Extracted from MTO on 06-Jul-2025 00:20,
last changed 27-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-Dec-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-Dec-2016 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-Dec-2016 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-Dec-2016 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 15-Dec-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 15-Dec-2016 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 15-Dec-2016 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 15-Dec-2016 | |
Type | Number | Details |
Application to Amend | 503153 | Lodged:15:20 22 March 2017Amending:NameFrom:A.C.N. 611 488 932 PTY LTDTo:WODGINA LITHIUM PTY LTDRECORDED:15:20 22 March 2017 |
Extension of Time | 525217 | Lodged:15:20:56 09 March 2018Type:Stat DecRECORDED:15:20:56 09 March 2018APPROVED:08:27:56 12 March 2018Time extended to 2 April 2018 |
Forfeiture | 529630 | Initiated:03/05/2018 for non-compliance with expenditure conditionsRECORDED:14:30 08 May 2018Notice Issued:Regulation 50 Notice sent 03/05/2018 for non-compliance with expenditure conditions pursuant to Reg 15.Compliance Date:02/06/2018FINALISED:Order by Minister on 15 June 2018 that E 09/2187 be Penalty Imposed |
Fine | 533787 | Fine in respect to:Forfeiture Process 529630Fine reason:Non-compliance with expenditure obligationsPenalty amount:$650.00Notification date:28/06/2018Due date:02/08/2018Pursuant to:Section 96A(5)RECORDED:27 June 2018PAYMENT RECEIVED:04 July 2018FINALISED:04 July 2018Receipt Number:84977747899Amount:$650.00Remaining balance:$0.00 |
Surrender - Outright | 568363 | Lodged:08:30 10 December 2019REGISTERED:08:30 10 December 2019 |