Extracted from MTO on 08-Mar-2021 03:55,
last changed 30-Jan-2021.
# | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 23-Nov-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Nov-2016 | |
3 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 23-Nov-2016 | |
4 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the Licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 23-Nov-2016 | |
5 | 1 | No activities being carried out within the proposed railway corridor (designated FNA 9198 ) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent. | 23-Nov-2016 | |
6 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No 24 as shown in TENGRAPH. | 23-Nov-2016 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP | 23-Nov-2016 | |
8 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 23-Nov-2016 | |
9 | 1 | The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP | 23-Nov-2016 | |
10 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP. | 23-Nov-2016 | |
11 | 1 | Mining on the Safety Zone established in Condition 6 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP . | 23-Nov-2016 | |
12 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 6 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 23-Nov-2016 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 23-Nov-2016 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 23-Nov-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Nov-2016 | |
3 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 23-Nov-2016 | |
4 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the Licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 23-Nov-2016 | |
5 | 1 | No activities being carried out within the proposed railway corridor (designated FNA 9198 ) that interfere with or restrict any rail route investigation activities being undertaken by the rail line proponent. | 23-Nov-2016 | |
6 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No 24 as shown in TENGRAPH. | 23-Nov-2016 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP | 23-Nov-2016 | |
8 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 23-Nov-2016 | |
9 | 1 | The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP | 23-Nov-2016 | |
10 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP. | 23-Nov-2016 | |
11 | 1 | Mining on the Safety Zone established in Condition 6 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP . | 23-Nov-2016 | |
12 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 6 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 23-Nov-2016 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 23-Nov-2016 | |
Type | Number | Details |
Application to Amend | 531607 | Lodged:10:48:42 31 May 2018Amending:Address (Including DTC Details)From:Principal Place of Business : CORONA MINING PTY LTD, SAME AS CORRESPONDENCE and DTC :CORONA MINING PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:Principal Place of Business : CORONA MINING PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxxxx400 and DTC :CORONA MINING PTY LTD, AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947, xxxxxxxxx@austwidemining.com.au, xxxxxxxxx400RECORDED:10:48:42 31 May 2018 |