Extracted from MTO on 03-Jul-2025 00:37,
last changed 03-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 26-Feb-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 26-Feb-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 26-Feb-2018 | |
4 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 26-Feb-2018 | |
5 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 26-Feb-2018 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, DMIRS. Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMIRS. | 26-Feb-2018 | |
2 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 26-Feb-2018 | |
3 | 1 | Unless the written approval of the Environmental Officer, DMIRS is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 26-Feb-2018 | |
4 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 26-Feb-2018 | |
5 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 26-Feb-2018 | |
Type | Number | Details |
Objection | 486117 | Lodged:11:15:32 04 May 2016Objectors:RED SKY STATIONS PTY LTDObjection Type:Tenement ApplicationRECORDED:11:15:32 04 May 2016received minute of programming directions dated 23 February 2017 to finalise objectionFINALISED:10:00 10 March 2017Wardens Decision Made on:10:00 10 March 2017Wardens Decision Status:Finalised |
Application to Amend | 530892 | Lodged:10:15:27 22 May 2018Amending:Address (Including DTC Details)From:Principal Place of Business : D & G SPRALJA PTY LTD, SAME AS CORRESPONDENCE and DTC :D & G SPRALJA PTY LTD, 94 COOK STREET, PORTSMITH, QLD, 4870To:Principal Place of Business : D & G SPRALJA PTY LTD, 94 COOK STREET, PORTSMITH, QLD, 4870, xxxxx@cairnsmarble.com, xxxxxxxxxxx211 and DTC :D & G SPRALJA PTY LTD, D & G SPRALJA PTY LTD, 94 COOK STREET, PORTSMITH, QLD, 4870, xxxxx@cairnsmarble.com, xxxxxxxxxxx211RECORDED:10:15:27 22 May 2018 |
Extension of Time | 552422 | Lodged:11:09:06 29 April 2019Type:Form 5RECORDED:11:09:06 29 April 2019APPROVED:16:14:01 29 April 2019 |
Extension of Time | 552556 | Lodged:10:15 30 April 2019Type:Exemption from ExpenditureRECORDED:10:15 30 April 2019WITHDRAWN:16:27 01 August 2019 |
Application for Forfeiture | 552971 | Lodged:13:10:30 06 May 2019Applicant:SQUADRON RESOURCES PTY LTDRespondent:D & G SPRALJA PTY LTDRECORDED:13:10:30 06 May 2019Warden's Determination:Dismissed 31/01/2020 10:00:00 |
Forfeiture | 576641 | Initiated:24/04/2020 for non-compliance with expenditure requirementsRECORDED:13:59 24 April 2020Notice Issued:Regulation 50 Notice sent 24/04/2020 for non-compliance with expenditure requirements pursuant to Reg 21/Sec 63A- under expended.Compliance Date:03/06/2020 |
Application to Amend | 626859 | Lodged:14:27:12 24 June 2021Amending:Address (Including DTC Details)From:STONE DIMENSIONS AUSTRALIA PTY LTD, SUITE 50, BLUEWATER 15 LABOUCHERE ROAD, SOUTH PERTH, WA, 6151, xxxxxx@lawtonlawyers.com.auTo:STONE DIMENSIONS AUSTRALIA PTY LTD, STONE DIMENSIONS OF AUSTRALIA PTY LTD, PO BOX 342, SOUTH PERTH, WA, 6951REJECTED:14:27:12 24 June 2021 |
Expiry - Full | 671636 | EFFECTIVE:Midnight 25 February 2023 |