Extracted from MTO on 07-Mar-2021 03:38,
last changed 16-Mar-2020.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 12-Mar-2009 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 12-Mar-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 12-Mar-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 12-Mar-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 12-Mar-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 12-Mar-2009 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Water Reserve 18234. | 12-Mar-2009 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 12-Mar-2009 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 12-Mar-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 12-Mar-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 12-Mar-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 12-Mar-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 12-Mar-2009 | |
7 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Water Reserve 18234. | 12-Mar-2009 | |
Type | Number | Details |
Extension of Time | 289560 | Lodged 9:30 AM on 30 Apr 2008 late lodgement of advertising.Approved by the Warden on 19 Mar 2008 |
Extension of Time | 289561 | Lodged 9:30 AM on 30 Apr 2008 late lodgement of services on pastoralistApproved by the Warden on 12 Mar 2008 |
Extension of Time | 289562 | Lodged 9:30 AM on 30 Apr 2008 lodgement of late securities.Approved by the Warden on 28 Mar 2008 |
Extension / Renewal of Term | 441837 | Lodged:14:05 11 March 2014Applied For Period:5 YearsRECORDED:14:05 11 March 2014GRANTED:18 June 2014Granted Period:5 YearsTerm Extended To:11/03/2019 |
Caveat | 486517 | Lodged:09:48:47 11 May 2016Caveat Type:Absolute CaveatCaveator:SHIRE OF COOLGARDIEShares Caveated:100/100 shares ABEH PTY LTDRECORDED:09:48:47 11 May 2016WITHDRAWN:15:55:53 10 April 2017 |
Withdrawal of Dealing | 504274 | Lodged:15:55:53 10 April 2017In respect to:Caveat 486517RECORDED:15:55:53 10 April 2017 |
Expiry - Full | 549830 | EFFECTIVE:Midnight 11 March 2019 |