1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 02-Mar-2012 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 02-Mar-2012 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 02-Mar-2012 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 02-Mar-2012 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 02-Mar-2012 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 02-Mar-2012 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 02-Mar-2012 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 02-Mar-2012 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 02-Mar-2012 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 02-Mar-2012 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 02-Mar-2012 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 02-Mar-2012 | |
Type | Number | Details |
Iron Ore Inclusion | 402450 | Lodged:12:10 27 July 2012RECORDED:12:10 27 July 2012AUTHORISED:00:00 10 August 2012 |
Forfeiture | 453983 | Initiated:29/08/2014 for non-compliance with expenditure conditionsRECORDED:09:00 02 September 2014Notice Issued:Regulation 50 Notice sent 29/08/2014 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:29/09/2014FINALISED:Order by Minister on 02 October 2014 that E 08/2209-I be Penalty Imposed |
Fine | 455692 | Fine in respect to:Forfeiture Process 453983Fine reason:Non-compliance with expenditure obligationsPenalty amount:$2,318.00Notification date:03/10/2014Due date:05/11/2014Pursuant to:Section 96A(5)RECORDED:03 October 2014PAYMENT RECEIVED:16 October 2014FINALISED:16 October 2014Receipt Number:06-139908Amount:$2,318.00Remaining balance:$0.00 |
Partial Surrender - Voluntary | 461992 | Lodged:16:08:28 09 February 2015Surrendered Blocks:HAMERSLEY RANGE 3064 p
HAMERSLEY RANGE 3065 f, g, l, m
HAMERSLEY RANGE 3066 j, k, o, p, t, u, y, z
HAMERSLEY RANGE 3067 q, r, s, t, v
HAMERSLEY RANGE 3138 b, c, dSurrendered Total:21 BL.REGISTERED:16:08:28 09 February 2015 |
Application to Amend | 466131 | Lodged:14:10 22 April 2015Amending:AddressFrom:Residential : DRAGON ENERGY LTD, SUITE 8, 1297 HAY STREET, WEST PERTH, WA, 6005 and Correspondence :DRAGON ENERGY LTD, PO BOX 1968, WEST PERTH, WA, 6872To:Residential : DRAGON ENERGY LTD, SAME AS CORRESPONDENCE and Correspondence :DRAGON ENERGY LTD, C/- ALLIANCE MINING CONSULTING, PO BOX 7174, KARAWARA, WA, 6152RECORDED:14:10 22 April 2015 |
Application to Amend | 478855 | Lodged:11:40 11 December 2015Amending:AddressFrom:DRAGON ENERGY LTD, C/- ALLIANCE MINING CONSULTING, PO BOX 7174, KARAWARA, WA, 6152To:DRAGON ENERGY LTD, C/- STELLA MINING MANAGEMENT PTY LTD, PO BOX 7174, KARAWARA, WA, 6152RECORDED:11:40 11 December 2015 |
Caveat | 484317 | Lodged:11:19:31 04 April 2016Caveat Type:Subject to Claim CaveatCaveator:SHANDONG LUNAN GEO-ENGINEERING EXPLORATION INSTITUTEShares Caveated:25/100 shares DRAGON ENERGY LTDREJECTED:11:19:31 04 April 2016 |
Caveat | 484869 | Lodged:15:19:40 11 April 2016Caveat Type:Subject to Claim CaveatCaveator:SHANDONG LUNAN GEO-ENGINEERING EXPLORATION INSTITUTEShares Caveated:25/100 shares DRAGON ENERGY LTDRECORDED:15:19:40 11 April 2016LAPSED:Midnight 01 April 2019RE Surrender - Outright 549467 - 14 day letter sent 18 Mar 19 |
Application to Amend | 498180 | Lodged:11:20:39 07 December 2016Amending:Address (Including DTC Details)From:DRAGON ENERGY LTD, C/- STELLA MINING MANAGEMENT PTY LTD, PO BOX 7174, KARAWARA, WA, 6152To:DRAGON ENERGY LTD, NINA MAS, C/- ANDERSON'S TENEMENT MANAGEMENT, PO BOX 2162, WARWICK, WA, 6024, xxxxx@atmwa.net.au, xxxxx241RECORDED:11:20:39 07 December 2016 |
Extension / Renewal of Term | 501867 | Lodged:12:39:59 01 March 2017Applied For Period:5 YearsRECORDED:12:39:59 01 March 2017GRANTED:12 May 2017Granted Period:5 YearsTerm Extended To:01/03/2022 |
Application to Amend | 502547 | Lodged:11:21:24 14 March 2017Amending:NameFrom:DRAGON ENERGY LTDTo:RIVA RESOURCES LIMITEDRECORDED:11:21:24 14 March 2017 |
Forfeiture | 534761 | Initiated:20/07/2018 for non-compliance with reporting requirementsRECORDED:15:57:40 10 July 2018Notice Issued:Regulation 50 Notice sent 20/07/2018 for non-compliance with reporting requirements pursuant to Sec 115A.Compliance Date:24/08/2018FINALISED:Order by Minister on 27 September 2018 that E 08/2209-I be Penalty Imposed |
Forfeiture | 536111 | Initiated:25/07/2018 for non-compliance with expenditure conditionsRECORDED:08:30 30 July 2018Notice Issued:Regulation 50 Notice sent 25/07/2018 for non-compliance with expenditure conditions pursuant to Reg 15.Compliance Date:29/08/2018 |
Fine | 539817 | Fine in respect to:Forfeiture Process 534761Fine reason:Non-compliance with mineral exploration reporting provisionsPenalty amount:$450.00Notification date:02/10/2018Due date:06/11/2018Pursuant to:Section 96A(5)RECORDED:01 October 2018PAYMENT RECEIVED:16 October 2018FINALISED:16 October 2018Receipt Number:3726924024Amount:$450.00Remaining balance:$0.00 |
Fine | 541264 | Fine in respect to:Forfeiture Process 536111Fine reason:Non-compliance with expenditure obligationsPenalty amount:$650.00Notification date:25/10/2018Due date:29/11/2018Pursuant to:Section 96A(5)RECORDED:25 October 2018PAYMENT RECEIVED:16 November 2018FINALISED:16 November 2018Receipt Number:4919911307Amount:$650.00Remaining balance:$0.00 |
Surrender - Outright | 548624 | Lodged:13:57:11 01 March 2019REJECTED:13:57:11 01 March 2019 |
Surrender - Outright | 549467 | Lodged:15:46:40 15 March 2019REGISTERED:08:30 02 April 2019RE Caveat 484869 - 14 day letter sent 18 Mar 19 |