECORDED:16:09:40 21 January 2025GRANTED:28 April 2025Granted Period:5 YearsTerm Extended To:05/02/2030 |