1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 18-Jan-2016 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 18-Jan-2016 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Jan-2016 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Jan-2016 | |
| 1 | In respect to the area designated as CPL 38 in TENGRAPH the following conditions apply: | 18-Jan-2016 | |
5 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMP the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMP. The program to include:- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 18-Jan-2016 | |
6 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMP. Such rehabilitation as is appropriate and may include:- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 18-Jan-2016 | |
7 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 18-Jan-2016 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 18-Jan-2016 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 18-Jan-2016 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 18-Jan-2016 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 18-Jan-2016 | |
| 1 | In respect to the area designated as CPL 38 in TENGRAPH the following conditions apply: | 18-Jan-2016 | |
5 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMP the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMP. The program to include:- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 18-Jan-2016 | |
6 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMP. Such rehabilitation as is appropriate and may include:- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 18-Jan-2016 | |
7 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 18-Jan-2016 | |
Type | Number | Details |
Application to Amend | 470348 | Lodged:16:10:28 30 June 2015Amending:AddressFrom:ONSLOW METALS PTY LTD, PO BOX 2086, MALAGA, WA, 6944To:ONSLOW METALS PTY LTD, C/- GETS, PO BOX 10939, KALGOORLIE, WA, 6433RECORDED:16:10:28 30 June 2015 |
Extension of Time | 470840 | Lodged:15:45:25 07 July 2015Type:SecurityRECORDED:15:45:25 07 July 2015APPROVED:10:43:23 22 July 2015 |
Extension of Time | 502743 | Lodged:10:43:31 17 March 2017Type:Form 5RECORDED:10:43:31 17 March 2017APPROVED:13:38:32 17 March 2017Time extended to 31 Mar 2017 for year ending 2017. |
Excess Tonnage | 509540 | Lodged:11:43 29 June 2017RECORDED:11:43 29 June 2017REFUSED:11:57:57 17 August 2017 |
Extension of Time | 524707 | Lodged:11:55:18 01 March 2018Type:Form 5RECORDED:11:55:18 01 March 2018APPROVED:14:27:56 01 March 2018Time to lodge extended to 01/06/2018 |
Extension of Time | 531320 | Lodged:15:08 28 May 2018Type:Form 5RECORDED:15:08 28 May 2018APPROVED:15:45:40 30 May 2018Time to lodge extended to 01/08/2018 |
Application for Forfeiture | 532230 | Lodged:11:35 07 June 2018Respondent:ONSLOW METALS PTY LTDApplicant:RAFFERTY, SeamusRECORDED:11:35 07 June 2018Warden's Determination:Dismissed 24/08/2018 10:00:00 |
Application to Amend | 551214 | Lodged:15:40:57 08 April 2019Amending:Address (Including DTC Details)From:Principal Place of Business : ONSLOW METALS PTY LTD, SAME AS CORRESPONDENCE and DTC :ONSLOW METALS PTY LTD, C/- GETS, PO BOX 10939, KALGOORLIE, WA, 6433To:Principal Place of Business : ONSLOW METALS PTY LTD, PO BOX 8197, SUBIACO EAST, WA, 6008, xxxxxx@mmwc.com.au, xxxxxxxxx866 and DTC :ONSLOW METALS PTY LTD, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008, xxxxxx@mmwc.com.au, xxxxxxxxx866RECORDED:15:40:57 08 April 2019 |
Expiry - Full | 594309 | EFFECTIVE:Midnight 17 January 2021 |