1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 22-Jan-2014 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 27-Mar-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 22-Jan-2014 | 26-Mar-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 22-Jan-2014 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 22-Jan-2014 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 22-Jan-2014 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 22-Jan-2014 | |
7 | 1 | No excavation, excepting shafts, approaching closer to the Coolgardie - Esperance Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Coolgardie - Esperance Highway or Highway verge being confined to below a depth of 30 metres from the natural surface. | 22-Jan-2014 | |
8 | 1 | No interference with Geodetic Survey Stations SSM-BBN 105 and SSM-BBN 106 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 22-Jan-2014 | |
9 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 22-Jan-2014 | |
10 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 27-Mar-2024 | |
11 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 27-Mar-2024 | |
12 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 27-Mar-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 22-Jan-2014 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 27-Mar-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 22-Jan-2014 | 26-Mar-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 22-Jan-2014 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 22-Jan-2014 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 22-Jan-2014 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 22-Jan-2014 | |
7 | 1 | No excavation, excepting shafts, approaching closer to the Coolgardie - Esperance Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Coolgardie - Esperance Highway or Highway verge being confined to below a depth of 30 metres from the natural surface. | 22-Jan-2014 | |
8 | 1 | No interference with Geodetic Survey Stations SSM-BBN 105 and SSM-BBN 106 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 22-Jan-2014 | |
9 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 22-Jan-2014 | |
10 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 27-Mar-2024 | |
11 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 27-Mar-2024 | |
12 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 27-Mar-2024 | |
Type | Number | Details |
Application to Amend | 430150 | Lodged:08:30 29 August 2013Amending:AddressFrom:ST. IVES GOLD MINING COMPANY PTY LTD, C/- GOLD FIELDS AUSTRALASIA (EXPLORATION), PO BOX 996, WEST PERTH, WA, 6872To:ST. IVES GOLD MINING COMPANY PTY LTD, C/- TENEMENTS, PO BOX 996, WEST PERTH, WA, 6872RECORDED:08:30 29 August 2013 |
Application to Amend | 451610 | Lodged:12:57:15 28 July 2014Amending:AddressFrom:ST IVES GOLD MINING COMPANY PTY LIMITED, C/- TENEMENTS, PO BOX 996, WEST PERTH, WA, 6872To:ST IVES GOLD MINING COMPANY PTY LIMITED, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872RECORDED:12:57:15 28 July 2014 |
Application to Amend | 493044 | Lodged:09:42:29 30 August 2016Amending:Address (Including DTC Details)From:Principal Place of Business : ST IVES GOLD MINING COMPANY PTY LIMITED, C/- GOLD FIELDS EXPLORATION, LEVEL 1, 62 COLIN STREET, WEST PERTH, WA, 6005 and DTC :ST IVES GOLD MINING COMPANY PTY LIMITED, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872To:Principal Place of Business : ST IVES GOLD MINING COMPANY PTY LIMITED, ADDRESS NOT PROVIDED and DTC :ST IVES GOLD MINING COMPANY PTY LIMITED, GEMMA GLASS / RACHAEL CHALMERS, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872, xxxxxxxxxxxxxx@goldfields.com, xxxxx204RECORDED:09:42:29 30 August 2016 |
Extension / Renewal of Term | 546242 | Lodged:10:07:13 18 January 2019Applied For Period:5 YearsRECORDED:10:07:13 18 January 2019GRANTED:11 April 2019Granted Period:5 YearsTerm Extended To:21/01/2024 |
Application to Amend | 616447 | Lodged:14:27:01 23 February 2021Amending:Address (Including DTC Details)From:ST IVES GOLD MINING COMPANY PTY LIMITED, GEMMA GLASS / RACHAEL CHALMERS, C/- TENEMENTS, PO BOX 628, WEST PERTH, WA, 6872, xxxxxxxxxxxxxx@goldfields.com, xxxxx204To:ST IVES GOLD MINING COMPANY PTY LIMITED, GEMMA GLASS / RACHAEL CHALMERS, C/- TENEMENTS, GPO BOX 2731, CLOISTERS SQUARE PO, WA, 6850, xxxxxxxxxxxxxx@goldfields.com, xxxxx204RECORDED:14:27:01 23 February 2021 |
Extension / Renewal of Term | 694481 | Lodged:13:24:05 19 January 2024Applied For Period:2 YearsRECORDED:13:24:05 19 January 2024GRANTED:20 March 2024Granted Period:2 YearsTerm Extended To:21/01/2026 |