1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 20-May-2011 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 22-Apr-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 20-May-2011 | 21-Apr-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 20-May-2011 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 20-May-2011 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 20-May-2011 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 20-May-2011 | |
7 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 22-Apr-2024 | |
8 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 22-Apr-2024 | |
9 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 22-Apr-2024 | |
10 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 22-Apr-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 20-May-2011 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 22-Apr-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 20-May-2011 | 21-Apr-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 20-May-2011 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 20-May-2011 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 20-May-2011 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 20-May-2011 | |
7 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 22-Apr-2024 | |
8 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 22-Apr-2024 | |
9 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 22-Apr-2024 | |
10 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 22-Apr-2024 | |
Type | Number | Details |
Application to Amend | 415204 | Lodged:15:55 17 January 2013Amending:AddressFrom:Residential : KARRAMINDIE RESOURCES PTY LTD, SAME AS CORRESPONDENCE and Correspondence :KARRAMINDIE RESOURCES PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:Residential : KARRAMINDIE RESOURCES PTY LTD, ADDRESS NOT PROVIDED and Correspondence :KARRAMINDIE RESOURCES PTY LTD, C/- ANDERSON'S TENEMENT MANAGEMENT, PO BOX 2162, WARWICK, WA, 6024RECORDED:15:55 17 January 2013 |
Forfeiture | 431592 | Initiated:20/09/2013 for non-compliance with expenditure conditionsRECORDED:10:00 20 September 2013Notice Issued:Regulation 50 Notice sent 20/09/2013 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:21/10/2013FINALISED:Order by Minister on 08 January 2014 that E 09/1700 be Penalty Imposed |
Fine | 438281 | Fine in respect to:Forfeiture Process 431592Fine reason:Non-compliance with expenditure obligationsPenalty amount:$933.00Notification date:09/01/2014Due date:10/02/2014Pursuant to:Section 96A(5)RECORDED:09 January 2014PAYMENT RECEIVED:05 February 2014Receipt Number:06-132668Amount:$933.00Remaining balance:$0.00FINALISED:05 February 2014 |
Application to Amend | 446917 | Lodged:11:06:30 22 May 2014Amending:AddressFrom:KARRAMINDIE RESOURCES PTY LTD, C/- ANDERSON'S TENEMENT MANAGEMENT, PO BOX 2162, WARWICK, WA, 6024To:KARRAMINDIE RESOURCES PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947RECORDED:11:06:30 22 May 2014 |
Forfeiture | 454885 | Initiated:02/09/2014 for non-compliance with expenditure conditionsRECORDED:15:10 16 July 2014Notice Issued:Regulation 50 Notice sent 02/09/2014 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:02/10/2014FINALISED:Order by Minister on 05 March 2015 that E 09/1700 be Penalty Imposed |
Fine | 463363 | Fine in respect to:Forfeiture Process 454885Fine reason:Non-compliance with expenditure obligationsPenalty amount:$1,250.00Notification date:05/03/2015Due date:08/04/2015Pursuant to:Section 96A(5)RECORDED:05 March 2015PAYMENT RECEIVED:26 March 2015FINALISED:26 March 2015Receipt Number:06-143951Amount:$1,250.00Remaining balance:$0.00 |
Application to Amend | 478371 | Lodged:10:36:33 04 December 2015Amending:NameFrom:KARRAMINDIE RESOURCES PTY LTDTo:YANGIBANA PTY LTDRECORDED:10:36:33 04 December 2015 |
Extension / Renewal of Term | 486562 | Lodged:14:35 11 May 2016Applied For Period:5 YearsRECORDED:14:35 11 May 2016GRANTED:09 August 2016Granted Period:5 YearsTerm Extended To:19/05/2021 |
Conversion | 491771 | Section:S67Application Date:15:23:47 02 Aug 2016New Tenement:G 09/15Discontinued due to G 09/15 Withdrawn 11:46:56 10 March 2017 |
Partial Surrender - Voluntary | 506663 | Lodged:13:39:33 19 May 2017Surrendered Blocks:HAMERSLEY RANGE 3410 j, k
HAMERSLEY RANGE 3411 d, f, g, h, jSurrendered Total:7 BL.REGISTERED:13:39:33 19 May 2017 |
Application to Amend | 526848 | Lodged:15:26:04 29 March 2018Amending:Address (Including DTC Details)From:Principal Place of Business : YANGIBANA PTY LTD, ADDRESS NOT PROVIDED and DTC :YANGIBANA PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:Principal Place of Business : YANGIBANA PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemning.com.au, xxxxxxxxx400 and DTC :YANGIBANA PTY LTD, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxx400RECORDED:15:26:04 29 March 2018 |
Extension of Time | 535335 | Lodged:15:51:17 18 July 2018Type:Form 5RECORDED:15:51:17 18 July 2018APPROVED:10:44:01 23 July 2018Time to lodge extended to 25/07/2018 |
Extension of Time | 584185 | Lodged:11:42:45 14 August 2020Type:Stat DecRECORDED:11:42:45 14 August 2020APPROVED:15:03:22 17 August 2020Time to lodged extended to 11/09/2020 |
Excess Tonnage | 588526 | Lodged:08:57:14 20 October 2020RECORDED:08:57:14 20 October 2020GRANTED:22:14 20 October 2020Additional 1,728 tonnes |
Conversion | 591641 | Section:S67Application Date:13:50:03 30 Nov 2020New Tenement:M 09/178Converted 00:00 11 July 2022 being commencement of term of M 09/178 |
Extension / Renewal of Term | 622840 | Lodged:12:31:55 19 May 2021Applied For Period:2 YearsRECORDED:12:31:55 19 May 2021GRANTED:22 July 2021Granted Period:2 YearsTerm Extended To:19/05/2023 |
Excess Tonnage | 625444 | Lodged:13:19:20 08 June 2021RECORDED:13:19:20 08 June 2021GRANTED:10:42 25 June 2021Additional 675 tonnes |
Extension / Renewal of Term | 672629 | Lodged:13:28:08 05 April 2023Applied For Period:2 YearsRECORDED:13:28:08 05 April 2023GRANTED:20 July 2023Granted Period:2 YearsTerm Extended To:19/05/2025 |
Extension / Renewal of Term | 733502 | Lodged:08:30 16 May 2025Applied For Period:2 YearsRECORDED:08:30 16 May 2025 |
Application to Amend | 734929 | Lodged:15:23:24 03 June 2025Amending:NameFrom:YANGIBANA PTY LTDTo:YANGIBANA JUBILEE PTY LTDRECORDED:15:23:24 03 June 2025 |