Extracted from MTO on 12-Jul-2025 00:44,
last changed 04-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 18-Jul-2011 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 18-Jul-2011 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Jul-2011 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Jul-2011 | |
5 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/245 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 18-Jul-2011 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 18-Jul-2011 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 18-Jul-2011 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Jul-2011 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Jul-2011 | |
5 | 1 | The rights of ingress to and egress from Miscellaneous Licence 15/245 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 18-Jul-2011 | |
Type | Number | Details |
Extension of Time | 348806 | Lodged:09:20 10 June 2010Type:SecurityRECORDED:09:20 10 June 2010APPROVED:10:40 11 June 2010 |
Amalgamation | 382760 | Lodged:12:36 06 October 2011Amalgamating:Whole of former P 15/5237Situated within:External boundaries of E 15/1213-IGranted 20/09/2013 in respect to P 15/5237 |
Partial Surrender - Voluntary | 401595 | Lodged:15:30 17 July 2012Surrendered Blocks:KALGOORLIE 2753 v
KALGOORLIE 2825 a, b, f, g, l, m, q, r, v, w
KALGOORLIE 2897 b, g, h, m, n
KALGOORLIE 2969 d, e, j, k, o, p, t, u, y, z
KALGOORLIE 2970 q, vSurrendered Total:28 BL.REGISTERED:15:30 17 July 2012 |
Forfeiture | 454578 | Initiated:17/09/2014 for non-compliance with rent requirementsRECORDED:08:23:21 12 September 2014Notice Issued:Regulation 50 Notice sent 17/09/2014 for non-compliance with rent requirements pursuant to Reg 109/Sec 63A- non payment of rent.Compliance Date:21/10/2014FINALISED:Order by Minister on 03 December 2014 that E 15/1213-I be Penalty Imposed |
Forfeiture | 456183 | Initiated:15/10/2014 for non-compliance with reporting requirements( Form 5 )RECORDED:15:26:54 14 October 2014Notice Issued:Regulation 50 Notice sent 15/10/2014 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- late lodgement of Form 5.Compliance Date:19/11/2014FINALISED:Order by Minister on 22 April 2015 that E 15/1213-I be Penalty Imposed |
Extension of Time | 456487 | Lodged:13:45 17 October 2014Type:RentRECORDED:13:45 17 October 2014REFUSED:12:00 03 December 2014 |
Extension of Time | 456488 | Lodged:13:45 17 October 2014Type:Form 5RECORDED:13:45 17 October 2014REFUSED:13:45:06 05 January 2015 |
Fine | 460010 | Fine in respect to:Forfeiture Process 454578Fine reason:Non-compliance with rent obligationsPenalty amount:$268.60Notification date:06/01/2015Due date:11/02/2015Pursuant to:Section 96A(5)RECORDED:06 January 2015PAYMENT RECEIVED:10 February 2015FINALISED:10 February 2015Receipt Number:06-142769Amount:$268.60Remaining balance:$0.00 |
Fine | 466383 | Fine in respect to:Forfeiture Process 456183Fine reason:Non-compliance with expenditure obligationsPenalty amount:$90.00Notification date:24/04/2015Due date:26/05/2015Pursuant to:Section 96A(5)RECORDED:24 April 2015PAYMENT RECEIVED:21 May 2015Receipt Number:06-145591Amount:$90.00Remaining balance:$0.00FINALISED:21 May 2015 |
Caveat | 486506 | Lodged:09:48:47 11 May 2016Caveat Type:Absolute CaveatCaveator:SHIRE OF COOLGARDIEShares Caveated:100/100 shares ABEH PTY LTDRECORDED:09:48:47 11 May 2016WITHDRAWN:15:55:53 10 April 2017 |
Amalgamation | 486580 | Lodged:16:15 11 May 2016Amalgamating whole of former P 15/4806 and P 15/4807 situated within the external boundaries of E 15/1213.
REFUSED 27 January 2017 |
Extension / Renewal of Term | 490731 | Lodged:14:50 15 July 2016Applied For Period:5 YearsRECORDED:14:50 15 July 2016GRANTED:28 October 2016Granted Period:5 YearsTerm Extended To:17/07/2021 |
Forfeiture | 495269 | Compliance Date:22/11/2016Initiated:17/10/2016 for non-compliance with reporting requirements( Form 5 )Notice Issued:Regulation 50 Notice sent 17/10/2016 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- non lodgement of Form 5.FINALISED:Order by Minister on 29 November 2016 that E 15/1213-I be Penalty Imposed |
Fine | 497844 | Fine in respect to:Forfeiture Process 495269Fine reason:Non-compliance with expenditure obligationsPenalty amount:$900.00Notification date:11/01/2017Due date:15/02/2017Pursuant to:Section 96A(5)RECORDED:30 November 2016PAYMENT RECEIVED:14 February 2017FINALISED:14 February 2017Receipt Number:06-158708Amount:$900.00Remaining balance:$0.00 |
Withdrawal of Dealing | 504275 | Lodged:15:55:53 10 April 2017In respect to:Caveat 486506RECORDED:15:55:53 10 April 2017 |
Forfeiture | 518132 | Initiated:13/11/2017 for non-compliance with reporting requirementsRECORDED:11:40 13 November 2017Notice Issued:Regulation 50 Notice sent 13/11/2017 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:18/12/2017FINALISED:Order by Minister on 23 March 2018 that E 15/1213-I be Penalty Imposed |
Amalgamation | 520941 | Lodged:16:25 27 December 2017Amalgamating:Portion of former P 15/5236Situated within:External boundaries of E 15/1213-IWithdrawn 15/05/2020 in respect to P 15/5236 |
Fine | 526340 | Fine in respect to:Forfeiture Process 518132Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$450.00Notification date:04/04/2018Due date:09/05/2018Pursuant to:Section 96A(5)RECORDED:23 March 2018PAYMENT RECEIVED:23 April 2018FINALISED:23 April 2018Receipt Number:06-165355Amount:$450.00Remaining balance:$0.00 |
Forfeiture | 564797 | Initiated:18/10/2019 for non-compliance with reporting requirements( Form 5 )RECORDED:11:21 18 October 2019Notice Issued:Regulation 50 Notice sent 18/10/2019 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- late lodgement of Form 5.Compliance Date:22/11/2019FINALISED:Order by Minister on 11 December 2019 that E 15/1213-I be Penalty Imposed |
Extension of Time | 566632 | Lodged:16:00 14 November 2019Type:Form 5RECORDED:16:00 14 November 2019REFUSED:12:40:09 18 November 2019 |
Extension of Time | 566640 | Lodged:16:00 14 November 2019Type:Form 5RECORDED:16:00 14 November 2019LAPSED:17:04:49 14 November 2019DUPLICATED. EOT FOR FORM 5 SCANNED WITH ANOTHER DOCUMENT SUBMITTED BY MR STRINGBERG FOR A PENDING APPLICATION. |
Fine | 568584 | Fine in respect to:Forfeiture Process 564797Fine reason:Non-compliance with expenditure obligationsPenalty amount:$90.00Notification date:16/12/2019Due date:20/01/2020Pursuant to:Section 96A(5)RECORDED:16 December 2019PAYMENT RECEIVED:06 January 2020FINALISED:06 January 2020Receipt Number:10128310Amount:$90.00Remaining balance:$0.00 |
Conversion | 628260 | New Tenement:M 15/1891Application Date:16:15 15 Jul 2021Section:S67 |
Surrender - Outright | 628323 | Lodged:15:50:22 16 July 2021REGISTERED:15:50:22 16 July 2021 |