Extracted from MTO on 02-Jul-2025 01:07,
last changed 02-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 17-Dec-2013 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 17-Dec-2013 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 17-Dec-2013 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 17-Dec-2013 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 17-Dec-2013 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 17-Dec-2013 | |
7 | 1 | No interference with Geodetic Survey Stations SSM-NMF 271,SSM-SALT,SSM-Yarraloola 54, 55, 56, 57, 58, 59, 65, 66 and 67 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 17-Dec-2013 | |
8 | 1 | In respect of the area covered by this licence if the Yaburara & Mardudhunera People (being the applicants in Federal Court Application No. WAD 127 of 1997 (WC96/89) send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Yaburara & Mardudhunera People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Pilbara Native Title Service. | 17-Dec-2013 | |
9 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Public Purposes Reserve 380 and Seabed, Foreshore and Navigable Waters. | 17-Dec-2013 | |
| 1 | Consent to explore on De Grey Mullewa Stock Route Reserve 9701 granted subject to the following additional condition: | 17-Dec-2013 | |
10 | 1 | No exploration activities being carried out on De Grey Mullewa Stock Route Reserve 9701 which restrict the use of the reserve. | 17-Dec-2013 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 17-Dec-2013 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 17-Dec-2013 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 17-Dec-2013 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 17-Dec-2013 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 17-Dec-2013 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 17-Dec-2013 | |
7 | 1 | No interference with Geodetic Survey Stations SSM-NMF 271,SSM-SALT,SSM-Yarraloola 54, 55, 56, 57, 58, 59, 65, 66 and 67 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 17-Dec-2013 | |
8 | 1 | In respect of the area covered by this licence if the Yaburara & Mardudhunera People (being the applicants in Federal Court Application No. WAD 127 of 1997 (WC96/89) send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Yaburara & Mardudhunera People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Pilbara Native Title Service. | 17-Dec-2013 | |
9 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Public Purposes Reserve 380 and Seabed, Foreshore and Navigable Waters. | 17-Dec-2013 | |
| 1 | Consent to explore on De Grey Mullewa Stock Route Reserve 9701 granted subject to the following additional condition: | 17-Dec-2013 | |
10 | 1 | No exploration activities being carried out on De Grey Mullewa Stock Route Reserve 9701 which restrict the use of the reserve. | 17-Dec-2013 | |
Type | Number | Details |
Extension of Time | 464703 | Lodged:12:05 27 March 2015Type:Form 5RECORDED:12:05 27 March 2015APPROVED:10:34:47 30 March 2015Time extended to 16 March 2015 |
Extension of Time | 481794 | Lodged:14:40 16 February 2016Type:Exemption from ExpenditureRECORDED:14:40 16 February 2016APPROVED:11:00 18 February 2016 |
Extension of Time | 490667 | Lodged:15:40 14 July 2016Type:Exemption from ExpenditureRECORDED:15:40 14 July 2016REFUSED:12:14 02 September 2016 |
Forfeiture | 495005 | Initiated:04/10/2016 for non-compliance with expenditure conditionsRECORDED:10:00 06 October 2016Notice Issued:Regulation 50 Notice sent 04/10/2016 for non-compliance with expenditure conditions pursuant to Reg 15.Compliance Date:08/11/2016FINALISED:Order by Minister on 31 January 2017 that E 08/2401-I be Penalty Imposed |
Fine | 500525 | Fine in respect to:Forfeiture Process 495005Fine reason:Non-compliance with expenditure obligationsPenalty amount:$3,254.00Notification date:07/02/2017Due date:14/03/2017Pursuant to:Section 96A(5)RECORDED:31 January 2017PAYMENT RECEIVED:10 March 2017FINALISED:10 March 2017Receipt Number:06-159106Amount:$3,254.00Remaining balance:$0.00 |
Forfeiture | 503303 | Initiated:28/03/2017 for non-compliance with reporting requirements( Form 5 )RECORDED:09:24:17 27 March 2017Notice Issued:Regulation 50 Notice sent 28/03/2017 for non-compliance with expenditure requirements pursuant to Reg 22/Sec 63A- non lodgement of Form 5.Compliance Date:02/05/2017 |
Application for Forfeiture | 503618 | Lodged:13:23:09 30 March 2017Applicant:LEICHHARDT INDUSTRIALS PTY LTDRespondent:MINERALOGY PTY LTDOn 28 February 2019 the Perth Mining Warden published decision [2019] WAMW 3, in which he made a recommendation to the minister that Exploration Licence 08/2401 be forfeited.Warden's Determination:Upheld 01/03/2019 11:36:19Forfeited by order of the Minister for non compliance with expenditure conditions.
Forfeiture gazetted 12pm 02 August 2019.
14 day prior right of application for the subject land grated to the applicant for forfeiture under Section 100. |
Extension of Time | 504197 | Lodged:15:45 07 April 2017Type:Form 5RECORDED:15:45 07 April 2017REFUSED:15:40:51 10 April 2017 |
Extension of Time | 504589 | Lodged:14:15 13 April 2017Type:Form 5RECORDED:14:15 13 April 2017WITHDRAWN:13:56 19 April 2017 |
Extension of Time | 504800 | Lodged:14:40 20 April 2017Type:Exemption from ExpenditureRECORDED:14:40 20 April 2017REFUSED:12:17 11 May 2017 |
Conversion | 509349 | New Tenement:G 08/89Application Date:09:59:31 29 Jun 2017Section:S67Discontinued due to G 08/89 Withdrawn 14:44 16 April 2018 |
Extension of Time | 524590 | Lodged:15:50 27 February 2018Type:Form 5RECORDED:15:50 27 February 2018LAPSED:12:00 02 August 2019 |
Extension of Time | 525676 | Lodged:14:10 15 March 2018Type:Form 5RECORDED:14:10 15 March 2018LAPSED:12:00 02 August 2019 |
Extension / Renewal of Term | 544648 | Lodged:14:56:17 13 December 2018Applied For Period:5 YearsRECORDED:14:56:17 13 December 2018LAPSED:02 August 2019 |