Extracted from MTO on 11-Jul-2025 01:36,
last changed 27-Jun-2025.
# | Ver | Text | Start | End |
1 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, IndustryRegulation and Safety. | 27-Aug-2024 | |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 07-Jun-2019 | 26-Aug-2024 |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 07-Jun-2019 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 07-Jun-2019 | |
4 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 07-Jun-2019 | |
5 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 07-Jun-2019 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licences 08/52 and 08/132 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 07-Jun-2019 | |
7 | 1 | No interference with Geodetic Survey Stations J 84A/102, J 84A/104, J 85A/4, J85A/1, Yanrey 40 and Yanrey 40T and and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 07-Jun-2019 | |
8 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 07-Jun-2019 | |
9 | 1 | No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 07-Jun-2019 | |
| 1 | In respect to the area designated as CPL 38 in TENGRAPH the following conditions apply: | 07-Jun-2019 | 08-Jul-2021 |
10 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 07-Jun-2019 | 08-Jul-2021 |
11 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 07-Jun-2019 | 08-Jul-2021 |
12 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 07-Jun-2019 | 08-Jul-2021 |
13 | 1 | No mining within 25 metres of either side of the petroleum pipeline licence area of PPA 69 and to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area. | 07-Jun-2019 | |
14 | 1 | No surface excavation approaching closer to the boundary of the Consultation Area than a distance equal to three times the depth of the excavation without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 07-Jun-2019 | |
15 | 1 | No explosives being used or stored within 150 metres of the petroleum licence area without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 07-Jun-2019 | |
16 | 1 | The rights of ingress to and egress from the petroleum pipeline licence area being at all times preserved for the employees, contractors and agents of the owners and operators of the pipeline. | 07-Jun-2019 | |
17 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purposes of protecting the pipeline and any existing condition imposed for this purpose may be cancelled or varied. | 07-Jun-2019 | |
18 | 1 | The Licensee's attention is drawn to the existence of File Notation Area subject to Ashburton North Stategic Industrial Area Improvement Scheme - Subject to Western Australian Planning Commision granted pursuant to section 91 of the Land Administration Act 1997 and which is shown designated asFNA 12505 in TENGRAPH. | 07-Jun-2019 | 15-Dec-2020 |
19 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 27-Aug-2024 | |
20 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 27-Aug-2024 | |
21 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 27-Aug-2024 | |
Cond # | Ver | Text | Start | End |
1 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, IndustryRegulation and Safety. | 27-Aug-2024 | |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, Department of Mines, Industry Regulation and Safety. | 07-Jun-2019 | 26-Aug-2024 |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 07-Jun-2019 | |
3 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 07-Jun-2019 | |
4 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 07-Jun-2019 | |
5 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 07-Jun-2019 | |
6 | 1 | The rights of ingress to and egress from Miscellaneous Licences 08/52 and 08/132 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 07-Jun-2019 | |
7 | 1 | No interference with Geodetic Survey Stations J 84A/102, J 84A/104, J 85A/4, J85A/1, Yanrey 40 and Yanrey 40T and and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 07-Jun-2019 | |
8 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 07-Jun-2019 | |
9 | 1 | No interference with the transmission line or the installations in connection therewith, and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 07-Jun-2019 | |
| 1 | In respect to the area designated as CPL 38 in TENGRAPH the following conditions apply: | 07-Jun-2019 | 08-Jul-2021 |
10 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Resource and Environmental Compliance, Department of Mines, Industry Regulation and Safety (DMIRS) the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Resource and Environmental Compliance, DMIRS. The program to include:
- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 07-Jun-2019 | 08-Jul-2021 |
11 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Resource and Environmental Compliance, DMIRS. Such rehabilitation as is appropriate and may include:
- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 07-Jun-2019 | 08-Jul-2021 |
12 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMIRS and arranging an inspection as required. | 07-Jun-2019 | 08-Jul-2021 |
13 | 1 | No mining within 25 metres of either side of the petroleum pipeline licence area of PPA 69 and to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area. | 07-Jun-2019 | |
14 | 1 | No surface excavation approaching closer to the boundary of the Consultation Area than a distance equal to three times the depth of the excavation without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 07-Jun-2019 | |
15 | 1 | No explosives being used or stored within 150 metres of the petroleum licence area without the mining tenement holder and the petroleum pipeline licensee reaching agreement as to a lesser distance. | 07-Jun-2019 | |
16 | 1 | The rights of ingress to and egress from the petroleum pipeline licence area being at all times preserved for the employees, contractors and agents of the owners and operators of the pipeline. | 07-Jun-2019 | |
17 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purposes of protecting the pipeline and any existing condition imposed for this purpose may be cancelled or varied. | 07-Jun-2019 | |
18 | 1 | The Licensee's attention is drawn to the existence of File Notation Area subject to Ashburton North Stategic Industrial Area Improvement Scheme - Subject to Western Australian Planning Commision granted pursuant to section 91 of the Land Administration Act 1997 and which is shown designated asFNA 12505 in TENGRAPH. | 07-Jun-2019 | 15-Dec-2020 |
19 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 27-Aug-2024 | |
20 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 27-Aug-2024 | |
21 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 27-Aug-2024 | |
Type | Number | Details |
Objection | 491668 | Lodged:12:06:38 02 August 2016Objectors:YARRI MINING PTY LTDObjection Type:Tenement ApplicationWithdrawn on 9 August, 2016 |
Objection | 491812 | Lodged:15:10:10 04 August 2016Objectors:YARRI MINING PTY LTDObjection Type:Tenement ApplicationRECORDED:15:10:10 04 August 2016WITHDRAWN:10:00 15 December 2017 |
Application to Amend | 525623 | Lodged:09:39:21 15 March 2018Amending:Address (Including DTC Details)From:SQUADRON RESOURCES PTY LTD, 80 BIRDWOOD PARADE, DALKEITH, WA, 6009To:SQUADRON RESOURCES PTY LTD, C/-HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxxxx977RECORDED:09:39:21 15 March 2018 |
Application to Amend | 531446 | Lodged:15:47:31 29 May 2018Amending:Address (Including DTC Details)From:SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977To:SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxx977RECORDED:15:47:31 29 May 2018 |
Application to Amend | 554325 | Lodged:15:35 21 May 2019Amending:Address (Including DTC Details)From:Principal Place of Business : SQUADRON RESOURCES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849 and DTC :SQUADRON RESOURCES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES (WA) PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849To:Principal Place of Business : SQUADRON RESOURCES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849 and DTC :SQUADRON RESOURCES PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxxx977RECORDED:15:35 21 May 2019 |
Application to Amend | 581636 | Lodged:11:28:02 08 July 2020Amending:NameFrom:SQUADRON RESOURCES PTY LTDTo:WYLOO METALS PTY LTDREJECTED:11:28:02 08 July 2020 |
Application to Amend | 581792 | Lodged:08:30 10 July 2020Amending:NameFrom:SQUADRON RESOURCES PTY LTDTo:WYLOO METALS PTY LTDRECORDED:08:30 10 July 2020 |
Application to Amend | 590133 | Lodged:14:30 11 November 2020REJECTED:14:30 11 November 2020Relodged:11:12 13 November 2020Amending:Address (Including DTC Details)From:Principal Place of Business : WYLOO METALS PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849 and DTC :WYLOO METALS PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, PO BOX 8249, PERTH BUSINESS CENTRE, PERTH, WA, 6849, xxxxx@hemts.com.au, xxxxxx977To:Principal Place of Business : WYLOO METALS PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :WYLOO METALS PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxxx977RECORDED:11:12 13 November 2020 |
