Extracted from MTO on 26-Jun-2025 00:26,
last changed 14-Aug-2023.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 05-Aug-2019 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 05-Aug-2019 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 05-Aug-2019 | |
4 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on CR 41924. | 05-Aug-2019 | |
5 | 1 | No interference with Geodetic Survey Station SSM-Kalgoorlie 136 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 05-Aug-2019 | |
6 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 16 as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 05-Aug-2019 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 05-Aug-2019 | |
8 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 6 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 05-Aug-2019 | |
9 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operator of the railway on corridor land. | 05-Aug-2019 | |
10 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 05-Aug-2019 | |
11 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 05-Aug-2019 | |
12 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 05-Aug-2019 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 05-Aug-2019 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 05-Aug-2019 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 05-Aug-2019 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 05-Aug-2019 | |
4 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on CR 41924. | 05-Aug-2019 | |
5 | 1 | No interference with Geodetic Survey Station SSM-Kalgoorlie 136 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 05-Aug-2019 | |
6 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 16 as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 05-Aug-2019 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 05-Aug-2019 | |
8 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 6 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 05-Aug-2019 | |
9 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operator of the railway on corridor land. | 05-Aug-2019 | |
10 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 05-Aug-2019 | |
11 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 05-Aug-2019 | |
12 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 05-Aug-2019 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 05-Aug-2019 | |
Type | Number | Details |
Surrender - Outright | 560313 | Lodged:09:59:22 12 August 2019REGISTERED:09:59:22 12 August 2019 |