Extracted from MTO on 07-Jul-2025 00:54,
last changed 28-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 15-Apr-2009 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 15-Apr-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-Apr-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-Apr-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-Apr-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-Apr-2009 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/75 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 15-Apr-2009 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Unnumbered Land Act 11. | 15-Apr-2009 | |
9 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 10 as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 15-Apr-2009 | |
10 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition (9) hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DMP. | 15-Apr-2009 | |
11 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition (9) hereof being approved by the State Mining Engineer, DMP in consultation with the operator of the railway on corridor land. | 15-Apr-2009 | |
12 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition (9) hereof without the prior approval of the operator of the railway on corridor land. | 15-Apr-2009 | |
13 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition (9) hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DMP. | 15-Apr-2009 | |
14 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods Safety Branch, DMP. | 15-Apr-2009 | |
15 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 15-Apr-2009 | |
16 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 15-Apr-2009 | |
17 | 1 | No mining within 25 metres of either side of the Goldfields Pipeline Licence 27 as shown in TENGRAPH.
| 15-Apr-2009 | |
18 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition {17} hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer DMP | 15-Apr-2009 | |
19 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 17 hereof without the prior approval of the operators of the Pipeline Licence 27. | 15-Apr-2009 | |
20 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 17 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer DMP | 15-Apr-2009 | |
21 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Pipeline Licence 27 without the prior written consent of the State Mining Engineer DMP. | 15-Apr-2009 | |
22 | 1 | Mining on the Safety Zone established in Condition 17 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer DMP . | 15-Apr-2009 | |
23 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 17 hereof being at all times preserved for employees, contractors and agents of the operators of the Pipeline Licence 27.
| 15-Apr-2009 | |
24 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Pipeline Licence 27. | 15-Apr-2009 | |
25 | 1 | Consent to explore on Resting Place for Travellers and Stock Reserve 17477 granted on 15/04/2009.
| 15-Apr-2009 | |
| 1 | Consent to mine on Kambalda Nature Reserve No. 33300 granted by the Minister responsible for the Mining Act 1978 subject to the following conditions. | 15-Apr-2009 | |
26 | 1 | Prior to accessing the reserve the licensee consulting with and ensuring that, where required by the Regional/District Manager, Department of Environment and Conservation (DEC), all vehicles, machinery and equipment entering the area are cleaned down to remove soil and plant propagules and adhering to such conditions specified by the Regional/District Manager, DEC, for the prevention of the spread of soil borne diseases. | 15-Apr-2009 | |
27 | 1 | Access to and from and the movement of vehicles and personnel being restricted to ground or seasonal conditions and routes approved by the Regional/District Manager, DEC. | 15-Apr-2009 | |
28 | 1 | The Regional/District Manager, DEC, being supplied with an itinerary and program of the locations of operations on the licence area and informed at least seven days in advance of any changes to that itinerary. | 15-Apr-2009 | |
29 | 1 | Prior to any activity not specified as "environmental disturbance" the licensee preparing a program for each phase of the proposed exploration for approval of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC. | 15-Apr-2009 | |
30 | 1 | Prior to any environmental disturbance, (as defined by the Director, Environment, DMP in agreement with the Executive Director, Department of Environment and Conservation (DEC), the Conservation Commission of WA (CCWA) and the Environmental Protection Authority), the licensee preparing a detailed program for each phase of proposed exploration for approval of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC and the CCWA. This process may result in additional conditions being imposed together with a requirement to lodge an Unconditional Performance Bond if required. This program to describe the environmental impacts and programs for their management and is to include the following :- maps and/or aerial photographs showing the proposed locations of all ground activities and disturbances;
- the purpose, specifications and extent of each activity and disturbance;
- descriptions of all vegetation types (in general terms), land forms, and unusual features likely to be disturbed by such proposed disturbances. The Regional/District Manager, DEC, specifying the level of vegetation description;
- details on proposals that may disturb sensitive terrestrial habitats including any declared rare flora and fauna if applicable;
- techniques, prescriptions, and timetable for rehabilitation of all proposed disturbances;
- undertaking for corrective measures for failed rehabilitation;
- details of water requirements from within the reserve;
- details of refuse disposal; and
- proposals for instruction and supervision of personnel and contractors in respect to environmental conditions.
