Extracted from MTO on 12-Jul-2025 00:49,
last changed 26-Jun-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 19-Apr-2013 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 04-Oct-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 19-Apr-2013 | 03-Oct-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 19-Apr-2013 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 19-Apr-2013 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 19-Apr-2013 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 19-Apr-2013 | |
7 | 1 | No exploration activities being carried out on Stock Route Reserve 9701 which restrict the use of the reserve. | 19-Apr-2013 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Crown Reserve 41787. | 19-Apr-2013 | |
9 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 04-Oct-2024 | |
10 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 04-Oct-2024 | |
11 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 04-Oct-2024 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 19-Apr-2013 | |
2 | 2 | All Exploration and prospecting disturbances, excluding supporting infrastructure, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Backfilling and rehabilitation being required no later than 12 months after completion of the activity unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 04-Oct-2024 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 19-Apr-2013 | 03-Oct-2024 |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 19-Apr-2013 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 19-Apr-2013 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 19-Apr-2013 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 19-Apr-2013 | |
7 | 1 | No exploration activities being carried out on Stock Route Reserve 9701 which restrict the use of the reserve. | 19-Apr-2013 | |
8 | 1 | The prior written consent of the Minister responsible for the Mining Act 1978 being obtained before commencing any exploration activities on Crown Reserve 41787. | 19-Apr-2013 | |
9 | 1 | All supporting infrastructure for exploration and prospecting including core yards, laydowns, camps, and access tracks (excluding drill lines), being rehabilitated to the satisfaction of the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. Rehabilitation being required by the earlier of 12 months from the infrastructure being no longer required to support exploration, or 12 months from the relevant programme of work expiring, unless otherwise approved in writing by the Environmental Officer, Department of Energy, Mines, Industry Regulation and Safety. | 04-Oct-2024 | |
10 | 1 | The tenement holder must maintain appropriate records of exploration/prospecting activities, and associated rehabilitation undertaken, in order to demonstrate compliance with all conditions and environmental management and rehabilitation practice commitments. These records to be made available to the Department upon request. | 04-Oct-2024 | |
11 | 1 | All exploration and prospecting operations to comply with the environmental management and rehabilitation practice commitments provided in the approved programme of work. | 04-Oct-2024 | |
Type | Number | Details |
Iron Ore Inclusion | 345537 | Lodged:11:23 27 April 2010RECORDED:11:23 27 April 2010AUTHORISED:00:00 19 April 2013 |
Application to Amend | 395606 | Lodged:15:45 11 March 2013Amending:AddressFrom:FMG PILBARA PTY LTD, C/- TENEMENT ADMINISTRATION SERVICES PTY LTD, LEVEL 2 326 HAY STREET, EAST PERTH, WA, 6004To:FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004RECORDED:15:45 11 March 2013 |
