Extracted from MTO on 18-Mar-2026 01:20,
last changed 13-Mar-2026.
| # | Ver | Text | Start | End |
| 1 | 2 | Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Petroleum and Exploration. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Mines, Petroleum and Exploration. | 11-Mar-2026 | |
| 1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 04-Apr-2019 | 10-Mar-2026 |
| 2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Apr-2019 | |
| 3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Apr-2019 | |
| 4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Apr-2019 | |
| 5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Apr-2019 | |
| 6 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Petroleum and Exploration. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Mines, Petroleum and Exploration. | 11-Mar-2026 | |
| 7 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department of Mines, Petroleum and Exploration upon request. | 11-Mar-2026 | |
| 8 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 11-Mar-2026 | |
| Cond # | Ver | Text | Start | End |
| 1 | 2 | Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Petroleum and Exploration. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Mines, Petroleum and Exploration. | 11-Mar-2026 | |
| 1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 04-Apr-2019 | 10-Mar-2026 |
| 2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Apr-2019 | |
| 3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Apr-2019 | |
| 4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Apr-2019 | |
| 5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Apr-2019 | |
| 6 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Petroleum and Exploration. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Mines, Petroleum and Exploration. | 11-Mar-2026 | |
| 7 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department of Mines, Petroleum and Exploration upon request. | 11-Mar-2026 | |
| 8 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 11-Mar-2026 | |
| Type | Number | Details |
| Application to Amend | 682240 | Lodged:10:00 27 July 2023Amending:Address (Including DTC Details)From:Principal Place of Business : RAND MINING LIMITED, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2, 326 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxx@landadmin.com.au, xxxxxx777 and DTC :RAND MINING LIMITED, TENEMENT MANAGER, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2, 326 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxx@landadmin.com.au, xxxxxx777To:Principal Place of Business : RAND MINING LIMITED, C/- AUSTRALIAN MINING AND EXPLORATION TITLE SERVICES PTY LTD, PO BOX 40, DUNCRAIG, WA, 6023, xx@amets.com.au, xxxxxxxxx853 and DTC :RAND MINING LIMITED, AUSTRALIAN MINING AND EXPLORATION TITLE SERVICES PTY LTD, C/- AUSTRALIAN MINING AND EXPLORATION TITLE SERVICES PTY LTD, PO BOX 40, DUNCRAIG, WA, 6023, xx@amets.com.au, xxxxxxxxx853RECORDED:10:00 27 July 2023 |
| Extension / Renewal of Term | 700124 | Lodged:11:06:07 02 April 2024Applied For Period:5 YearsRECORDED:11:06:07 02 April 2024GRANTED:04 June 2024Granted Period:5 YearsTerm Extended To:03/04/2029 |
| Application to Amend | 713323 | Lodged:13:52:44 27 August 2024Amending:Address (Including DTC Details)From:Principal Place of Business : TRIBUNE RESOURCES LIMITED, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2, 326 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxx@landadmin.com.au, xxxxxx777 and DTC :TRIBUNE RESOURCES LIMITED, TENEMENT MANAGER, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2, 326 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxx@landadmin.com.au, xxxxxx777To:Principal Place of Business : TRIBUNE RESOURCES LIMITED, PO BOX 40, DUNCRAIG, WA, 6023, xx@amets.com.au, xxxxxxxxx739 and DTC :TRIBUNE RESOURCES LIMITED, C/- AUSTRALIAN MINING & EXPLORATION TITLE SERVICES PTY LTD, PO BOX 40, DUNCRAIG, WA, 6023, xx@amets.com.au, xxxxxxxxx739RECORDED:13:52:44 27 August 2024 |