1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 15-May-2023 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-May-2023 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-May-2023 | |
4 | 1 | The Licensee making verbal or written contact with the holder of any underlying pastoral or grazing lease within a reasonable time prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-May-2023 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-May-2023 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/233 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 15-May-2023 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 15-May-2023 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-May-2023 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-May-2023 | |
4 | 1 | The Licensee making verbal or written contact with the holder of any underlying pastoral or grazing lease within a reasonable time prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-May-2023 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-May-2023 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/233 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 15-May-2023 | |
Type | Number | Details |
Objection | 518158 | Lodged:11:58:38 10 November 2017Objectors:HBJ MINERALS PTY LTDObjection Type:Tenement ApplicationRECORDED:11:58:38 10 November 2017Objector - Avoca Mining Pty LtdWITHDRAWN:16:00 26 April 2023 |
Application to Amend | 688082 | Lodged:15:59:18 18 October 2023Amending:Address (Including DTC Details)From:Principal Place of Business : DYNAMIC METALS LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT, PO BOX 1434, WANGARA, WA, 6947 and DTC :DYNAMIC METALS LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT, PO BOX 1434, WANGARA, WA, 6947To:Principal Place of Business : DYNAMIC METALS LIMITED, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxx400 and DTC :DYNAMIC METALS LIMITED, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxx400RECORDED:15:59:18 18 October 2023 |
Caveat | 709423 | Lodged:12:35:22 15 July 2024Caveat Type:Consent CaveatCaveator:A.C.N. 654 242 690 PTY LTDShares Caveated:100/100 shares DYNAMIC METALS LIMITEDRECORDED:12:35:22 15 July 2024 |