1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 04-Sep-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 04-Sep-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Sep-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Sep-2015 | |
5 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Sep-2015 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Sep-2015 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licences 08/17, 08/37 and 08/38 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licences. | 04-Sep-2015 | |
8 | 1 | No interference with Geodetic Survey Station FS-4 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 04-Sep-2015 | |
9 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 04-Sep-2015 | |
10 | 1 | All Mining Act tenement activities prohibited within 200 metres of RAMSAR or ANCA listed wetlands (AW 6 Cape Range Subterranean Waterways) unless written permission of the Department of Environment and Conservation is first obtained. | 04-Sep-2015 | |
11 | 1 | No excavation or drilling works, or installation, erection or deposit of any structure or installation on the surface of the land the subject of Miscellaneous Licence 08/17. | 04-Sep-2015 | |
12 | 1 | The rights of ingress and egress being at all times preserved to the Licencee. | 04-Sep-2015 | |
| 1 | Consent to explore on Temporary Reserve 70/2614 granted. | 04-Sep-2015 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 04-Sep-2015 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 04-Sep-2015 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 04-Sep-2015 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 04-Sep-2015 | |
5 | 1 | The licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 04-Sep-2015 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 04-Sep-2015 | |
7 | 1 | The rights of ingress to and egress from Miscellaneous Licences 08/17, 08/37 and 08/38 being at all times preserved to the licensee and no interference with the purpose or installations connected to the licences. | 04-Sep-2015 | |
8 | 1 | No interference with Geodetic Survey Station FS-4 and mining within 15 metres thereof being confined to below a depth of 15 metres from the natural surface. | 04-Sep-2015 | |
9 | 1 | Mining on a strip of land 20 metres wide with any pipeline as the centreline being confined to below a depth of 31 metres from the natural surface and no mining material being deposited upon such strip and the rights of ingress to and egress from the facility being at all times preserved to the owners thereof. | 04-Sep-2015 | |
10 | 1 | All Mining Act tenement activities prohibited within 200 metres of RAMSAR or ANCA listed wetlands (AW 6 Cape Range Subterranean Waterways) unless written permission of the Department of Environment and Conservation is first obtained. | 04-Sep-2015 | |
11 | 1 | No excavation or drilling works, or installation, erection or deposit of any structure or installation on the surface of the land the subject of Miscellaneous Licence 08/17. | 04-Sep-2015 | |
12 | 1 | The rights of ingress and egress being at all times preserved to the Licencee. | 04-Sep-2015 | |
| 1 | Consent to explore on Temporary Reserve 70/2614 granted. | 04-Sep-2015 | |
Type | Number | Details |
Application to Amend | 397341 | Lodged:15:10 11 May 2012REJECTED:15:10 11 May 2012 |
Extension of Time | 397726 | Lodged:16:10 17 May 2012Serve Shire CouncilRECORDED:16:10 17 May 2012APPROVED:10:00 03 April 2014 |
Objection | 398163 | Lodged:14:56 24 May 2012Objectors:LEARMONTH LIMESTONE PTY LTDObjection Type:Tenement ApplicationRECORDED:14:56 24 May 2012WITHDRAWN:15:30 24 May 2012 |
Objection | KR672/112 | Lodged:15:33:13 24 May 2012Objectors:LEARMONTH LIMESTONE PTY LTDObjection Type:Tenement ApplicationRECORDED:15:33:13 24 May 2012filed Minute of Consent Orders dated 6 March, 2014 containing agreed conditions to finalise objection.Wardens Decision Made on:10:00 13 June 2014Wardens Decision Status:FinalisedWardens Decision Text:Objection withdrawn and recommendation made to the Minister to grant E08/2390. |
Application to Amend | 398911 | Lodged:13:45 06 June 2012Amending:Other/Non-title changesRECORDED:13:45 06 June 2012'Sub surface rights apply in respect to all private property". |
Application to Amend | 486600 | Lodged:14:40 11 May 2016Amending:Address (Including DTC Details)From:HANSON CONSTRUCTION MATERIALS PTY LTD, C/- WESTERN TENEMENT SERVICES, PO BOX 428, GREENWOOD, WA, 6924To:HANSON CONSTRUCTION MATERIALS PTY LTD, C/- WESTERN TENEMENT SERVICES, PO BOX 3285, EAST PERTH, WA, 6892RECORDED:14:40 11 May 2016 |
Application to Amend | 507641 | Lodged:12:31:34 06 June 2017Amending:Address (Including DTC Details)From:HANSON CONSTRUCTION MATERIALS PTY LTD, C/- WESTERN TENEMENT SERVICES, PO BOX 3285, EAST PERTH, WA, 6892To:HANSON CONSTRUCTION MATERIALS PTY LTD, WESTERN TENEMENT SERVICES, C/- WESTERN TENEMENT SERVICES, PO BOX 3285, EAST PERTH, WA, 6892, xxxxx@wts.net.au, xxxxxxx111RECORDED:12:31:34 06 June 2017 |
Extension / Renewal of Term | 585434 | Lodged:08:30 03 September 2020Applied For Period:5 YearsRECORDED:08:30 03 September 2020GRANTED:10 November 2020Granted Period:5 YearsTerm Extended To:03/09/2025 |