Extracted from MTO on 21-Apr-2021 03:52,
last changed 04-Apr-2021.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 04-Apr-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Apr-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Apr-2018 | |
4 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Apr-2018 | |
5 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the Licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Apr-2018 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 04-Apr-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Apr-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Apr-2018 | |
4 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Apr-2018 | |
5 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the Licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Apr-2018 | |
Type | Number | Details |
Extension of Time | 496597 | Lodged:10:00 21 October 2016Type:Service on PastoralistRECORDED:10:00 21 October 2016APPROVED:14:03 21 November 2016 |
Extension of Time | 497111 | Lodged:10:21:15 17 November 2016Type:Service on PastoralistRECORDED:10:21:15 17 November 2016APPROVED:14:03 21 November 2016 |
Application to Amend | 534349 | Lodged:10:16:01 05 July 2018Amending:Address (Including DTC Details)From:Principal Place of Business : HURRICANE PROSPECTING PTY LTD, 61 THE STRAND, BAYSWATER, WA, 6053, xxxxxxxxxxxx@gmail.com, xxxxxxx404 and DTC :HURRICANE PROSPECTING PTY LTD, 61 THE STRAND, BAYSWATER, WA, 6053To:Principal Place of Business : HURRICANE PROSPECTING PTY LTD, DEBLIN TENEMENT MANAGEMENT SERVICES, PO BOX 456, MOUNT HAWTHORN, WA, 6915, xxxx@deblin.com.au, xxxxxxx190 and DTC :HURRICANE PROSPECTING PTY LTD, THE TENEMENT MANAGER, DEBLIN TENEMENT MANAGEMENT SERVICES, PO BOX 456, MOUNT HAWTHORN, WA, 6915, xxxx@deblin.com.au, xxxxxxx190RECORDED:10:16:01 05 July 2018 |
Extension of Time | 581321 | Lodged:08:30 03 July 2020Type:Form 5RECORDED:08:30 03 July 2020APPROVED:13:09:32 03 July 2020Additional time granted to 15 Aug 2020 for the year ending 2020. |