Extracted from MTO on 11-Jul-2025 01:13,
last changed 03-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 23-Oct-2009 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 23-Oct-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 23-Oct-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Oct-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 23-Oct-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 23-Oct-2009 | |
7 | 1 | In respect of the area covered by this licence if the Kururma Marthudunera People (being the applicants in Federal Court Application No/s. WC99/012 send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Kurama Marthudunera People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Yamatje Marlpa Aboriginal Corporation. | 23-Oct-2009 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 23-Oct-2009 | |
2 | 1 | All costeans and other disturbances to the surface of the land made as a result of exploration, including drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Industry and Resources (DoIR). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DoIR. | 23-Oct-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 23-Oct-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DoIR is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 23-Oct-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 23-Oct-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 23-Oct-2009 | |
7 | 1 | In respect of the area covered by this licence if the Kururma Marthudunera People (being the applicants in Federal Court Application No/s. WC99/012 send a request by pre-paid post to the licensee's or agent's address, not more than ninety days after the grant of this licence, the licensee shall within thirty days of the request execute in favour of Kurama Marthudunera People the Regional Standard Heritage Agreement (RSHA) endorsed by peak industry groups and the Yamatje Marlpa Aboriginal Corporation. | 23-Oct-2009 | |
Type | Number | Details |
Licence Instrument | 547654 | Lodged:00:00 23 October 2009ISSUED:00:00 23 October 2009 |
Application to Amend | 367539 | Lodged:16:15 11 March 2011Amending:AddressFrom:ZANTHUS RESOURCES PTY LTD, C/- STATEWIDE TENEMENT & ADVISORY SERVICES PTY LTD, PO BOX 8095 PERTH BUSINESS CENTRE, PERTH, WA, 6849To:ZANTHUS RESOURCES PTY LTD, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008RECORDED:16:15 11 March 2011 |
Application to Amend | 413490 | Lodged:14:00 18 December 2012Amending:AddressFrom:ZANTHUS RESOURCES PTY LTD, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008To:ZANTHUS RESOURCES PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947RECORDED:14:00 18 December 2012 |
Extension / Renewal of Term | 456259 | Lodged:15:30 15 October 2014Applied For Period:5 YearsRECORDED:15:30 15 October 2014GRANTED:03 February 2015Granted Period:5 YearsTerm Extended To:22/10/2019 |
Application to Amend | 504259 | Lodged:15:48:42 10 April 2017Amending:Address (Including DTC Details)From:Principal Place of Business : ZANTHUS RESOURCES PTY LTD, SAME AS CORRESPONDENCE and DTC :ZANTHUS RESOURCES PTY LTD, C/- AUSTWIDE MINING TITLE MANAGEMENT PTY LTD, PO BOX 1434, WANGARA, WA, 6947To:Principal Place of Business : ZANTHUS RESOURCES PTY LTD, P.O. BOX Z5183, ST GEORGES TERRACE, PERTH, WA, 6831, xxxxxxxxx@coziron.com, xxxxx099 and DTC :ZANTHUS RESOURCES PTY LTD, P.O. BOX Z5183, ST GEORGES TERRACE, PERTH, WA, 6831, xxxxxxxxx@coziron.com, xxxxx099RECORDED:15:48:42 10 April 2017 |
Forfeiture | 547221 | Initiated:04/02/2019 for non-compliance with expenditure conditionsRECORDED:14:29:11 16 November 2018Notice Issued:Regulation 50 Notice sent 04/02/2019 for non-compliance with expenditure conditions pursuant to Reg 21 & 22.Compliance Date:14/03/2019FINALISED:Order by Minister on 03 April 2019 that E 08/1825-I be Penalty Imposed |
Application to Amend | 544269 | Lodged:16:08 07 December 2018Amending:Address (Including DTC Details)From:ZANF PTY LTD, C/- M & M WALTER CONSULTING, PO BOX 8197, SUBIACO EAST, WA, 6008To:ZANF PTY LTD, ZANF PTY LTD, PO BOX 1492, WEST PERTH, WA, 6872, xxxxxxx@mcreasy.com.au, xxxxxxx100RECORDED:16:08 07 December 2018 |
Fine | 550818 | Fine in respect to:Forfeiture Process 547221Fine reason:Non-compliance with expenditure obligationsPenalty amount:$3,296.00Notification date:03/04/2019Due date:08/05/2019Pursuant to:Section 96A(5)RECORDED:03 April 2019PAYMENT RECEIVED:08 May 2019FINALISED:10 May 2019Receipt Number:10095356Amount:$3,296.00Remaining balance:$0.00 |
Surrender - Outright | 552757 | Lodged:16:02:53 02 May 2019REGISTERED:16:02:53 02 May 2019 |