Extracted from MTO on 08-Mar-2021 03:52,
last changed 14-Oct-2020.
# | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Jul-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Jul-2016 | |
3 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Jul-2016 | |
4 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the Licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Jul-2016 | |
5 | 1 | No interference with Geodetic Survey Stations YANREY 28, YANREY 29 and YANREY 30 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 04-Jul-2016 | |
6 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No. 40 as shown in TENGRAPH. | 04-Jul-2016 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP | 04-Jul-2016 | |
8 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 04-Jul-2016 | |
9 | 1 | The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP | 04-Jul-2016 | |
10 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP. | 04-Jul-2016 | |
11 | 1 | Mining on the Safety Zone established in Condition 6 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP . | 04-Jul-2016 | |
12 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 6 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 04-Jul-2016 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 04-Jul-2016 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Jul-2016 | |
2 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Jul-2016 | |
3 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Jul-2016 | |
4 | 1 | The licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-
- the grant of the Licence; or
- registration of a transfer introducing a new licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Jul-2016 | |
5 | 1 | No interference with Geodetic Survey Stations YANREY 28, YANREY 29 and YANREY 30 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 04-Jul-2016 | |
6 | 1 | No mining within 25 metres of either side of the Gas/Petroleum pipeline contained within Petroleum Pipeline Licence No. 40 as shown in TENGRAPH. | 04-Jul-2016 | |
7 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 6 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the Director Petroleum DMP | 04-Jul-2016 | |
8 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 6 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 04-Jul-2016 | |
9 | 1 | The licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 6 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the Director Petroleum DMP | 04-Jul-2016 | |
10 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the Director Petroleum DMP. | 04-Jul-2016 | |
11 | 1 | Mining on the Safety Zone established in Condition 6 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the Director Petroleum DMP . | 04-Jul-2016 | |
12 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 6 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 04-Jul-2016 | |
13 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 04-Jul-2016 | |
Type | Number | Details |
Objection | 476455 | Lodged:13:04 27 October 2015Objectors:RED SKY STATIONS PTY LTDObjection Type:Tenement ApplicationRECORDED:13:04 27 October 2015Warden made orders in terms of Minute of Consent Orders dated 1 December 2015 amending description of E08/2774 to exclude Hamersley Range Primary Blocks 2318 c, d and e and 2319 a and b and withdrawing objection.WITHDRAWN:10:00 17 December 2015 |
Application to Amend | 512344 | Lodged:13:48:12 10 August 2017Amending:Address (Including DTC Details)From:Principal Place of Business : CAULDRON ENERGY LTD, SAME AS CORRESPONDENCE and DTC :CAULDRON ENERGY LTD, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901To:Principal Place of Business : CAULDRON ENERGY LTD, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901, xxxxxxx@capelam.com.au, xxxxxxx555 and DTC :CAULDRON ENERGY LTD, NGAIRE KOCH, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901, xxxxxxx@capelam.com.au, xxxxxxx555RECORDED:13:48:12 10 August 2017 |
Application to Amend | 524209 | Lodged:15:11:18 21 February 2018Amending:Address (Including DTC Details)From:Principal Place of Business : CAULDRON ENERGY LTD, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901, xxxxxxx@capelam.com.au, xxxxxxx555 and DTC :CAULDRON ENERGY LTD, NGAIRE KOCH, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901, xxxxxxx@capelam.com.au, xxxxxxx555To:Principal Place of Business : CAULDRON ENERGY LTD, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901, xxxxxxxxxxxxx@capelam.com.au, xxxxxxx555 and DTC :CAULDRON ENERGY LTD, MELISSA CAYLEY, LAND AND AGREEMENTS MANAGER, PO BOX 1385, WEST LEEDERVILLE, WA, 6901, xxxxxxxxxxxxx@capelam.com.au, xxxxxxx555RECORDED:15:11:18 21 February 2018 |