1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 06-May-2020 | |
2 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 06-May-2020 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 06-May-2020 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 06-May-2020 | |
5 | 1 | The rights of ingress to and egress from Miscellaneous Licence 08/158, 47/784 and 47/909 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 06-May-2020 | |
6 | 1 | The rights of ingress to and egress from Mineral Lease 248SA being at all times preserved to the lessee and no interference with the purpose or installations (either present or future) connected to Mineral Lease 248SA. | 06-May-2020 | |
7 | 1 | No excavation, excepting shafts, approaching closer to the Pannawonica Road, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Pannawonica Road or Highway verge being confined to below a depth of 30 metres from the natural surface. | 06-May-2020 | |
8 | 1 | No mining on a strip of land 60 metres wide with the Mesa A Railway Line as the centreline and no materials being deposited or machinery or buildings being erected on such strip of land. | 06-May-2020 | |
9 | 1 | Blasting operations being controlled so that no damage or injury can be caused by fly rock, concussion, vibration or other means. | 06-May-2020 | |
10 | 1 | No interference with Geodetic Survey Station SSM-YARRALOOLA 77 and 78 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 06-May-2020 | |
11 | 1 | The Licencee shall not interfere with any installations, structures, excavations, roads and improvements situated or to be situated on General Lease K876559. | 06-May-2020 | |
12 | 1 | The rights of ingress to and egress from the General Lease K876559 land being at all times preserved to the lessee. | 06-May-2020 | |
13 | 1 | No mining within 25 metres of either side of the petroleum pipeline licence area of PL105 to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area. | 06-May-2020 | |
14 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 12 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 06-May-2020 | |
15 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 12 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 06-May-2020 | |
16 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 12 hereof without the prior approval of the operator of the railway on corridor land. | 06-May-2020 | |
17 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 12 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 06-May-2020 | |
18 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 06-May-2020 | |
19 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 06-May-2020 | |
20 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 06-May-2020 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 06-May-2020 | |
2 | 1 | Unless the written approval of the Environmental Officer, Department of Mines, Industry Regulation and Safety is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 06-May-2020 | |
3 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 06-May-2020 | |
4 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 06-May-2020 | |
5 | 1 | The rights of ingress to and egress from Miscellaneous Licence 08/158, 47/784 and 47/909 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 06-May-2020 | |
6 | 1 | The rights of ingress to and egress from Mineral Lease 248SA being at all times preserved to the lessee and no interference with the purpose or installations (either present or future) connected to Mineral Lease 248SA. | 06-May-2020 | |
7 | 1 | No excavation, excepting shafts, approaching closer to the Pannawonica Road, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the Pannawonica Road or Highway verge being confined to below a depth of 30 metres from the natural surface. | 06-May-2020 | |
8 | 1 | No mining on a strip of land 60 metres wide with the Mesa A Railway Line as the centreline and no materials being deposited or machinery or buildings being erected on such strip of land. | 06-May-2020 | |
9 | 1 | Blasting operations being controlled so that no damage or injury can be caused by fly rock, concussion, vibration or other means. | 06-May-2020 | |
10 | 1 | No interference with Geodetic Survey Station SSM-YARRALOOLA 77 and 78 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 06-May-2020 | |
11 | 1 | The Licencee shall not interfere with any installations, structures, excavations, roads and improvements situated or to be situated on General Lease K876559. | 06-May-2020 | |
12 | 1 | The rights of ingress to and egress from the General Lease K876559 land being at all times preserved to the lessee. | 06-May-2020 | |
13 | 1 | No mining within 25 metres of either side of the petroleum pipeline licence area of PL105 to a depth of 50 metres being the Consultation Area as shown in TENGRAPH, without the mining tenement holder and the petroleum pipeline licensee consulting with each other and reaching agreement on access and mining activities to be undertaken within the Consultation Area. | 06-May-2020 | |
