Extracted from MTO on 15-Jul-2025 01:01,
last changed 28-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 14-Apr-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 14-Apr-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 14-Apr-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 14-Apr-2015 | |
5 | 1 | No excavation, excepting shafts, approaching closer to the North West Coastal Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the North West Coastal Highway or Highway verge being confined to below a depth of 30 metres from the natural surface. | 14-Apr-2015 | |
6 | 1 | No interference with Geodetic Survey Station WYL 94 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 14-Apr-2015 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 08/133 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 14-Apr-2015 | |
| 1 | In respect to the area designated as CPL 44 in TENGRAPH the following conditions apply: | 14-Apr-2015 | |
8 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMP the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMP. The program to include:- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 14-Apr-2015 | |
9 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMP. Such rehabilitation as is appropriate and may include:- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 14-Apr-2015 | |
10 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 14-Apr-2015 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 14-Apr-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 14-Apr-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 14-Apr-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 14-Apr-2015 | |
5 | 1 | No excavation, excepting shafts, approaching closer to the North West Coastal Highway, Highway verge or the road reserve than a distance equal to twice the depth of the excavation and mining on the North West Coastal Highway or Highway verge being confined to below a depth of 30 metres from the natural surface. | 14-Apr-2015 | |
6 | 1 | No interference with Geodetic Survey Station WYL 94 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 14-Apr-2015 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licence 08/133 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licence. | 14-Apr-2015 | |
| 1 | In respect to the area designated as CPL 44 in TENGRAPH the following conditions apply: | 14-Apr-2015 | |
8 | 1 | Prior to any ground-disturbing activity, as defined by the Executive Director, Environment Division, DMP the licensee preparing a detailed program for each phase of proposed exploration for approval of the Executive Director, Environment Division, DMP. The program to include:- maps and/or aerial photographs showing all proposed routes, construction and upgrading of tracks, camps, drill sites and any other disturbances;
- the purpose, specifications and life of all proposed disturbances;
- proposals which may disturb any declared rare or geographically restricted flora and fauna; and
- techniques, prescriptions and timetable for the rehabilitation of all proposed disturbances
| 14-Apr-2015 | |
9 | 1 | The licensee, at his expense, rehabilitating all areas cleared, explored or otherwise disturbed during the term of the licence to the satisfaction of the Executive Director, Environment Division, DMP. Such rehabilitation as is appropriate and may include:- stockpiling and return of topsoil;
- backfilling all holes, trenches and costeans;
- ripping;
- contouring to the original landform;
- revegetation with seed; and
- capping and backfilling of all drill holes.
| 14-Apr-2015 | |
10 | 1 | Prior to the cessation of exploration/prospecting activity the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 14-Apr-2015 | |
Type | Number | Details |
Extension of Time | 440927 | Lodged:10:47 21 February 2014SecurityRECORDED:10:47 21 February 2014APPROVED:09:50 20 March 2014 |
Application to Amend | 502621 | Lodged:10:25 15 March 2017Amending:Address (Including DTC Details)From:Principal Place of Business : NORTH WEST STONE PTY LTD, SAME AS CORRESPONDENCE and DTC :NORTH WEST STONE PTY LTD, PO BOX 588, BELMONT, WA, 6984To:Principal Place of Business : NORTH WEST STONE PTY LTD, 675 MURRAY STREET, WEST PERTH, WA, 6005 and DTC :NORTH WEST STONE PTY LTD, PO BOX 1088, WEST PERTH, WA, 6872RECORDED:10:25 15 March 2017 |
Surrender - Outright | 575911 | Lodged:15:22:17 09 April 2020REJECTED:15:22:17 09 April 2020 |
Surrender - Outright | 576179 | Lodged:09:30 15 April 2020REJECTED:09:30 15 April 2020 |
Expiry - Full | 576476 | EFFECTIVE:Midnight 13 April 2020 |