| 15-Apr-2009 | |
31 | 1 | All rehabilitation being to the satisfaction of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC. | 15-Apr-2009 | |
32 | 1 | At agreed intervals, not greater than 12 monthly, the licensee reporting to the Director, Environment, DMP and the Regional/District Manager, DEC, on the progress of the operation and the rehabilitation program. | 15-Apr-2009 | |
33 | 1 | Prior to the cessation of the exploration/prospecting activity in the reserve, the licensee notifying the Environmental Officer, DMP and the Regional/ District Manager, DEC, and arranging an inspection as required. | 15-Apr-2009 | |
34 | 1 | The licensee making provision to prevent spillage of fuel and discharge of pollutants generally and for all exploration sites being kept free from any rubbish and being left in a clean and tidy state. | 15-Apr-2009 | |
35 | 1 | The licensee not establishing any camp, base works or area, fuelling depot or similar establishment on the licence area unless the site and access has received prior approval of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC. | 15-Apr-2009 | |
36 | 1 | Domestic animals, traps, or firearms not being taken onto the reserve. | 15-Apr-2009 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 15-Apr-2009 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 15-Apr-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-Apr-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-Apr-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-Apr-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-Apr-2009 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/75 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 15-Apr-2009 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Unnumbered Land Act 11. | 15-Apr-2009 | |
9 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 10 as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 15-Apr-2009 | |
10 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition (9) hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer, DMP. | 15-Apr-2009 | |
11 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition (9) hereof being approved by the State Mining Engineer, DMP in consultation with the operator of the railway on corridor land. | 15-Apr-2009 | |
12 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition (9) hereof without the prior approval of the operator of the railway on corridor land. | 15-Apr-2009 | |
13 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition (9) hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer, DMP. | 15-Apr-2009 | |
14 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods Safety Branch, DMP. | 15-Apr-2009 | |
15 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 15-Apr-2009 | |
16 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 15-Apr-2009 | |
17 | 1 | No mining within 25 metres of either side of the Goldfields Pipeline Licence 27 as shown in TENGRAPH.
| 15-Apr-2009 | |
18 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition {17} hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer DMP | 15-Apr-2009 | |
19 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 17 hereof without the prior approval of the operators of the Pipeline Licence 27. | 15-Apr-2009 | |
20 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 17 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer DMP | 15-Apr-2009 | |
21 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Pipeline Licence 27 without the prior written consent of the State Mining Engineer DMP. | 15-Apr-2009 | |
22 | 1 | Mining on the Safety Zone established in Condition 17 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer DMP . | 15-Apr-2009 | |
23 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 17 hereof being at all times preserved for employees, contractors and agents of the operators of the Pipeline Licence 27.
| 15-Apr-2009 | |
24 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Pipeline Licence 27. | 15-Apr-2009 | |
25 | 1 | Consent to explore on Resting Place for Travellers and Stock Reserve 17477 granted on 15/04/2009.
| 15-Apr-2009 | |
| 1 | Consent to mine on Kambalda Nature Reserve No. 33300 granted by the Minister responsible for the Mining Act 1978 subject to the following conditions. | 15-Apr-2009 | |
26 | 1 | Prior to accessing the reserve the licensee consulting with and ensuring that, where required by the Regional/District Manager, Department of Environment and Conservation (DEC), all vehicles, machinery and equipment entering the area are cleaned down to remove soil and plant propagules and adhering to such conditions specified by the Regional/District Manager, DEC, for the prevention of the spread of soil borne diseases. | 15-Apr-2009 | |
27 | 1 | Access to and from and the movement of vehicles and personnel being restricted to ground or seasonal conditions and routes approved by the Regional/District Manager, DEC. | 15-Apr-2009 | |
28 | 1 | The Regional/District Manager, DEC, being supplied with an itinerary and program of the locations of operations on the licence area and informed at least seven days in advance of any changes to that itinerary. | 15-Apr-2009 | |
29 | 1 | Prior to any activity not specified as "environmental disturbance" the licensee preparing a program for each phase of the proposed exploration for approval of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC. | 15-Apr-2009 | |
30 | 1 | Prior to any environmental disturbance, (as defined by the Director, Environment, DMP in agreement with the Executive Director, Department of Environment and Conservation (DEC), the Conservation Commission of WA (CCWA) and the Environmental Protection Authority), the licensee preparing a detailed program for each phase of proposed exploration for approval of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC and the CCWA. This process may result in additional conditions being imposed together with a requirement to lodge an Unconditional Performance Bond if required. This program to describe the environmental impacts and programs for their management and is to include the following :- maps and/or aerial photographs showing the proposed locations of all ground activities and disturbances;
- the purpose, specifications and extent of each activity and disturbance;
- descriptions of all vegetation types (in general terms), land forms, and unusual features likely to be disturbed by such proposed disturbances. The Regional/District Manager, DEC, specifying the level of vegetation description;
- details on proposals that may disturb sensitive terrestrial habitats including any declared rare flora and fauna if applicable;
- techniques, prescriptions, and timetable for rehabilitation of all proposed disturbances;
- undertaking for corrective measures for failed rehabilitation;
- details of water requirements from within the reserve;
- details of refuse disposal; and
- proposals for instruction and supervision of personnel and contractors in respect to environmental conditions.
