Extracted from MTO on 10-Jul-2025 00:26,
last changed 01-Jul-2025.
# | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 30-Jun-2009 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 30-Jun-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 30-Jun-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 30-Jun-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 30-Jun-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 30-Jun-2009 | |
| 1 | In respect to the areas of land designated EPA Red Book Recommendation: EPA 9.2 in TENGRAPH, hereinafter referred to as the designated area, the following additional conditions shall apply: | 30-Jun-2009 | |
7 | 1 | Prior to accessing the licence area, the licensee shall consult with the Environmental Officer, DMP, and ensure that where required all vehicles and equipment entering the designated area are washed down to remove soil and plant propagules and adhering to such conditions specified for the prevention of the spread of soil- borne diseases. | 30-Jun-2009 | |
8 | 1 | Prior to any activity involving disturbance to vegetation and soils including:-- exploration access; and/or
- exploration sampling;
the licensee preparing a detailed program for each phase of proposed exploration for written approval of the Director, Environment, DMP.The Director, Environment, DMP to consult with the Regional/District Manager, Department of Environment and Conservation or other government agency (as relevant) prior to approval. This program to describe the environmental impacts and programs for their management and is to include:-- maps and/or aerial photographs showing the proposed locations of all ground activities and disturbances;
- the purpose, specifications and extent of each activity and disturbance;
- descriptions of all vegetation types (in general terms), land forms, and unusual features likely to be disturbed by such proposed disturbances.
- details on proposals that may disturb sensitive terrestrial habitats including any declared rare flora and fauna if applicable;
- procedures to protect the integrity of special ecosystems such as wetland systems, mangal communities and rainforests areas (and/or associated rainforest monitoring sites) if applicable;
- techniques, prescriptions, and timetable for rehabilitation of all proposed disturbances;
- undertaking for corrective measures for failed rehabilitation;
- details of water requirements from within the designated area;
- details of refuse disposal; and
- proposals for instruction and supervision of personnel and contractors in respect to environmental conditions.
| 30-Jun-2009 | |
9 | 1 | Access to and from and the movement of vehicles within the licence area being restricted to ground or seasonal conditions and routes approved under the program or otherwise agreed by the Environmental Officer, DMP. | 30-Jun-2009 | |
10 | 1 | At agreed intervals, not greater than 12 monthly, the licensee providing a brief report to the Director, Environment, DMP outlining the progress of the operation and rehabilitation program and the proposed operations and rehabilitation programs for the next 12 months. | 30-Jun-2009 | |
11 | 1 | Prior to the cessation of the exploration/prospecting activity in the designated area, the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 30-Jun-2009 | |
| 1 | Consent to mine on Ministerial Temporary Reserve 5980H granted. | 30-Jun-2009 | |
Cond # | Ver | Text | Start | End |
1 | 1 | All surface holes drilled for the purpose of exploration are to be capped, filled or otherwise made safe immediately after completion. | 30-Jun-2009 | |
2 | 1 | All disturbances to the surface of the land made as a result of exploration, including costeans, drill pads, grid lines and access tracks, being backfilled and rehabilitated to the satisfaction of the Environmental Officer, Department of Mines and Petroleum (DMP). Backfilling and rehabilitation being required no later than 6 months after excavation unless otherwise approved in writing by the Environmental Officer, DMP. | 30-Jun-2009 | |
3 | 1 | All waste materials, rubbish, plastic sample bags, abandoned equipment and temporary buildings being removed from the mining tenement prior to or at the termination of exploration program. | 30-Jun-2009 | |
4 | 1 | Unless the written approval of the Environmental Officer, DMP is first obtained, the use of drilling rigs, scrapers, graders, bulldozers, backhoes or other mechanised equipment for surface disturbance or the excavation of costeans is prohibited. Following approval, all topsoil being removed ahead of mining operations and separately stockpiled for replacement after backfilling and/or completion of operations. | 30-Jun-2009 | |
5 | 1 | The Licensee notifying the holder of any underlying pastoral or grazing lease by telephone or in person, or by registered post if contact cannot be made, prior to undertaking airborne geophysical surveys or any ground disturbing activities utilising equipment such as scrapers, graders, bulldozers, backhoes, drilling rigs; water carting equipment or other mechanised equipment. | 30-Jun-2009 | |
6 | 1 | The Licensee or transferee, as the case may be, shall within thirty (30) days of receiving written notification of:-- the grant of the Licence; or
- registration of a transfer introducing a new Licensee;
advise, by registered post, the holder of any underlying pastoral or grazing lease details of the grant or transfer. | 30-Jun-2009 | |
| 1 | In respect to the areas of land designated EPA Red Book Recommendation: EPA 9.2 in TENGRAPH, hereinafter referred to as the designated area, the following additional conditions shall apply: | 30-Jun-2009 | |
7 | 1 | Prior to accessing the licence area, the licensee shall consult with the Environmental Officer, DMP, and ensure that where required all vehicles and equipment entering the designated area are washed down to remove soil and plant propagules and adhering to such conditions specified for the prevention of the spread of soil- borne diseases. | 30-Jun-2009 | |
8 | 1 | Prior to any activity involving disturbance to vegetation and soils including:-- exploration access; and/or
- exploration sampling;
the licensee preparing a detailed program for each phase of proposed exploration for written approval of the Director, Environment, DMP.The Director, Environment, DMP to consult with the Regional/District Manager, Department of Environment and Conservation or other government agency (as relevant) prior to approval. This program to describe the environmental impacts and programs for their management and is to include:-- maps and/or aerial photographs showing the proposed locations of all ground activities and disturbances;
- the purpose, specifications and extent of each activity and disturbance;
- descriptions of all vegetation types (in general terms), land forms, and unusual features likely to be disturbed by such proposed disturbances.