Partial Surrender - Voluntary | 618324 | Lodged:16:21:12 19 March 2021Surrendered Blocks:HAMERSLEY RANGE 1525 x, z
HAMERSLEY RANGE 1596 g, n, s, x
HAMERSLEY RANGE 1597 c, d, e, j, k, o, p, u, z
HAMERSLEY RANGE 1598 a, f, l, q, v, w, z
HAMERSLEY RANGE 1668 c
HAMERSLEY RANGE 1669 e, k
HAMERSLEY RANGE 1670 a, b, f, g, l, m, r, s, w, x
HAMERSLEY RANGE 1740 u, z
HAMERSLEY RANGE 1742 b, c, g, h
HAMERSLEY RANGE 1812 e, j, k, p, u, z
HAMERSLEY RANGE 1813 f, l, m, q, r, s, v, w, x, y
HAMERSLEY RANGE 1884 e, k, p, u, z
HAMERSLEY RANGE 1885 a, b, c, d, e, f, g, h, j, k, l, m, n, o, p, q, r, s, t, u, v, w, x, y, z
HAMERSLEY RANGE 1956 e
HAMERSLEY RANGE 1957 a, b, c, d, eSurrendered Total:93 BL.REGISTERED:16:21:12 19 March 2021 |
Application to Amend | 633392 | Lodged:13:18:54 01 October 2021Amending:Address (Including DTC Details)From:Principal Place of Business : WYLOO METALS PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, LEVEL 19, SUITE 4, 44 ST GEORGES TERRACE, PERTH, WA, 6000 and DTC :WYLOO METALS PTY LTD, HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, C/- HETHERINGTON EXPLORATION & MINING TITLE SERVICES PTY LTD, SUITE 404, GROUND FLOOR, 50 ST GEORGES TERRACE, PERTH, WA, 6000, xxxxx@hemts.com.au, xxxxxx977To:Principal Place of Business : WYLOO METALS PTY LTD, 171-173 MOUNTS BAY ROAD, PERTH, WA, 6000, xxxxxxxxx@wyloometals.com, xxxxxxx949 and DTC :WYLOO METALS PTY LTD, WYLOO METALS PTY LTD, PO BOX 3155, BROADWAY NEDLANDS, WA, 6009, xxxxxxxxx@wyloometals.com, xxxxxxx949RECORDED:13:18:54 01 October 2021 |
Partial Surrender - Voluntary | 683114 | Lodged:14:42:19 07 August 2023Surrendered Blocks:HAMERSLEY RANGE 1813 t, u, zSurrendered Total:3 BL.REGISTERED:14:42:19 07 August 2023 |
Application to Amend | 688493 | Lodged:12:09:55 24 October 2023Amending:Address (Including DTC Details)From:Principal Place of Business : WYLOO METALS PTY LTD, 171-173 MOUNTS BAY ROAD, PERTH, WA, 6000, xxxxxxxxx@wyloometals.com, xxxxxxx949 and DTC :WYLOO METALS PTY LTD, WYLOO METALS PTY LTD, PO BOX 3155, BROADWAY NEDLANDS, WA, 6009, xxxxxxxxx@wyloometals.com, xxxxxxx949To:Principal Place of Business : WYLOO METALS PTY LTD, LEVEL 1, 8 RICHARDSON STREET, WEST PERTH, WA, 6005, xxxxxxxxx@wyloo.com, xxxxxxxxxxxx200 and DTC :WYLOO METALS PTY LTD, WYLOO METALS PTY LTD, PO BOX 1810, WEST PERTH, WA, 6872, xxxxxxxxx@wyloo.com, xxxxxxxxxxxx200RECORDED:12:09:55 24 October 2023 |
Partial Surrender - Voluntary | 696528 | Lodged:13:00:10 14 February 2024Surrendered Blocks:HAMERSLEY RANGE 1524 m, r, w
HAMERSLEY RANGE 1525 w
HAMERSLEY RANGE 1596 b, h, o, t, y
HAMERSLEY RANGE 1597 b, h, n, t, y
HAMERSLEY RANGE 1668 d, j, o, u, z
HAMERSLEY RANGE 1669 d, j, o, p, u, z
HAMERSLEY RANGE 1670 q, v
HAMERSLEY RANGE 1740 e, k, p
HAMERSLEY RANGE 1741 e, k, p
HAMERSLEY RANGE 1742 aSurrendered Total:34 BL.REGISTERED:13:00:10 14 February 2024 |
Extension / Renewal of Term | 704232 | Lodged:08:30 16 May 2024Applied For Period:5 YearsRECORDED:08:30 16 May 2024GRANTED:23 July 2024Granted Period:5 YearsTerm Extended To:06/06/2029 |
Application to Amend | 720693 | Lodged:10:36:23 28 November 2024Amending:Address (Including DTC Details)From:Principal Place of Business : WYLOO METALS PTY LTD, LEVEL 1, 8 RICHARDSON STREET, WEST PERTH, WA, 6005, xxxxxxxxx@wyloo.com, xxxxxxxxxxxx200 and DTC :WYLOO METALS PTY LTD, WYLOO METALS PTY LTD, PO BOX 1810, WEST PERTH, WA, 6872, xxxxxxxxx@wyloo.com, xxxxxxxxxxxx200To:Principal Place of Business : WYLOO METALS PTY LTD, LEVEL 8, TOWER 3 CAPITAL SQUARE, 1 SPRING STREET, PERTH, WA, 6000, xxxxxxxxx@wyloo.com, xxxxxxxxxxxx200 and DTC :WYLOO METALS PTY LTD, WYLOO METALS PTY LTD, PO BOX 7142, CLOISTERS SQUARE, PERTH, WA, 6850, xxxxxxxxx@wyloo.com, xxxxxxxxxxxx200RECORDED:10:36:23 28 November 2024 |
Application to Amend | 720697 | Lodged:10:56:29 28 November 2024Amending:Address (Including DTC Details)FromToREJECTED:10:56:29 28 November 2024 |
Partial Surrender - Voluntary | 723760 | Lodged:13:07 17 January 2025Surrendered Blocks:HAMERSLEY RANGE 1524 g, n, s, x
HAMERSLEY RANGE 1525 v
HAMERSLEY RANGE 1596 c, j, p, u, z
HAMERSLEY RANGE 1597 a, g, m, s, x
HAMERSLEY RANGE 1668 e, k, p
HAMERSLEY RANGE 1669 c, q, t, v, y
HAMERSLEY RANGE 1741 a, d, f, j, l, o, q, u, v, z
HAMERSLEY RANGE 1813 aSurrendered Total:34 BL.REGISTERED:13:07 17 January 2025 |