| 15-Apr-2009 | |
31 | 1 | All rehabilitation being to the satisfaction of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC. | 15-Apr-2009 | |
32 | 1 | At agreed intervals, not greater than 12 monthly, the licensee reporting to the Director, Environment, DMP and the Regional/District Manager, DEC, on the progress of the operation and the rehabilitation program. | 15-Apr-2009 | |
33 | 1 | Prior to the cessation of the exploration/prospecting activity in the reserve, the licensee notifying the Environmental Officer, DMP and the Regional/ District Manager, DEC, and arranging an inspection as required. | 15-Apr-2009 | |
34 | 1 | The licensee making provision to prevent spillage of fuel and discharge of pollutants generally and for all exploration sites being kept free from any rubbish and being left in a clean and tidy state. | 15-Apr-2009 | |
35 | 1 | The licensee not establishing any camp, base works or area, fuelling depot or similar establishment on the licence area unless the site and access has received prior approval of the Director, Environment, DMP in agreement with the Regional/District Manager, DEC. | 15-Apr-2009 | |
36 | 1 | Domestic animals, traps, or firearms not being taken onto the reserve. | 15-Apr-2009 | |
Type | Number | Details |
Extension of Time | 262393 | Lodged on 21 Feb 2007 to serve Pastoralist and Chief Executive.Approved by the Warden on 16 Mar 2007 |
Extension of Time | 273994 | Lodged 10:20 AM on 03 Aug 2007 to lodge late service on grazing lease holder.Approved by the Warden on 04 Sep 2007 |
Transfer | 285529 | Transfer 285529 was registered on 07 Mar 2008 against E 15/320. Pursuant to Section 120AA the applicant details have been amended. |
Application to Amend | 434630 | Lodged:13:42:31 06 November 2013Amending:AddressFrom:BHP BILLITON NICKEL WEST PTY LTD, C/- LAND SERVICES, PO BOX 8301, PERTH BUSINESS CENTRE, WA, 6849To:BHP BILLITON NICKEL WEST PTY LTD, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872RECORDED:13:42:31 06 November 2013 |
Extension / Renewal of Term | 443568 | Lodged:08:30 04 April 2014Applied For Period:5 YearsRECORDED:08:30 04 April 2014GRANTED:16 June 2014Granted Period:5 YearsTerm Extended To:14/04/2019 |
Partial Surrender - Compulsory | 465580 | Lodged:14:21:51 13 April 2015Section:Section 65 (3)Surrendered Blocks:KALGOORLIE 2611 y, z
KALGOORLIE 2683 d, e
KALGOORLIE 2684 aSurrendered Total:5 BL.REGISTERED:Midnight 14 April 2015Surrendered area to be released 08:30:00 15/05/2015 under Section 65 (3)Surrendered area released 08:30:00 15/05/2015 under Section 65 (3) |
Amalgamation | 469687 | Lodged:10:25 19 June 2015Amalgamating:Portion of P 15/4969Situated within:External boundaries of E 15/983Granted 01/12/2015 in respect to P 15/4969 |
Application to Amend | 493044 | Lodged:09:42:29 30 August 2016Amending:Address (Including DTC Details)From:ST IVES GOLD MINING COMPANY PTY LIMITED, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872To:ST IVES GOLD MINING COMPANY PTY LIMITED, GEMMA GLASS / RACHAEL CHALMERS, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872, xxxxxxxxxxxxxx@goldfields.com, xxxxx204RECORDED:09:42:29 30 August 2016 |
Amalgamation | 519933 | Lodged:09:10 12 December 2017Amalgamating:Whole of former P 15/5980Situated within:External boundaries of E 15/983Withdrawn 12/12/2017 in respect to P 15/5980 |
Extension / Renewal of Term | 551466 | Lodged:16:06:29 11 April 2019Applied For Period:2 YearsRECORDED:16:06:29 11 April 2019GRANTED:05 November 2019Granted Period:2 YearsTerm Extended To:14/04/2021 |
Application to Amend | 616447 | Lodged:14:27:01 23 February 2021Amending:Address (Including DTC Details)From:ST IVES GOLD MINING COMPANY PTY LIMITED, GEMMA GLASS / RACHAEL CHALMERS, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872, xxxxxxxxxxxxxx@goldfields.com, xxxxx204To:ST IVES GOLD MINING COMPANY PTY LIMITED, GEMMA GLASS / RACHAEL CHALMERS, C/- TENEMENTS, GPO BOX 2731, CLOISTERS SQUARE PO, WA, 6850, xxxxxxxxxxxxxx@goldfields.com, xxxxx204RECORDED:14:27:01 23 February 2021 |
Expiry - Full | 620988 | EFFECTIVE:Midnight 14 April 2021 |