Extracted from MTO on 12-Jul-2025 01:14,
last changed 08-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Jul-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Jul-2016 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Jul-2016 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Jul-2016 | |
5 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 17-Nov-2021 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Jul-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Jul-2016 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Jul-2016 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Jul-2016 | |
5 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 17-Nov-2021 | |
Type | Number | Details |
Forfeiture | 514882 | Initiated:21/09/2017 for non-compliance with rent requirementsRECORDED:10:02:22 20 September 2017Notice Issued:Regulation 50 Notice sent 21/09/2017 for non-compliance with rent requirements pursuant to Reg 109/Sec 63A- non payment of rent.Compliance Date:26/10/2017FINALISED:Order by Minister on 08 November 2017 that E 09/2161 be Penalty Imposed |
Forfeiture | 516534 | Initiated:20/10/2017 for non-compliance with reporting requirements( Form 5 )RECORDED:14:33 20 October 2017Notice Issued:Regulation 50 Notice sent 20/10/2017 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- non lodgement of Form 5.Compliance Date:23/11/2017WITHDRAWN:07 March 2018 (EOT approved) |
Extension of Time | 516953 | Lodged:12:56 24 October 2017Type:Form 5RECORDED:12:56 24 October 2017APPROVED:15:07:46 24 October 2017Time extended to 31 October 2017 |
Fine | 518108 | Fine in respect to:Forfeiture Process 514882Fine reason:Non-compliance with rent obligationsPenalty amount:$226.00Notification date:10/11/2017Due date:15/12/2017Pursuant to:Section 96A(5)RECORDED:10 November 2017PAYMENT RECEIVED:15 December 2017FINALISED:15 December 2017Receipt Number:EFTAmount:$226.00Remaining balance:$0.00 |
Application to Amend | 534349 | Lodged:10:16:01 05 July 2018Amending:Address (Including DTC Details)From:Principal Place of Business : HURRICANE PROSPECTING PTY LTD, SAME AS CORRESPONDENCE and DTC :HURRICANE PROSPECTING PTY LTD, 61 THE STRAND, BAYSWATER, WA, 6053To:Principal Place of Business : HURRICANE PROSPECTING PTY LTD, DEBLIN TENEMENT MANAGEMENT SERVICES, PO BOX 456, MOUNT HAWTHORN, WA, 6915, xxxx@deblin.com.au, xxxxxxx190 and DTC :HURRICANE PROSPECTING PTY LTD, THE TENEMENT MANAGER, DEBLIN TENEMENT MANAGEMENT SERVICES, PO BOX 456, MOUNT HAWTHORN, WA, 6915, xxxx@deblin.com.au, xxxxxxx190RECORDED:10:16:01 05 July 2018 |
Extension of Time | 538588 | Lodged:10:47:55 06 September 2018Type:Form 5RECORDED:10:47:55 06 September 2018APPROVED:11:42:01 06 September 2018Time extended until 24 September 2018 for YE 2018. |
Extension of Time | 563499 | Lodged:09:03:33 24 September 2019Type:Form 5RECORDED:09:03:33 24 September 2019APPROVED:11:42:51 24 September 2019Time to lodge extended to 15/10/2019 |
Forfeiture | 572742 | Initiated:24/02/2020 for non-compliance with reporting requirementsRECORDED:10:12:46 24 February 2020Notice Issued:Regulation 50 Notice sent 24/02/2020 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:30/03/2020FINALISED:Order by Minister on 03 June 2020 that E 09/2161 be Penalty Imposed |
Fine | 579231 | Fine in respect to:Forfeiture Process 572742Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$450.00Notification date:05/06/2020Due date:10/07/2020Pursuant to:Section 96A(5)RECORDED:03 June 2020PAYMENT RECEIVED:09 June 2020FINALISED:09 June 2020Receipt Number:54324002355Amount:$450.00Remaining balance:$0.00 |
Extension of Time | 586141 | Lodged:13:02:19 15 September 2020Type:Form 5RECORDED:13:02:19 15 September 2020APPROVED:15:28:40 15 September 2020Time to lodge extended to 15/10/2020 |
Forfeiture | 591195 | Initiated:25/11/2020 for non-compliance with reporting requirementsRECORDED:10:46:15 25 November 2020Notice Issued:Regulation 50 Notice sent 25/11/2020 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:04/01/2021FINALISED:Order by Minister on 12 February 2021 that E 09/2161 be Penalty Imposed |
Fine | 595723 | Fine in respect to:Forfeiture Process 591195Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$360.00Notification date:15/02/2021Due date:22/03/2021Pursuant to:Section 96A(5)RECORDED:12 February 2021PAYMENT RECEIVED:17 February 2021FINALISED:17 February 2021Receipt Number:11272845784Amount:$360.00Remaining balance:$0.00 |
Extension / Renewal of Term | 627425 | Lodged:15:20:59 02 July 2021Applied For Period:5 YearsRECORDED:15:20:59 02 July 2021GRANTED:20 October 2021Granted Period:5 YearsTerm Extended To:03/07/2026 |
Extension of Time | 628195 | Lodged:10:34:29 15 July 2021Type:OtherRECORDED:10:34:29 15 July 2021APPROVED:11:49:39 15 July 2021Time to lodge extended to 30 July 2021 |
Extension of Time | 629327 | Lodged:11:38:20 30 July 2021Type:OtherRECORDED:11:38:20 30 July 2021APPROVED:13:43:02 30 July 2021Time to lodge extended to 13 August 2021 |
Forfeiture | 634433 | Initiated:22/10/2021 for non-compliance with reporting requirementsRECORDED:10:21:35 20 October 2021Notice Issued:Regulation 50 Notice sent 22/10/2021 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:19/11/2021FINALISED:Order by Minister on 06 April 2022 that E 09/2161 be Penalty Imposed |
Fine | 646697 | Fine in respect to:Forfeiture Process 634433Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$180.00Notification date:06/04/2022Due date:12/05/2022Pursuant to:Section 96A(5)RECORDED:06 April 2022PAYMENT RECEIVED:13 April 2022FINALISED:13 April 2022Receipt Number:22762610325Amount:$180.00Remaining balance:$0.00 |
Extension of Time | 685247 | Lodged:14:27:14 04 September 2023Type:Form 5RECORDED:14:27:14 04 September 2023APPROVED:11:22:50 22 September 2023Time to lodge extended to 18 Sep 2023 |
Extension of Time | 714473 | Lodged:12:58:10 11 September 2024Type:Form 5RECORDED:12:58:10 11 September 2024APPROVED:15:33:18 16 September 2024Extension of Time to lodge Form 5 until 21 September 2024. |
Forfeiture | 719926 | Initiated:21/11/2024 for non-compliance with reporting requirementsRECORDED:10:51:48 21 November 2024Notice Issued:Regulation 50 Notice sent 21/11/2024 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:06/01/2025 |