- details on proposals that may disturb sensitive terrestrial habitats including any declared rare flora and fauna if applicable;
- procedures to protect the integrity of special ecosystems such as wetland systems, mangal communities and rainforests areas (and/or associated rainforest monitoring sites) if applicable;
- techniques, prescriptions, and timetable for rehabilitation of all proposed disturbances;
- undertaking for corrective measures for failed rehabilitation;
- details of water requirements from within the designated area;
- details of refuse disposal; and
- proposals for instruction and supervision of personnel and contractors in respect to environmental conditions.
| 30-Jun-2009 | |
9 | 1 | Access to and from and the movement of vehicles within the licence area being restricted to ground or seasonal conditions and routes approved under the program or otherwise agreed by the Environmental Officer, DMP. | 30-Jun-2009 | |
10 | 1 | At agreed intervals, not greater than 12 monthly, the licensee providing a brief report to the Director, Environment, DMP outlining the progress of the operation and rehabilitation program and the proposed operations and rehabilitation programs for the next 12 months. | 30-Jun-2009 | |
11 | 1 | Prior to the cessation of the exploration/prospecting activity in the designated area, the licensee notifying the Environmental Officer, DMP and arranging an inspection as required. | 30-Jun-2009 | |
| 1 | Consent to mine on Ministerial Temporary Reserve 5980H granted. | 30-Jun-2009 | |
Type | Number | Details |
Extension of Time | 265142 | Lodged 9.40 am on 24 April 2007 to Lodge SecurityApproved by the Warden on 09 May 2007 |
Extension of Time | 265145 | Lodged 9:40 AM on 24 Apr 2007 to serve Pastoralist.Approved by the Warden on 09 May 2007 |
Application to Amend | 173355 | Lodged 10:11 AM on 29 Aug 2007 amending the holder from: LEAMONTH LIMESTONE PTY LTD- 100/100ths shares to: LEARMONTH LIMESTONE PTY LTD - 100/100ths shares; and amending address to read 'c/- Western Tenement Services, PO Box 428, GREENWOOD LPO, WA 6924'REGISTERED 10:11 AM 29 Aug 2007 |
Extension of Time | 380256 | Lodged:11:39 26 August 2011Type:Form 5RECORDED:11:39 26 August 2011Extension of time until 9 September 2011 to lodge Form 5 for the year ending 29 June 2011APPROVED:09:29:40 31 August 2011 |
Extension / Renewal of Term | 449819 | Lodged:14:36:28 27 June 2014Applied For Period:5 YearsRECORDED:14:36:28 27 June 2014GRANTED:07 August 2014Granted Period:5 YearsTerm Extended To:29/06/2019 |
Application to Amend | 486600 | Lodged:14:40 11 May 2016Amending:Address (Including DTC Details)From:LEARMONTH LIMESTONE PTY LTD, C/- WESTERN TENEMENT SERVICES, PO BOX 428, GREENWOOD LPO, WA, 6924To:LEARMONTH LIMESTONE PTY LTD, C/- WESTERN TENEMENT SERVICES, PO BOX 3285, EAST PERTH, WA, 6892RECORDED:14:40 11 May 2016 |
Extension of Time | 515075 | Lodged:10:48:37 22 September 2017Type:Stat DecRECORDED:10:48:37 22 September 2017APPROVED:09:04:11 28 September 2017Time to lodge extended to 06 Oct 2017 |
Extension of Time | 539591 | Lodged:14:56:15 25 September 2018Type:Stat DecRECORDED:14:56:15 25 September 2018APPROVED:15:26:13 25 September 2018Time to lodge extended to 08/10/2018 |
Surrender - Outright | 557501 | Lodged:16:15:47 28 June 2019REGISTERED:16:15:47 28 June 2019 |