14 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by Condition 12 hereof than a distance equal to three times the depth of the excavation without the prior written approval of Mines Safety, DMIRS. | 06-May-2020 | |
15 | 1 | Mining below 15 metres from the natural surface of the land in the Safety Zone established in Condition 12 hereof being approved by Mines Safety, DMIRS in consultation with the operator of the railway on corridor land. | 06-May-2020 | |
16 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 12 hereof without the prior approval of the operator of the railway on corridor land. | 06-May-2020 | |
17 | 1 | The Licensee not excavating, drilling, installing, erecting, depositing or permitting to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 12 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of Mines Safety, DMIRS. | 06-May-2020 | |
18 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the rail corridor land without the prior written consent of the Director, Dangerous Goods and Petroleum Safety, DMIRS. | 06-May-2020 | |
19 | 1 | The rights of ingress to and egress from the rail corridor land being at all times preserved to the employees, contractors and agents of the operator of the railway on corridor land, and the Public Transport Authority of WA. | 06-May-2020 | |
20 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the rail corridor land. | 06-May-2020 | |
Type | Number | Details |
Iron Ore Inclusion | 469528 | Lodged:08:30 17 June 2015RECORDED:08:30 17 July 2015AUTHORISED:13:28:13 17 July 2015 |
Objection | 471421 | Lodged:09:52:55 20 July 2015Objectors:ROBE RIVER MINING CO. PTY LIMITEDObjection Type:Tenement ApplicationRECORDED:09:52:55 20 July 2015Minute of Programming Directions lodged 18/11/2016 to finalise objectionFINALISED:10:00 19 January 2017Wardens Decision Made on:10:00 19 January 2017Wardens Decision Status:Finalised |
Objection | 471422 | Lodged:10:05:46 20 July 2015Objectors:ROBE RIVER LIMITEDObjection Type:Tenement ApplicationRECORDED:10:05:46 20 July 2015Minute of Programming Directions lodged 18/11/2016 to finalise objectionFINALISED:10:00 19 January 2017Wardens Decision Made on:10:00 19 January 2017Wardens Decision Status:Finalised |
Application to Amend | 522059 | Lodged:11:42:57 22 January 2018Amending:Address (Including DTC Details)From:Principal Place of Business : AMCI (IO) PTY LTD, SAME AS CORRESPONDENCE and DTC :AMCI (IO) PTY LTD, L 1 1 PRESTON ST, COMO, WA, 6152To:Principal Place of Business : AMCI (IO) PTY LTD, C/- API MANAGEMENT PTY LTD, LEVEL 14, 225 ST GEORGES TERRACE, PERTH, WA, 6000, xxxx@apijv.com.au, xxxxxx222 and DTC :AMCI (IO) PTY LTD, C/- API MANAGEMENT PTY LTD, PO BOX 7361, CLOSITERS SQUARE, WA, 6850, xxxx@apijv.com.au, xxxxxx222RECORDED:11:42:57 22 January 2018 |
Application to Amend | 522063 | Lodged:11:57:01 22 January 2018Amending:Address (Including DTC Details)From:Principal Place of Business : AQUILA STEEL PTY LTD, SAME AS CORRESPONDENCE and DTC :AQUILA STEEL PTY LTD, L 1 1 PRESTON ST, COMO, WA, 6152To:Principal Place of Business : AQUILA STEEL PTY LTD, C/- API MANAGEMENT PTY LTD, LEVEL 14, 225 ST GEORGES TERRACE, PERTH, WA, 6000, xxxx@apijv.com.au, xxxxxx222 and DTC :AQUILA STEEL PTY LTD, C/- API MANAGEMENT PTY LTD, PO BOX 7361, CLOISTERS SQUARE, WA, 6850, xxxx@apijv.com.au, xxxxxx222RECORDED:11:57:01 22 January 2018 |
Application to Amend | 646915 | Lodged:13:37:53 08 April 2022Amending:Address (Including DTC Details)From:AMCI (IO) PTY LTD, C/- API MANAGEMENT PTY LTD, PO BOX 7361, CLOSITERS SQUARE, WA, 6850, xxxx@apijv.com.au, xxxxxx222To:AMCI (IO) PTY LTD, C/- API MANAGEMENT PTY LTD, PO BOX 7361, CLOISTERS SQUARE, WA, 6850, xxxx@apijv.com.au, xxxxxxxxxxxxxx222RECORDED:13:37:53 08 April 2022 |
Application to Amend | 690948 | Lodged:11:39:22 28 November 2023Amending:Address (Including DTC Details)From:AQUILA STEEL PTY LTD, C/- API MANAGEMENT PTY LTD, LEVEL 14, 225 ST GEORGES TERRACE, PERTH, WA, 6000, xxxx@apijv.com.au, xxxxxx222To:AQUILA STEEL PTY LTD, C/- API MANAGEMENT PTY LTD, LEVEL 18, 225 ST GEORGES TERRACE, PERTH, WA, 6000, xxxx@apijv.com.au, xxxxxxxxx222RECORDED:11:39:22 28 November 2023 |
Application to Amend | 690949 | Lodged:11:39:22 28 November 2023Amending:Address (Including DTC Details)From:AMCI (IO) PTY LTD, C/- API MANAGEMENT PTY LTD, LEVEL 14, 225 ST GEORGES TERRACE, PERTH, WA, 6000, xxxx@apijv.com.au, xxxxxx222To:AMCI (IO) PTY LTD, C/- API MANAGEMENT PTY LTD, LEVEL 18, 225 ST GEORGES TERRACE, PERTH, WA, 6000, xxxx@apijv.com.au, xxxxxxxxx222RECORDED:11:39:22 28 November 2023 |
Surrender - Outright | 722210 | Lodged:10:41:55 18 December 2024REGISTERED:10:41:55 18 December 2024 |