Extracted from MTO on 13-Jul-2025 00:19,
last changed 26-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 03-Dec-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 03-Dec-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 03-Dec-2018 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 03-Dec-2018 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 03-Dec-2018 | |
| 1 | In respect to the area designated as CPL 34 in TENGRAPH the following conditions apply: | 03-Dec-2018 | |
6 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 03-Dec-2018 | |
7 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 03-Dec-2018 | |
8 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 03-Dec-2018 | |
9 | 1 | No interference with Geodetic Survey Station NMF 629 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 03-Dec-2018 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 03-Dec-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 03-Dec-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 03-Dec-2018 | |
4 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 03-Dec-2018 | |
5 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 03-Dec-2018 | |
| 1 | In respect to the area designated as CPL 34 in TENGRAPH the following conditions apply: | 03-Dec-2018 | |
6 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 03-Dec-2018 | |
7 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 03-Dec-2018 | |
8 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 03-Dec-2018 | |
9 | 1 | No interference with Geodetic Survey Station NMF 629 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 03-Dec-2018 | |
Type | Number | Details |
Extension / Renewal of Term | 691281 | Lodged:10:38:18 01 December 2023Applied For Period:5 YearsRECORDED:10:38:18 01 December 2023GRANTED:12 March 2024Granted Period:5 YearsTerm Extended To:02/12/2028 |
Partial Surrender - Voluntary | 720847 | Lodged:11:37:25 29 November 2024Surrendered Blocks:HAMERSLEY RANGE 2988 n
HAMERSLEY RANGE 2989 h, o, q, r, s, tSurrendered Total:7 BL.REGISTERED:11:37:25 29 November 2024 |