1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 30-Nov-2012 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 30-Nov-2012 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 30-Nov-2012 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 30-Nov-2012 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 30-Nov-2012 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 30-Nov-2012 | |
7 | 1 | No mining within 25 metres of either side of the Dampier to Perth Gas/Petroleum pipeline as shown in TENGRAPH.
| 30-Nov-2012 | |
8 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 7 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer DMP | 30-Nov-2012 | |
9 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 7 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 30-Nov-2012 | |
10 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 7 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer DMP | 30-Nov-2012 | |
11 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the State Mining Engineer DMP. | 30-Nov-2012 | |
12 | 1 | Mining on the Safety Zone established in Condition 7 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer DMP . | 30-Nov-2012 | |
13 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 7 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 30-Nov-2012 | |
14 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 30-Nov-2012 | |
15 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 30-Nov-2012 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 30-Nov-2012 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 30-Nov-2012 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 30-Nov-2012 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 30-Nov-2012 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 30-Nov-2012 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 30-Nov-2012 | |
7 | 1 | No mining within 25 metres of either side of the Dampier to Perth Gas/Petroleum pipeline as shown in TENGRAPH.
| 30-Nov-2012 | |
8 | 1 | No surface excavation approaching closer to the boundary of the Safety Zone established by condition 7 hereof than a distance equal to three times the depth of the excavation without the prior written approval of the State Mining Engineer DMP | 30-Nov-2012 | |
9 | 1 | No interference with the drainage pattern, and no parking, storage or movement of equipment or vehicles used in the course of mining within the Safety Zone established by Condition 7 hereof without the prior approval of the operators of the Gas/Petroleum pipeline. | 30-Nov-2012 | |
10 | 1 | The Licensee shall not excavate, drill, install, erect, deposit or permit to be excavated, drilled, installed, erected or deposited within the Safety Zone established in Condition 7 hereof, any pit, well, pavement, foundation, building, or other structure or installation, or material of any nature whatsoever without the prior written consent of the State Mining Engineer DMP | 30-Nov-2012 | |
11 | 1 | No explosives being used or stored within one hundred and fifty (150) metres of the Gas/Petroleum pipeline without the prior written consent of the State Mining Engineer DMP. | 30-Nov-2012 | |
12 | 1 | Mining on the Safety Zone established in Condition 7 hereof being confined to below a depth of 50 metres from the natural surface unless otherwise approved by the State Mining Engineer DMP . | 30-Nov-2012 | |
13 | 1 | The rights of ingress to and egress from the pipeline easement established in Condition 7 hereof being at all times preserved for employees, contractors and agents of the operators of the Gas/Petroleum pipeline. | 30-Nov-2012 | |
14 | 1 | Such further conditions as may from time to time be imposed by the Minister responsible for the Mining Act 1978 for the purpose of protecting the Gas/Petroleum pipeline. | 30-Nov-2012 | |
15 | 1 | No interference with the use of the Aerial Landing Ground and mining thereon being confined to below a depth of 15 metres from the natural surface. | 30-Nov-2012 | |
Type | Number | Details |
Application to Amend | 381971 | Lodged:11:31 20 September 2011Amending:AddressFrom:COCCINELLA PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 8638, PERTH BUSINESS CENTRE, WA, 6849To:COCCINELLA PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931RECORDED:11:31 20 September 2011 |
Extension of Time | 480027 | Lodged:13:08 11 January 2016Type:Stat DecRECORDED:13:08 11 January 2016APPROVED:15:30:04 11 January 2016Time extended to 10 February 2016 |
Forfeiture | 488035 | Initiated:31/05/2016 for non-compliance with expenditure conditionsRECORDED:15:30 31 May 2016Notice Issued:Regulation 50 Notice sent 31/05/2016 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:30/06/2016FINALISED:Order by Minister on 13 June 2016 that E 08/2248 be Penalty Imposed |
Fine | 488692 | Fine in respect to:Forfeiture Process 488035Fine reason:Non-compliance with expenditure obligationsPenalty amount:$838.00Notification date:16/06/2016Due date:21/07/2016Pursuant to:Section 96A(5)RECORDED:16 June 2016PAYMENT RECEIVED:16 June 2016Receipt Number:06-154559Amount:$838.00Remaining balance:$0.00FINALISED:16 June 2016 |
Extension / Renewal of Term | 515421 | Lodged:14:49:41 29 September 2017Applied For Period:5 YearsRECORDED:14:49:41 29 September 2017GRANTED:29 November 2017Granted Period:5 YearsTerm Extended To:29/11/2022 |
Partial Surrender - Compulsory | 539236 | Lodged:14:19:02 17 September 2018Section:Section 65 (3)Surrendered Blocks:HAMERSLEY RANGE 2704 u, x, y, z
HAMERSLEY RANGE 2705 q, vSurrendered Total:6 BL.REGISTERED:Midnight 29 November 2018Surrendered area to be released 08:30:00 19/12/2018 under Section 65 (3)Surrendered area released 08:30:00 19/12/2018 under Section 65 (3) |
Application to Amend | 543911 | Lodged:16:27:46 04 December 2018Amending:Address (Including DTC Details)From:Principal Place of Business : COCCINELLA PTY LTD, SAME AS CORRESPONDENCE and DTC :COCCINELLA PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931To:Principal Place of Business : COCCINELLA PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxx997 and DTC :COCCINELLA PTY LTD, MCMAHON MINING TITLE SERVICES PTY LTD, C/- MCMAHON MINING TITLE SERVICES PTY LTD, PO BOX 592, MAYLANDS, WA, 6931, xxxx@mmts.net.au, xxxxxxxxx997RECORDED:16:27:46 04 December 2018 |
Forfeiture | 578569 | Initiated:29/04/2020 for non-compliance with expenditure conditionsRECORDED:13:50 22 May 2020Notice Issued:Regulation 50 Notice sent 29/04/2020 for non-compliance with expenditure conditions pursuant to Reg 15.Compliance Date:02/06/2020FINALISED:Order by Minister on 12 June 2020 that E 08/2248 be Penalty Imposed |
Fine | 579811 | Fine in respect to:Forfeiture Process 578569Fine reason:Non-compliance with expenditure obligationsPenalty amount:$3,348.00Notification date:15/06/2020Due date:20/07/2020Pursuant to:Section 96A(5)RECORDED:12 June 2020PAYMENT RECEIVED:25 June 2020FINALISED:26 June 2020Receipt Number:10150673Amount:$3,348.00Remaining balance:$0.00 |
Surrender - Outright | 596011 | Lodged:11:58:37 16 February 2021REGISTERED:11:58:37 16 February 2021 |