Forfeiture | 495005 | Initiated:27/09/2016 for non-compliance with expenditure conditionsRECORDED:10:00 06 October 2016Notice Issued:Regulation 50 Notice sent 27/09/2016 for non-compliance with expenditure conditions pursuant to Reg 15.Compliance Date:01/11/2016FINALISED:Order by Minister on 03 November 2016 that E 08/2137-I be Penalty Imposed |
Fine | 496498 | Fine in respect to:Forfeiture Process 495005Fine reason:Non-compliance with expenditure obligationsPenalty amount:$3,928.00Notification date:04/11/2016Due date:09/12/2016Pursuant to:Section 96A(5)RECORDED:04 November 2016PAYMENT RECEIVED:14 November 2016FINALISED:14 November 2016Receipt Number:06-157469Amount:$3,928.00Remaining balance:$0.00 |
Extension / Renewal of Term | 527583 | Lodged:14:09:53 10 April 2018Applied For Period:5 YearsRECORDED:14:09:53 10 April 2018GRANTED:19 June 2018Granted Period:5 YearsTerm Extended To:18/04/2023 |
Partial Surrender - Compulsory | 549522 | Lodged:11:24:55 18 March 2019Section:Section 65 (3)Surrendered Blocks:HAMERSLEY RANGE 1608 m, r, w, x
HAMERSLEY RANGE 1680 b, c, g, h, m, n, o, r, s, t, w, x, y
HAMERSLEY RANGE 1751 e, k
HAMERSLEY RANGE 1752 a, b, c, d, f, g, h, j, lSurrendered Total:28 BL.REGISTERED:Midnight 18 April 2019Surrendered area to be released 08:30:00 16/05/2019 under Section 65 (3)Surrendered area released 08:30:00 16/05/2019 under Section 65 (3) |
Application to Amend | 587109 | Lodged:10:26:02 25 September 2020Amending:Address (Including DTC Details)From:Principal Place of Business : FMG PILBARA PTY LTD, SAME AS CORRESPONDENCE and DTC :FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004To:Principal Place of Business : FMG PILBARA PTY LTD, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.au and DTC :FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auRECORDED:10:26:02 25 September 2020 |
Application to Amend | 587934 | Lodged:15:58 08 October 2020Amending:Address (Including DTC Details)From:FMG PILBARA PTY LTD, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auTo:FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auRECORDED:15:58 08 October 2020 |
Partial Surrender - Voluntary | 627295 | Lodged:13:55:11 01 July 2021Surrendered Blocks:HAMERSLEY RANGE 1608 b, c, d, e, g, h, j, k, n, o, p, s, t, u, y, z
HAMERSLEY RANGE 1609 q, v
HAMERSLEY RANGE 1680 d, e, j, k, p, u, z
HAMERSLEY RANGE 1681 a, f, l, m, q, r, v, w
HAMERSLEY RANGE 1753 b, cSurrendered Total:35 BL.REGISTERED:13:55:11 01 July 2021 |
Application to Amend | 670270 | Lodged:08:30 07 March 2023Amending:Address (Including DTC Details)From:FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auTo:FMG PILBARA PTY LTD, SUITE 9, LEVEL 3, 47 HAVELOCK STREET, WEST PERTH, WA, 6005, xxxxx@czrresources.com, xxxxxxx050RECORDED:08:30 07 March 2023 |
Application to Amend | 670272 | Lodged:08:30 07 March 2023Amending:Address (Including DTC Details)From:FMG PILBARA PTY LTD, ACQUISITIONS AND TENEMENTS DEPARTMENT, PO BOX 3379 HAY STREET, EAST PERTH, WA, 6004, xxxxxxxxxxxxxxxxxx@fmgl.com.auTo:FMG PILBARA PTY LTD, CZR RESOURCES LTD, PO BOX 16, WEST PERTH, WA, 6872, xxxxx@czrresources.com, xxxxxxxxx050RECORDED:08:30 07 March 2023 |
Extension / Renewal of Term | 673279 | Lodged:11:42:32 13 April 2023Applied For Period:2 YearsRECORDED:11:42:32 13 April 2023GRANTED:05 July 2023Granted Period:2 YearsTerm Extended To:18/04/2025 |
Caveat | 685655 | Lodged:09:21:13 11 September 2023Caveat Type:Consent CaveatCaveator:FMG PILBARA PTY LTDShares Caveated:100/100 shares ZANTHUS RESOURCES PTY LTDRECORDED:09:21:13 11 September 2023 |
Excess Tonnage | 698005 | Lodged:08:30 06 March 2024RECORDED:08:30 06 March 2024Approved Additional Tonnes:9,000GRANTED:15:30:43 03 May 2024 |
Extension / Renewal of Term | 731447 | Lodged:12:18:34 17 April 2025Applied For Period:2 YearsRECORDED:12:18:34 17 April 2025GRANTED:23 June 2025Granted Period:2 YearsTerm Extended To:18/04/2027 |