1 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 07-May-2024 | |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 11-Mar-2020 | 06-May-2024 |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 11-Mar-2020 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 11-Mar-2020 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 11-Mar-2020 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 11-Mar-2020 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/88, 15/90, 15/96, 15/111, 15/119, 15/126, 15/127, 15/130, 15/200, 15/211 and 15/224 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 11-Mar-2020 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Crown Reserve 17462 - Government Requirements and Unnumbered Land Act Reserve 11. | 11-Mar-2020 | |
8 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 0000015 as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 11-Mar-2020 | |
9 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 8 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 11-Mar-2020 | |
10 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 8 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 11-Mar-2020 | |
11 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 8 hereof without the prior approval of the operator of the railway on corridor land. | 11-Mar-2020 | |
12 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 8 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 11-Mar-2020 | |
13 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 11-Mar-2020 | |
14 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 11-Mar-2020 | |
15 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 11-Mar-2020 | |
16 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 07-May-2024 | |
17 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 07-May-2024 | |
18 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 07-May-2024 | |
Cond # | Ver | Text | Start | End |
1 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 07-May-2024 | |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 11-Mar-2020 | 06-May-2024 |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 11-Mar-2020 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 11-Mar-2020 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 11-Mar-2020 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 11-Mar-2020 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/88, 15/90, 15/96, 15/111, 15/119, 15/126, 15/127, 15/130, 15/200, 15/211 and 15/224 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 11-Mar-2020 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Crown Reserve 17462 - Government Requirements and Unnumbered Land Act Reserve 11. | 11-Mar-2020 | |
8 | 1 | No mining within 30 metres of either side and to a depth of 15 metres of the Rail Corridor Land 0000015 as shown in TENGRAPH without the prior written approval of the Minister responsible for the Mining Act 1978. | 11-Mar-2020 | |
9 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 8 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 11-Mar-2020 | |
10 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 8 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 11-Mar-2020 | |
11 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 8 hereof without the prior approval of the operator of the railway on corridor land. | 11-Mar-2020 | |
12 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 8 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 11-Mar-2020 | |
13 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 11-Mar-2020 | |
14 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 11-Mar-2020 | |
15 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 11-Mar-2020 | |
16 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 07-May-2024 | |
17 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 07-May-2024 | |
18 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 07-May-2024 | |
Type | Number | Details |
Objection | 520616 | Lodged:11:17:53 20 December 2017Objectors:MLG OZ PTY LTDObjection Type:Tenement ApplicationRECORDED:11:17:53 20 December 2017FINALISED:09:15:48 01 August 2019Wardens Decision Made on:16:00 25 July 2019Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent. |
Objection | 521152 | Lodged:08:30 05 January 2018Objectors:FOCUS MINERALS LTD, FOCUS OPERATIONS PTY LTDObjection Type:Tenement ApplicationRECORDED:08:30 05 January 2018WITHDRAWN:00:00 30 May 2018Wardens Decision Made on:00:00 30 May 2018Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn by consent. |
Objection | 521370 | Lodged:08:30 10 January 2018Objectors:SIBERIA MINING CORPORATION PTY LTDObjection Type:Tenement ApplicationRECORDED:08:30 10 January 2018WITHDRAWN:00:00 02 May 2018Wardens Decision Made on:00:00 02 May 2018Wardens Decision Status:LapsedWardens Decision Text:Objection withdrawn by consent. |
Extension of Time | 539761 | Lodged:10:30 28 September 2018Type:Service on PastoralistRECORDED:10:30 28 September 2018EOT incorrectly lodged on this tenement.REFUSED:11:32:12 08 October 2018 |
Application to Amend | 564675 | Lodged:08:43:21 15 October 2019Amending:Address (Including DTC Details)From:Principal Place of Business : OUTBACK MINERALS PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931 and DTC :OUTBACK MINERALS PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931To:Principal Place of Business : OUTBACK MINERALS PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997 and DTC :OUTBACK MINERALS PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxx997RECORDED:08:43:21 15 October 2019 |
Application to Amend | 675443 | Lodged:14:41:35 09 May 2023Amending:Address (Including DTC Details)From:OUTBACK MINERALS PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 6301, EAST PERTH, WA, 6892, xxxx@mmts.net.au, xxxxxxx997To:OUTBACK MINERALS PTY LTD, C/- FRS, PO BOX 1112, KALAMUNDA, WA, 6926, xxxxxxx@datumpeg.com.au, xxxxxxx769RECORDED:14:41:35 09 May 2023 |
Extension / Renewal of Term | 727796 | Lodged:08:30 10 March 2025Applied For Period:5 YearsRECORDED:08:30 10 March 2025GRANTED:21 May 2025Granted Period:5 YearsTerm Extended To:10/03/2030 |
Application to Amend | 733753 | Lodged:15:25:43 19 May 2025Amending:Address (Including DTC Details)From:OUTBACK MINERALS PTY LTD, C/- FRS, PO BOX 1112, KALAMUNDA, WA, 6926, xxxxxxx@datumpeg.com.au, xxxxxxx769To:OUTBACK MINERALS PTY LTD, TENEMENT HOLDER, C/- FRS, PO BOX 1112, KALAMUNDA, WA, 6926, xxxxxxx@datumpeg.com.au, xxxxxxx769RECORDED:15:25:43 19 May 2025 |