Extracted from MTO on 29-Jun-2025 00:54,
last changed 29-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 02-Nov-2017 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 02-Nov-2017 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 02-Nov-2017 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 02-Nov-2017 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 02-Nov-2017 | |
6 | 1 | No interference with Geodetic Survey Station BYRO 1, BYRO 2 and NMF 609 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 02-Nov-2017 | |
| 1 | In respect to the area designated as CPL 5 in TENGRAPH the following conditions apply: | 02-Nov-2017 | |
7 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMP the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMP. The program to include:- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 02-Nov-2017 | |
8 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMP. Such rehabilitation as is appropriate and may include:- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 02-Nov-2017 | |
9 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 02-Nov-2017 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 02-Nov-2017 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 02-Nov-2017 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 02-Nov-2017 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 02-Nov-2017 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 02-Nov-2017 | |
6 | 1 | No interference with Geodetic Survey Station BYRO 1, BYRO 2 and NMF 609 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 02-Nov-2017 | |
| 1 | In respect to the area designated as CPL 5 in TENGRAPH the following conditions apply: | 02-Nov-2017 | |
7 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMP the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMP. The program to include:- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 02-Nov-2017 | |
8 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMP. Such rehabilitation as is appropriate and may include:- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 02-Nov-2017 | |
9 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 02-Nov-2017 | |
Type | Number | Details |
Surrender - Outright | 546016 | Lodged:12:10:02 15 January 2019REJECTED:12:10:02 15 January 2019 |
Forfeiture | 548182 | Initiated:27/02/2019 for non-compliance with reporting requirements( Form 5 )RECORDED:08:42 27 February 2019Notice Issued:Regulation 50 Notice sent 27/02/2019 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- non lodgement of Form 5.Compliance Date:03/04/2019FINALISED:Order by Minister on 05 July 2019 that E 09/2220 be Forfeited |