Extracted from MTO on 28-Jun-2025 00:24,
last changed 28-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 08-May-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 08-May-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 08-May-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 08-May-2015 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 08-May-2015 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 08-May-2015 | |
7 | 1 | No interference with Geodetic Survey Station SSM-WOORAMEL 79 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 08-May-2015 | |
8 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No 40 as shown in TENGRAPH. | 08-May-2015 | |
9 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 8 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP | 08-May-2015 | |
10 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 8 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 08-May-2015 | |
11 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 8 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP | 08-May-2015 | |
12 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP. | 08-May-2015 | |
13 | 1 | Mining on the Safety Zone established in Condition 8 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP . | 08-May-2015 | |
14 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 8 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 08-May-2015 | |
15 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 08-May-2015 | |
16 | 1 | In respect of the area covered by the licence the licensee, if so requested in writing by the Gnulli, the applicant in the Federal Court application no. WAD 6161 of 1998 (WC1997/028), such request being sent by pre-paid post to reach the licensee's address, not more than ninety days after the grant of this licence, shall within thirty days of the request execute in favour of the Gnulli, the Regional Standard Heritage Agreement endorsed by peak industry groups and the Yamatji Marlpa Aboriginal Corporation. | 08-May-2015 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 08-May-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 08-May-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 08-May-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 08-May-2015 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 08-May-2015 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 08-May-2015 | |
7 | 1 | No interference with Geodetic Survey Station SSM-WOORAMEL 79 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 08-May-2015 | |
8 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No 40 as shown in TENGRAPH. | 08-May-2015 | |
9 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 8 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP | 08-May-2015 | |
10 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 8 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 08-May-2015 | |
11 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 8 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP | 08-May-2015 | |
12 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP. | 08-May-2015 | |
13 | 1 | Mining on the Safety Zone established in Condition 8 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP . | 08-May-2015 | |
14 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 8 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 08-May-2015 | |
15 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 08-May-2015 | |
16 | 1 | In respect of the area covered by the licence the licensee, if so requested in writing by the Gnulli, the applicant in the Federal Court application no. WAD 6161 of 1998 (WC1997/028), such request being sent by pre-paid post to reach the licensee's address, not more than ninety days after the grant of this licence, shall within thirty days of the request execute in favour of the Gnulli, the Regional Standard Heritage Agreement endorsed by peak industry groups and the Yamatji Marlpa Aboriginal Corporation. | 08-May-2015 | |
Type | Number | Details |
Forfeiture | 537292 | Initiated:20/08/2018 for non-compliance with reporting requirements( Form 5 )RECORDED:08:15:41 17 August 2018Notice Issued:Regulation 50 Notice sent 20/08/2018 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- non lodgement of Form 5.Compliance Date:25/09/2018FINALISED:Order by Minister on 05 October 2018 that E 09/2082 be Penalty Imposed |
Fine | 540212 | Fine in respect to:Forfeiture Process 537292Fine reason:Non-compliance with expenditure obligationsPenalty amount:$480.00Notification date:09/10/2018Due date:13/11/2018Pursuant to:Section 96A(5)RECORDED:08 October 2018PAYMENT RECEIVED:13 October 2018FINALISED:13 October 2018Receipt Number:87697093077Amount:$480.00Remaining balance:$0.00 |
Expiry - Full | 578259 | EFFECTIVE:Midnight 07 May 2020 |